Appeal by plaintiff, The People of the State of New York, from a judgment entered on a jury’s verdict of no cause of action. The action was commenced by the State to recover damages claimed to have arisen through the abandonment by defendant C. & W. Construction Co., Inc., of a contract to construct the Drink Hall at Saratoga Springs. The construction company claims that a balance is due it from the State. However, under our statutes it may not counterclaim therefor in the action brought by the State, but must seek its remedy in the Court of Claims. Thus, in reviewing this judgment, we may only consider the right of the State to recover.
Two issues were litigated: Whether the defendant contractor was justified in abandoning the work on or about October 31, 1934; and whether or not the cost of completing the contract thereafter exceeded the unpaid balance in the hands of the State.
The contract was readvertised and relet to Louis Keil for $175,300. The State admitted that there was $110,424.64 uncertified balance under the C. & W. contract; and computed total expenditures in completing the work, including the amount paid under the Keil contract, at $190,569.78, and sought judgment against the defendant for $80,145.14.
The State now claims error in connection with the rule as to the measure of damages adopted by the court. The complaint was framed upon the theory that the amount paid under the Keil contract, together with extras for heating, etc., was the proper measure. By an amendment this was changed to a demand for the fair and reasonable value of the labor and material necessary for the completion of the C. & W. Construction Co. contract. The Keil contract price and the items of labor performed and material furnished thereunder were proven as bearing on fair and reasonable value. The rule as charged by the court, to which no exception was taken, appears from the following excerpt: “ Now was that Keil contract reasonable under the circumstances or was
No good purpose would be served by a discussion of the claims made by the respective parties, item by item. The record and printed exhibits are in two volumes with a total of nearly 1,200 pages. There is no error of law which requires reversal and there is evidence to sustain the verdict.
The judgment should be affirmed, with costs.
Hill, P. J., Rhodes, McNamee, Bliss and Heffernan, JJ.., concur.
Judgment affirmed, with costs.