This action was brought to recover the sum of $231,081.59, a balance alleged to be due the plaintiff under a contract for the construction of the new East. River bridge. The defendant claimed the right to deduct from.such balance the sum of $175,000 for 175 days’ alleged overtime in the completion of the work. The contract under which the work was done provided that whenever, in the opinion of the engineer-having supervision of the work for the city, the other party to the contract shall have “ completely performed,” then the .engineer should so certify in writing to the commissioners and “ on the expiration of thirty days after the acceptance by said Commissioners of the work * * the said Commissioners will direct to be paid to the said party of the second part, in cash, the amount remaining ” due. The work was completed and the bridge accepted by the city on the 15th of November, 1902, but the final certificate was not given until the 30th- of July, 1903. It was demanded, however, immediately upon completion of the work but the engineer refused to give a certificate other than one which would show that the contractor had not performed the work on time; in
The issued raised by the pleadings were sent to ,a referee to hear and determine, who found for the- plaintiff in the full amount claimed, together with interest thereon from December 15, 1902 — that is, thirty days after the completion and acceptance of the work. Judgment was entered upon the referee’s report and the defendant now appeals from so much thereof as allowed interest on the sum recovered froin December 15,1902—claiming that, interest could only be recovered on such sum from the 23d of August, 1903 — that is, thirty days after the claim was filed with the comptroller.
The city’s contention in this respect is . based upon the provision of section '261 of' the Greater New York charter (Laws of 1901, chap. 466), that “No action or special proceeding, for- any cause whatever, shall be prosecuted or maintained against. The Oity of New York,, unless it shall appear by and as an allegation in the complaint or -necessary moving papers, that at least thirty days have .elapsed since the demand, claim or claims upon which such action or special proceeding is founded, were presented to the comptroller of said city for adjustment and that lie has neglected or refused to make an adjustment or payment thereof for thirty days after such presentment.” I am unable to see the force of this contention'. The section of the charter quoted has no application to the question here presented. It simply requires that as a basis for the maintenance of an action or special proceeding a claim' shall be filed at least thirty days before the action is commenced or the special proceeding instituted. • It does not state in terms, nor can it be implied 'from the facts here presented; that interest cannot: be recovered on the claim made, if stieh claim be subsequently established. Here the. cause of action against the city arose out of the-
The plaintiff was entitled to a certificate when the work was completed and the bridge accepted by the city, and by express terms the .contract provided that “on the expiration of thirty days after the acceptance by said Commissioners,’’ payment would be made. The legal obligation, therefore, rested upon the city (plaintiff having fully performed the contract and the work having been accepted) to pay the stipulated price within the stipulated time. If the contention of the city be correct, then it could, by the engineer’s withholding his final certificate, deprive the plaintiff of interest ón the amount to which it was entitled, even though the validity of its claim were conceded. The plaintiff, as already said, was entitled to the final certificate on the 15th of November, 1902, and it then demanded the same. The engineer refused to give it until the 23d of July, 1903. This was a wrongful and unlawful act upon his part. The judgment so determined and the city conceded it by not appealing. The engineer, in giving or withholding the certificate represented the city, and his act must be charged to it. The plaintiff cannot, 'by the wrongful act of the engineer, be deprived of the interest to which it would otherwise be legally entitled.
The judgment awarded interest from the 15th of December, 1902, that is, thirty days after the demand for the certificate w-as made and thirty days after it was legally entitled to receive such certificate.
I think the judgment is right and should be affirmed, with costs.
O’Brien, P. J., Patterson, Laughlin and Houghton, JJ., concurred.
Judgment affirmed, with costs.