Kingsway Construction Co. v. Metropolitan Life Insurance

Hotchkiss, J.:

The action is to recover damages because of defendant’s failure to complete a building loan.

On February 19, 1909, before plaintiff corporation was organized and before it had taken title to the premises in question, one Rae Grinsberg, the wife of Samuel, and who the promoters of the plaintiff proposed should eventually become its president, acting in plaintiff’s behalf, applied in writing to the defendant for the loan. The application was in substance as follows: The undersigned desires to procure a Loan of $180,000 at 6 and 5% per cent interest per annum, for the term of 5 years * * * on the bond of Kingsway Construction Co. secured by First Mortgage on the property described as follows:” here *386follows a description of the premises and the dimensions, number of stories, building material and proposed use of the improvement to be placed thereon; the owner’s estimated value of the land and of the buildings to be erected and their anticipated annual rent; the periods of construction when payments on account of the loan were desired; and that “fire insurance to cover ” would be placed in companies designated by the defendant and written through its authorized agent. The application stated that it was made “ expressly subject to the approval of the applicant’s title ” by the defendant’s attorneys, and in response to a requirement contained on the printed blank on which the application was made, plaintiff submitted the names of two individuals as references to its pecuniary responsibility as bondsmen.

On March eleventh Stabler, defendant’s comptroller, wrote to plaintiff, saying:

“Subject to the approval of title by our attorneys and subject also to the approval of plans and specifications still to be submitted our finance committee has authorized a loan of $180,000 to be made to you on premises * * *. Interest to be at 6% for two years from April 1, 1909, and for three years longer. We are to receive the collateral bonds of [Mrs.] Rae Ginsberg and others interested in the company, guaranteeing to us the completion of the building. The improvement is to consist of a six-story elevator apartment house with stores on the avenue, and is to be built according to plans and specifications still to be submitted, and to be enclosed by Aug. 1, 1909, and completed by Jan. 1, 1910. Fire insurance to the amount of $160,000 is to be placed through our brokers, Messrs. Dutcher & Bdmister, 58 William St., as the building progresses.
“An architect’s fee of $450 is to be paid to our Architect, Mr. D. E. Waid, out of the first advance for his services. Please arrange with our attorneys, Messrs. Ritch, Woodford, Bovee & Butcher, 18 Wall St., for the examination of title and preparation of papers. Please also arrange with Mr. Waid for a schedule of payments.”

On March sixteenth Stabler wrote Rae Ginsberg that before defendant went any further with the matter of the loan it *387would be necessary for defendant to have satisfactory references as to plaintiff’s responsibility. On March twenty-fifth he again wrote to the same effect. In the meantime under date of March twentieth a provisional schedule of proposed payments had been prepared by Waid with the approval of Samuel Grinsberg, who conducted all negotiations in plaintiff’s behalf. On March thirty-first Waid wrote plaintiff that by the terms of the proposed loan agreement, it was the right of the defendant’s architect to inspect all foundation trenches before any cement was put in and that he must be notified when each trench was completely open and before any cement work was done. The letter also said: “Will you kindly have sent me at your earliest convenience the complete revised specifications and general floor plans and elevations and framing plans, also the foundation details. * * * I strongly advise that you submit preliminary designs, both plans and elevations, before working drawings are made, in order that delays may be obviated in the event that the Metropolitan Life Insurance Company has any objections to any features of the same.” In another paragraph of the letter it was said: “Please note paragraph c E ’ on page six of the loan contract, particularly with reference to erection of stairs,” etc. The words “loan contract ” undoubtedly referred to the printed form of contract commonly used by defendant in making its building loans. Attached to the letter were a number of “specifications” which Waid referred to as proposed to be contained in the formal contract of loan, and concerning which he requested that plaintiff’s architect should consult with him in case plaintiff desired any changes.

On April third the defendant’s attorneys notified plaintiff that they had received the approved application; that the examination of title had been referred to them, and that plaintiff should see them with regard to the business.

