Cody v. White

Freedman, J.

Upon the evidence which I find entitled to be believed, I find that the work .of excavating the area on Oolumbus avenue and Eightieth street was part of the original contract, and that the plaintiffs were paid all they were entitled to under the terms of the original contract. Ho deduction was made for not completing in time or for not having excavated the cellar to a uniform depth of ten feet. The question was adjusted between the parties so far as the original contract was concerned, and the defendant cannot now recover back anything on account of imperfect performance in the respects mentioned. I also find that the building of the retaining wall was not part of the original contract, and that the defendant did not request the plaintiffs to build the same or agree with them that they should build it, but that the defendant procured an Italian to build the same and paid him for it. This leaves only the item of the digging of the trench for the sewer connection, which is conceded to have been extra work of the value of $200. This work was completed in August, 1898, and the lien was not filed until April 27, 1899, which was too late, if the extra work was to be -considered the result of an independent contract.. The original contract, however, provides that any addition or omission shall be added to or deducted from it and become part of the original contract. The question then arises when the original contract was completed. There is a conflict of evidence upon this point, which should be determined in favor of the contention of the defendant, namely, that it was completed by September 1, 1898. But independently of that it certainly must be held to have been fully completed at the time when the differences arising under it were adjusted between the parties and the plaintiffs received the balance found due to them thereunder. This was some time in August or September, 1898. In either aspect, therefore, the Hen was filed too late and it had *640no validity. The question then remains whether the plaintiffs should not have at least a personal judgment for $200. Under the decision of the Appellate Division in McDonald v. Mayor, 58 App. Div. 73, this cannot be done, because the action to enforce a mechanic’s lien is a statutory one, in which the right.to a per-' sonal judgment against the person liable for the debt is mainly incidental to the main purpose and depends entirely upon the validity of the lien. As to said extra work, therefore, the plaintiffs must be left to their remedy by a common-law action. Upon the whole case the complaint must be dismissed upon the merits, with costs.

Judgment is directed to be entered in favor of the defendant and against the plaintiffs "dismissing the complaint upon the merits, and in accordance with this decision, together with costs to be taxed.

Judgment for defendant, dismissing complaint, with costs.