Bethlehem Steel Co. v. Turner Construction Co.

Dore, J.

(dissenting in part). While Bethlehem’s interpretation of the words in question may prevail after a trial, I think the words themselves are not necessarily capable of only one meaning and that the precise meaning Bethlehem claims; and, therefore, their application and meaning so far as the steel price is concerned should be finally determined only after a plenary trial in which all the surrounding circumstances may be shown so as to reveal the real intention of the parties at the time.

*72Mutual through its officer, Hughes, alleged that he negotiated with Bethlehem the prices and the conditions on which Bethlehem was to be paid. He specifically states that the negotiations were conducted by him and another with Paul Mackall, vice-president, and C. E. Simmons, contracting manager of Bethlehem; that Bethlehem delivered the “ proposal ” to him on June 28,1948; and that, after discussion, a “ verbal ” agreement was reached in which Bethlehem agreed to provide the structural steel at a price of $182 a ton subject to escalation up to $15 per ton. No reply affidavit is furnished by plaintiff or any of its named officers. On this aspect of the appeal, plaintiff is relying on what amounts to a technicality, namely, that no formal written contract between Mutual and Bethlehem was made. Although it was drawn up, it was not formally signed between Mutual and Bethlehem; and the so-called proposal ” of June 28, 1948, containing the identical price adjustment clause as in the Turner-B ethlehem contract was never actually accepted in writing. But of course there was an agreement between Mutual and Bethlehem as well as between Turner and Bethlehem. Turner was not to pay a dollar under the contract between it and Bethlehem; Turner was to receive a fixed price as general contractor; and all payments were to be made and were made by Mutual. It is therefore unbelievable that Mutual had not agreed with Bethlehem and with Turner before the Turner-B ethlehem contract was made concerning the escalation clause and the price. This is made conclusive by plaintiff’s failure to produce affidavits by its named officers that no such agreement was made.

But on Mutual’s own construction of the dispute as to the price escalation clause in question, the items based upon changes in labor rates, freight rates and prices of material purchased by Bethlehem from others for use in performance of the contract, are due to plaintiff. The parties should be able in the interest of avoiding unnecessary litigation reasonably to agree on what the total is of these items. But if they cannot or will not, I recommend that the order should direct an assessment as to these items and the entry of judgment in favor of plaintiff of the total amount found to be due thereon.

Special Term in its opinion erroneously and prematurely held to be excluded at any trial evidence with regard to similar price adjustment clauses in other similar contracts. On the trial such evidence may be relevant as indicating an accepted practice and understanding in the trade as to such price adjustment clauses.

*73Accordingly, I dissent in part and vote to modify the order appealed from so as to grant plaintiff partial summary judgment based on changes in labor and freight rates and in prices of material purchased by Bethlehem from others and to otherwise deny summary judgment; and as so modified, I vote to affirm the order appealed from.

Peck, P. J., Cohn, Breitel and Bastow, JJ., concur, in Per Curiam opinion; Dore, J., dissents in part, in opinion.

Order reversed, with $20 costs and disbursements to the appellant, the motion granted and an assessment of the amount due plaintiff directed.