On March thirtieth plaintiff started to excavate for its proposed building, and between that date and April third Samuel Grinsberg submitted to Waid plaintiff’s proposed plans but no specifications. On the latter date Waid wrote plaintiff that certain changes in these plans would have to be made before he could recommend their acceptance. Samuel thereafter con*388ferred with Waid concerning his objections, and Samuel swears that he agreed to make all changes requested by Waid, none of which, he claims, would have delayed construction or necessitated new plans. Defendant’s evidence, however, was to the effect that Waid insisted upon new plans in substitution for at least a portion of the plans presented. No further plans, however, were ever furnished, and the plaintiff continued work on the foundations.

On April ninth Waid wrote plaintiff that an inspector had found that concrete was being loaded on a bed of sand on the face of a rock; that all work so done must be taken out to allow an inspection of the bottom; that no more work should he done until the necessary plans had been approved; and also that no cement should be laid until the bottom of the trenches had been inspected. Plaintiff nevertheless continued its work and on April thirteenth was notified by defendant that it would proceed no further with the loan.

The court charged the jury that defendant’s letter of March eleventh constituted as matter of law an acceptance of the loan and a complete contract between the parties except so far as the approval of plans were concerned, and it was left to the jury to determine whether what had occurred between Samuel Ginsberg and Waid constituted an approval of plans on defendant’s part. The important matter of specifications seems to have been lost sight of. The jury was also charged that plaintiff was entitled to a reasonable opportunity to prepare plans for approval, and that if they found that Waid had acted in bad faith and had refused to approve plans offered by plaintiff for the purpose of enabling the defendant to escape from its contract, plaintiff was in such event excused from procuring defendant’s approval of the plans.

It is apparent that the theory on which the case was submitted to the jury was radically wrong. As for the good faith of defendant’s architect, Waid, I can discover nothing in the evidence justifying- the injection of any such question into the case. But the vice of the charge lay principally in the treatment of defendant’s letter of March eleventh. This partook more of the nature of a counter proposition than it did of an acceptance of plaintiff’s application for the loan. It contained *389a number of essential details not covered by the application. The indefinite statement in the application concerning the period during which the respective rates of interest were to be paid was made fixed and positive; collateral bonds for the completion of the building were required to be given by Eae Ginsberg and others interested in the plaintiff; the proposed buildings were to contain elevators and were to be built according not only to plans but to specifications thereafter to be approved by the defendant; a schedule of payments to be made on account of the loan was to be arranged with defendant’s architect; the buildings were to be inclosed by August 1,1909, and completed by January 1, 1910; the amount of fire insurance was definitely fixed; the plaintiff was required to pay defendant’s architect’s fees out of the first moneys it should receive; defendant’s attorneys were to prepare the “papers” which should formally evidence the contract of the parties. It is evident that, anticipating the execution of these papers and for the evident purpose of accommodating themselves to plaintiff’s convenience and facilitating the preliminaries necessary for the expression in writing of the completed agreement, some of defendant’s representatives attempted to work out with plaintiff some details, but there is nothing to show that the defendant ever abandoned the essential requirements of its letter of March eleventh, or that it ever released plaintiff from compliance therewith. There was no attempt on plaintiff’s part to show any substantial performance of these requirements. No representative of it ever conferred with defendant’s attorneys with respect to the preparation of any formal loan agreement or in the matter of the title; no guarantors of the completion of the building were ever furnished, nor were two satisfactory references as to plaintiff’s responsibility as a bondsman given; in short, plaintiff was not shown to have even orally accepted, much less to have complied with, the material conditions under which defendant was willing to make the loan. It is perfectly plain that by the letter of March eleventh defendant expected and required that the contract for the loan should be reduced to writing; and so far as the plaintiff is concerned, it may be said, as was said of the plaintiff in Brauer v. Oceanic Steam Navigation Co. (77 *390App. Div. 407, 411): “It is simply impossible to believe that he ever supposed that a contract of such a character, with so much detail, with so many matters to be covered fixing rights and obligations and liabilities, was simply to be left in the ah.” The case presented by this record is entirely different from the class of cases illustrated by Sanders v. Pottlitzer Bros. Fruit Co. (144 N. Y. 209).

The judgment and order should be reversed, with costs, and the complaint dismissed, with costs.

Ingraham, P. J., Laughlin, Scott and Dowling, JJ., concurred.

Judgment and order reversed, with costs, and complaint dismissed, with costs.

See Penal Law, § 664, subd. 5.— [Rep.