Tn July, 1893, the plaintiff’s assignor, one Mahoney, entered into two contracts with the city of Yew York for “ Regulating and Paving with Macadam- Pavement ”. the roadway of Eleventh avenue from Kingsbridgé road to Fort George road and the roadway of Fort George avenue from Amsterdam to Eleventh avenue, respectively.
' There seems to be no question but that if the contracts for “ regulating and grading ” these streets had been actually performed as therein required, then the performance of the contracts in question would not have necessitated the removal of any rock, except possibly for three inches along the gutters and such slight projections of rock as might be found in other places. When Mahoney commenced work under his contracts, however, he found, upon - removing the soft filling on the surface of the streets, that the rock had in fact been removed to a depth of only about a foot below the curb, instead of two feet, as required by the contracts and he immediately protested that he was not bound, under his contracts, to remove the rock which should have been removed under the contracts for the grading of the streets; but the city authorities having supervision of the work insisted that the rock must be removed by the plaintiff before the streets were paved. In order to fulfill his contracts, therefore, he and the plaintiff, to whom he assigned the contracts while the work was in progress, were obliged to excavate and remove about a foot of rock beneath all the pavement laid.
After completing the contracts, plaintiff brought two actions to recover the cost of removing this rock. Upon the trial they were consolidated and the jury rendered a verdict in favor of the plaintiff for $37,485, the only question submitted to them being the amount of the extra or additional work done and its value. From the judgment entered thereon and an order denying a motion for a new trial defendant appeals.
It is not seriously disputed but what both parties to the contracts,
The words quoted are quite applicable to the facts in the present case, except that this plaintiff, if anything, occupies a more favorable position. An examination of the streets indicated that they had been graded. The contracts for such grading were on file in the comptroller’s office as public records with the certificates showing that the work had been fully performed, and for which the contractors had been paid in full. The plaintiff’s assignor, before making his estimates, personally ascertained both of these facts. Under his contract he had the right to select his'own method of ascertaining the actual work to be doné and he adopted this method. If the plaintiff in the Ilorgan case was justified in assuming from the mere existence of the outlet pipe that the lake could be substantially drained through it, it seems to me more clear that the plaintiff’s assignor was justified in assuming that the rock had been removed for two' feet below the curb line. The contracts for the grading required it to be removed to that extent"and the public records of the city showed the contracts had been fully performed. 'The contract in the Iiorgan case-required the contractor to pump out the water from the lake, but this was held to mean simply the water that might remain in the lake owing to the irregularities in the bottom, which could not be carried off through the drainage pipe. So, in the present case, while the contract provided for the excavation of rock, it seems to me this had reference to such rock as might be found above the two feet subgrade, owing to irregularities in its surface, or rock for three inches along the gutters. This was all the parties had in mind when the con-tracts were entered. into. It was not then contemplated by either of them that the plaintiff’s assignor would have to remove at least a foot of rock which then supposedly had been removed under the grading contracts. This was a subject on which their minds did
I am of the opinion that the plaintiff was entitled to recover for this additional work, and since its performance was not controverted the only, questions for the jury, as the trial court held, were the amount of such work and its value.
Objection is made to the form of the complaints, but, they allege facts sufficient to sustain the recovery. It is not necessary to determine the exact form of the action, because it does not appear that the question was properly raised Upon the trial, or that the defendant was misled or prejudiced in any way oil that account. Neither were there any errors committed calling for reversal. .
The judgment and order appealed from • must, therefore, be affirmed, with costs.
Miller and Dowling, JJ., concurred; Ingraham, 'P. J.,-and . Laughlin, J., dissented.