The action arises out of a contract dated August 3, 1916, made by the plaintiffs with the city of New York acting by the Public Service Commission for the construction of part of what is known as route 61, a part of the Broadway-Fourth Avenue Rapid Transit railroad.
The contract provided that the work to be done thereunder was to be completed on or before the 3d day of February, 1919, for the agreed sum of $4,194,797. The complaint is most voluminous. To a large extent it consists of evidentiary matter
The alleged facts set forth in the three causes of action, which are attacked by the demurrer, are identical in substance and differ merely in respect of the measure of damages.
The action was commenced on February 3, 1920. The complaint was served on February 26, 1921. The complaint so far as it relates to the three causes of action under review alleges that at the time of the execution of the plaintiffs’ contract “ and continuously until June, 1918, and for a long period thereafter, there were twenty-eight (28) subway contracts ” outstanding and in the process of performance held by different contractors, and that the total amount agreed to be paid by the city under all of these contracts amounted to approximately $65,000,000, and. that in June, 1918, there remained undone and unperformed under these contracts work and materials aggregating at contract prices the sum of approximately $19,000,000.
It is alleged that at the times mentioned in the complaint the various subway contractors were associated together under a corporation known as the General Contractors Association, which acted for the plaintiff and the other contractors and in their behalf entered into collective agreements presumably with labor unions interested in subway construction for the purpose of safeguarding the contractors with respect to the wages to be paid for labor until the completion of the contracts.
It is further alleged that, despite these precautions taken by the contractors, “ certain classes of the workmen ” of the plaintiffs as well as of the other contractors demanded an increase in the wages over the then prevailing rate; that conferences were thereafter had not only with the workmen and the contractors, but with the chairman of the Public Service Commission, who advised the contractors to yield to the labor demands, as a result of which the workmen agreed to accept certain formulated increases in wages to be operative as to some of them during the year 1917 and as to others during 1917 and 1918; that these agreements were violated by the workmen in February, 1917; that conferences were again called; that the Public Service Commission insisted “ that the subway work must not be interrupted and that to .prevent its interruption the said last increase in the scale of wages demanded by said workmen should and must be granted and paid by plaintiffs and said other contractors, respectively, for the future in order to avert a strike, * * * and that there was a way and a way would be found on the part of the defendant and said Commission
It is further alleged that the defendant thereafter refused to carry out its agreement and that plaintiffs and the other contractors thereupon notified their workmen and the board of estimate and the Public Service Commission that it would not continue to pay said increased wages because of defendant’s failure to carry out its agreement and thatuntil said defendant should make and give plaintiffs and said other contractors, respectively, an enforceable and binding agreement, promise or assurance in substance and to the effect as stated and provided in said understanding or agreement, or to put chapter 586 of the Laws of 1918,
It is further alleged that thereupon said board of estimate and apportionment and the Public Service Commission agreed that the “ defendant would pay and reimburse plaintiffs and said other contractors, respectively, in addition to its and their respective contract prices, the amount or amounts of such increased wages and also the amount or amounts of the increased cost of labor and materials due to the war, from and after April 6, 1917, * * * and that if and insofar as it was or might become necessary to enable defendant to carry out and perform said agreement on its part, said Board and said Commission would cancel and place said contracts under the operation of said Lockwood Law, or modify or supplement the same, so that plaintiffs and said other contractors, respectively, would in such event have -the full benefit of the relief it contemplated,” and that the defendant also agreed to settle and pay all legal claims for damages “ for breaches of contract, faults and defaults on the part of the defendant occurring prior to April 6, 1917, or thereafter up to June 15, 1918, and which still existed unsettled in favor of the plaintiffs or said other contractors, respectively, for the purpose of further aiding them and of financing their contracts; ” that thereafter the strike was terminated and work resumed on plaintiffs’ contract as well as on the other contracts and that “ the promisés, agreement and assurances by defendant hereinbefore set. forth, to pay plaintiffs said increased cost and damages, were intended to and did modify or supplement plaintiffs’ said construction contract.”
