Action by materialman upon a surety bond executed by defendant with a principal contractor to indemnify the city of Tonawanda on a paving contract,
Plaintiff furnished material, the last item being delivered in November, 1914, on a credit of sixty days. This action was commenced in February, 1916, more than one year after the cause of action accrued, and defendant claims that this action cannot be maintained because the plaintiff is hot a party to the bond, and must find its right to sue the surety in some statute, in this case in the charter of the city as above quoted.
Bonds of this character are intended for the protection of every one in any way contributing to the work contracted for, even to the unskilled laborer who works with his hands. Bights should not be lost through! technicalities if it is possible to avoid such results.
“ The rule of strict construction is liable at times to work a practical injustice and it ought not to be extended beyond the reason for the rule, particularly when the surety is engaged in the business of becoming surety for pay and presumably for profit.” St. John’s College v. Aetna Indemnity Co., 201 N. Y. 342, citing Guaranty Co. v. Pressed Brick Co., 191 U. S. 425.
The limitation clause affects the remedy and not the right of action. Sharrow v. Inland Lines, 214 N. Y. 101.
Certainly this is so in a case where the surety writes in a" limitation clause different from that of the statute, The Code of Civil Procedure (§ 414)) recognizes
If we accept the contention of the defendant, the bond was worthless because the limitation clause precluded any action within the limitation provided in the charter.
No one should be permitted to take advantage of his own wrong, and there is little, if any, reason to hold otherwise than that the surety should abide by his contract.
Judgment for plaintiff, with costs.