This appeal involves purely a question of law. Plaintiff contracted to do some building work for defendants and to have it finished by a day certain. The contract also provided for liquidated damages at the rate of ten dollars a day for each day’s delay.
Defendants offered no proof of damage; nor do I think that it can be claimed that that was necessary as the provision for liquidated damages in this case is so reasonable as to indicate beyond any doubt that it was not intended to be a provision for a penalty. See Mosler Safe Co. v. Maiden Lane Safe Deposit Co., 199 N. Y. 479; United States v. Bethlehem Steel Co., 205 U. S. 105, 119.
The,learned judge below was of opinion that as defendants had permitted the plaintiff to finish the work after the date originally fixed for completion, this constituted a waiver of the right to recover the amount of damages liquidated by the terms of the contract even by way of counterclaim. I cannot concur in this view, and think that the decision in Deeves & Son v. Manhattan L. Ins. Co., 195 N. Y. 324, plainly indicates the contrary to be the correct rule. The acceptance of the work at the delayed day may quite properly be regarded as a waiver or abandonment of any defense to the action for the compensation provided in the contract, but, as said by the Court of Appeals, defendant is merely thereby remitted to a counterclaim for his damages, and in the case at bar these damages are fixed by the very contract upon which plaintiff seeks to recover.
Judgment modified, and, as modified, affirmed, with costs to appellants.