The complaint also specifically alleges that at a session of the New York State Legislature in 1918, “ the said Public Service Com
It is also alleged that the defendant and board of estimate and apportionment and the Public Service Commission and Rapid Transit Construction Commissioner “ failed, neglected and refused to place in operation said Lockwood Law as regards plaintiffs’ contract or as regards any of said other contracts, although repeatedly requested by plaintiffs and said other contractors, respectively, and although they offered and stood ready to comply with each and every stipulation and requirement of said law on their part essential to enable defendant to do so.”
Upon the foregoing alleged facts the plaintiffs ask damages in amounts aggregating $755,084.61 in the fourth cause of action; $372,608.43 in the fifth cause of action and $688,127.96 in the sixth cause of action.
The contract for the subway construction between the parties provides that time is of the essence of the contract and that the contractor shall complete all work covered by his contract within thirty months of its delivery. It also provides for per diem liquidated damages in the event of delay in completion of the contract, subject, however, to the provision that if the delay is occasioned by any labor strikes for which the contractor is not responsible, the Public Service Commission may extend the time for completion by the amount of the time of such delay as the Commission shall determine the contractor was subjected to by reason of the strike.
In this connection it might be well briefly to refer to the legislative enactments which were apparently designed to give relief to those who were engaged in performing public contracts during the period of the war.
The first of these acts is known as the Walters Law, being chapter 585 of the Laws of 1918. That act related to contracts for the construction of public works generally.
On the same day that chapter 585 was enacted, chapter 586 was also enacted. That act related to the “ completion of the construction of essential rapid transit lines in a time of war, and the powers of the Public Service Commission for the First District, with the concurrence of the board of estimate and
The third act, known as the Lusk Act, was an amendment of chapter 585 of the Laws of 1918 and was passed on May 13, 1921, while the instant action was pending, and is chapter 711 of the Laws of 1921.
The plaintiffs insist that regardless of the relief available to them under the legislation above mentioned the causes of action demurred to are all sufficient to entitle them to the damages which they seek. In my opinion the allegations relating to these causes of action read in their entirety show that there was no enforcible agreement made by the defendant modifying the original contract between the parties. The facts alleged merely indicate that members of. the board of estimate and apportionment and of the Public Service Commission were sympathetic to the demands of the contractors engaged in subway construction; that they advised with them and promised to assist them in securing legislation which would permit the contractors to receive compensation additional to that fixed by the original contracts and indeed it is alleged as matter of fact that they actively participated in advocacy of the. remedial legislation which was subsequently enacted.
What steps, if any, plaintiffs actually took to secure the benefits of the remedial legislation mentioned does not appear. There is a general allegation that the defendant, the board of estimate and apportionment and the Public Service Commission “ failed, neglected and refused to place in operation said Lockwood Law as regards plaintiffs’ contract,” but in what respects they refused to put into operation or effect the Lockwood Law is not made apparent. t
It is obvious too from what has been stated that if the position of the plaintiffs be correct the effect of the alleged promises of the Public Service Commission and the board of estimate and apportionment would be to increase the prices fixed under the original contracts for the various subway contracts by many millions of dollars, without even the formality of a written agreement to show that the city had consented to modify the original contracts by providing additional compensation to the plaintiffs and the other contractors beyond that prescribed by the contracts so as fully to reimburse them by reason of the unexpected increase in wages and cost of materials which had taken place after the making of the contracts.
At the outset it is to be borne in mind that the making of a subway contract is strictly controlled by the Rapid Transit Act and the complaint is barren of any allegations showing that the Public Service Commission as a board or the board of estimate and apportionment as a legal body had taken any action for the modification of the original contract in the respects claimed by the plaintiffs. It is probably needless to say that such a modification of the agreement as is here claimed was not authorized under any of the provisions of the original contract, or the Rapid Transit Act. It is to be presumed that the contractor took his chances as to the conditions that might arise after the making of the contract in the matter of an increase in wages or costs of material.
A recovery may not be predicated upon a moral consideration. (Gordon v. State of New York, 233 N. Y. 1.)
