The city of New York, for the purpose of sewering its twenty-third and twenty-fourth wards, or a portion thereof, provided for the construction of a system of sewers, to consist of a main branch and several lateral sewers emptying into it,, all of which .were delineated on a map or plan. After the map had been filed the city advertised for bids for the construction of the main sewer, extending in the West Farms road from Edgewater road to Boston road, and in
The plaintiff fully performed his contract and was paid therefor upwards of $300,000. Subsequently he commenced this action to recover damages amounting to between $29,000 and $30,000, alleged to have been sustained by him by ’reason of the act of the- city in permitting water1 to flow upon his work from the lateral sewers, which were constructed prior to the completion of his contract.^
- The answer put in issue the material allegations of the complaint upon which the right to recover, was predicated.
. At the trial it appeared that subsequent to the execution, of the plaintiff’s contract the city entered into other contracts tor the construction of six lateral sewers ; that they were constructed prior to the completion of plaintiff’s work, and that water did, in fact, flow therefrom upon-plaintiff’s work,'or percolate, through the adjacent soil, causing him damage. The trial court, however, at the conclusion of the plaintiff’s case, concluded this did not entitle him to recover under the terms of his contract,-and dismissed the cotnplaint, directing the exceptions taken thereto to be heard in the first instance at the Appellate Division.
I am of the opinion the complaint was properly dismissed. The plaintiff’s work was but a part of the work adopted by the city for the construction -of a system Of sewers, and that other contracts Were to, be let was clearly contemplated and provision made therefor in case such other contracts should be completed prior -to the work which plaintiff contracted to do and perform..' The sewer1 which plaintiff was to construct was. the trunk line; ; The other1 'sewers were'merely branches, or subsidiary to, and must of necessity" flow into it. They could-not flow elsewhere, and this the plaintiff knew, and for that reason the contract specifically provided that the city was not to be liable for damages resulting to ¡the plaintiff from the watei; which flowed in or upon the work which he contracted to perform. 1 The plaintiff had notice that contracts for the construction of the lateral sewers were to be made and that connections from them, when made, -would be with the sewer which he agreed to build-. He knew that "water "would flow through such sewers when constructed. He also knew that if water did flow
The case in this respect cannot be distinguished from Kelly v. City of New York (106 App. Div. 576), where this court held that by the express terms of the 'contract then under consideration, the city was not liable for damages resulting from water which flowed into a trench which plaintiffs contracted to build.
It seems to me clear that the acts of which plaintiff now complains, and which he alleges caused him damage, were not due to any act of omission or commission on the part of the city, but were the
direct consequence of the performance of his work, and for which he had specifically stipulated.
In addition to the foregoing, it would seem if the plaintiff had performed his contract within the stipulated time his work would have been completed before the construction of the lateral sewers, in which event no damage would have been sustained by him. .
I am of the opinion, therefore, that the' exceptions are not well taken, for which reason the same should be overruled and the motion for a new trial denied, with costs. ■
Patterson, P. J., • Ingraham, Claree and. Houghton, JJ., concurred.
■ Exceptions overruled and motion for new trial denied. • Settle order on notice.