It is claimed by plaintiffs that a new consideration was created by then abandonment of the right to withdraw from performance of the contract by reason of defendant’s alleged breaches of its contract with plaintiffs, citing De Cicco v. Schweizer (221 N. Y. 431). But as the learned counsel for the appellant points out in his brief the promise in that case was by a third party to induce the parties to perform their contracts and he incidentally aptly quotes from the opinion where the court stated (at p. 433): “ There is a general acceptance of the proposition that where A is under a contract with B, a promise made by one to the other to induce performance is void.’11
Moreover, it appears here that plaintiffs continued to perform the contract after the defendant’s alleged breaches had occurred. They must, therefore, be deemed to have waived the breaches. (Leahy v. Lucius Engineering Co., 186 App. Div. 354, 357; affd., sub nom. Leahy v. Fairlie, 227 N. Y. 660.)
The plaintiffs argue that they were under no obligation to prevent strikes and that their settlement of the strike by paying-
I am of the opinion that the obligation rested upon the plaintiffs to make all lawful efforts to prevent strikes and to make all reasonable efforts to end them. The strike in question was limited to' the matter of higher wages and no other issue was involved. It was incumbent upon the plaintiffs to secure workmen at such wages as were obtainable under then existing conditions. Besides, from a reading in their entirety of all the allegations in the causes of action under review, in connection with the allegations which refer to the strike, it is quite apparent that at that time there was a shortage of labor and a largely increased wage rate. If the work could only be resumed by paying the increased wages, it was obligatory upon the plaintiffs to pay such increased wages and a promise on the part of any officials of the board of estimate and apportionment or of the Public Service Commission to pay additional compensation to insure the plaintiffs’ performance of their contracts was nudum pactum.
If there was no legal consideration which will uphold the alleged modified agreements, it follows that there can be no recovery thereon under common-law rules or under the legislative relief enactments, since they would be violative of section 28 of article 3 of the State Constitution which reads as follows: “ The Legislature shall not, nor shall the common council of any city, nor any board of supervisors, grant any extra compensation to any public officer, servant, agent or contractor.” (Matter of Mahon v. Board of Education, 171 N. Y. 263; Stemmler v. Mayor, etc., 179 id. 473; Gordon v. State of New York, 233 id. 1.)
It is now only necessary to consider the effect of section 28 of article 3 on the legislative enactment known as the Lusk Law (i. e., chapter 711 of the Laws of 1921).
That act provides in substance with respect to contracts for the construction of public works made prior to April 6, 1917, other than a war contract as therein referred to, which have been proceeded with or completed during the period of the state of war between the United States of America and the Imperial German Government, at an increased cost due to the existence of a state of war, that “ any damage, loss or expense, which a court of competent jurisdiction may find to have been occasioned by increased cost in the performance of the work under such contract resulting from or due to the existence of a state of war * * * is hereby declared to be and is made a valid and legal claim against and an obligation of the State, county, municipality or political division of the State of New York with or for which said contract was made.”
“ The Appellate Division in the opinion there delivered said that the Legislature in the enactment of the statute of 1919 recognized claims of the character of the one in the instant case as founded in equity and justice and the claim is not only a moral obligation against the State but a legal claim as well. Liability of the State based upon equity and justice and by reason of a moral obligation has been frequently urged in this court and thus far claimant has succeeded by reason of the application of such terms. Equity and justice recognize the inviolability of contracts, protect and enforce the rights of parties thereunder, inhibit an unlawful abrogation of the same, award damages arising from a
“ The State did not undertake to indemnify claimant against loss upon his contract. On the contrary, it required him to give a bond for a strict compliance on his part with the terms of the same. War conditions and the increased cost of labor and materials or scarcity of labor were not precipitated by the State or due to any act upon its part. So far as the record discloses, the State performed every obligation resting upon it under the contract. The contract between the claimant and the State was purely a business transaction akin to contracts between individuals. Undoubtedly claimant anticipated a profit would result from his contract. If disappointed and a loss resulted, he assumed the risk of such loss and to bear the same. A contribution to him and other contractors similarly situated by the taxpayers of the State under the statute of 1919 or in whatever form framed would operate as a dispensation of charity.”
It thus follows that it is unnecessary to consider any of the other legal points raised in this case.
The order appealed from should be reversed, with ten dollars costs and disbursements, and the demurrers to the fourth, fifth and sixth causes of action sustained, with ten dollars costs.
Clarke, P. J., and Mbrrell, J., concur; Page and Smith, JJ., dissent.