This action was originally brought to foreclose a mechanic’s lien for $1,395.50 on a block of buildings in the city of San Francisco. The buildings were erected by plaintiff for defendants under a written contract, which provided that plaintiff should furnish all the materials, and do the work according to plans and specifications made by George Bordwell, architect, and receive therefor the sum of $9,800, payable in installments as the work progressed, the last payment to be made “when the houses shall be completed, each in all its parts, and accepted by the architect.” The $1,395.50, consisted of an unpaid balance of the contract price and $375 alleged to be due for extra work and materials. The ease was tried, and judgment rendered for plaintiff. An ap
The defendants, by their answer, denied that they were indebted to plaintiff in the sums of money named in the complaint, or in any sums or sum whatever, and to the first two counts they pleaded the statute of limitations. They then alleged that the labor and materials sued for, except the last item of $105, were executed under a written contract, which was furnished by the parties on the 26th of April, 1876, and a copy of which was set forth and made a part of the answer. They further alleged that they complied with all the conditions of the contract on their part, and paid plaintiff during the progress of the work the sum of $9,104, but that plaintiff failed to comply with the conditions of the contract on his part; that he omitted to put in the buildings many things required by the contract and specifications, and that the value of the articles and work omitted was $450; that the buildings were not completed within the time named in the contract, and defendants were damaged thereby in the sum of $900; that the foundation was not put down to solid ground, and by reason thereof the buildings settled, to the damage of the same in the sum of over $1,000. The prayer was for judgment against the plaintiff for $1,500 and costs of suit. The case was tried before a jury, and the verdict and judgment were
When the trial commenced, the plaintiff first introduced in evidence the building contract, a copy of which is set out in the answer, and the specifications referred to therein. He then introduced evidence showing that the terms of the contract were subsequently changed in certain respects by agreement of the parties; that he proceeded to construct and complete the buildings according to the plans and specifications; that he performed certain extra work, which was provided for by an indorsement on the contract, and for which he was to receive $270; that he also placed an extra door in one of the houses by direction of the architect at a cost of $15, and by an agreement with defendants laid a new sidewalk in front of the building, for which they were to pay him $90; that he was prevented by defendants from completing the whole work at the time named in the contract; that after it was in fact completed the architect suggested certain items of work which he wished to have done, saying that when they were done to his satisfaction he would accept the buildings as complete, and that he (plaintiff) did the suggested work, so far as it was called for by the contract; that a few days afterward, at a meeting of the plaintiff, defendant Balletta, and the architect, the architect said he was satisfied with the building, and would accept it; that at this meeting the architect also said to plaintiff’s attorney, who was present, that “he [plaintiff] had a hard contract anyhow, and that he was glad that he had finished it up, and that he had advised him not to take the contract in the first place; that he knew he lost a great deal of money on it; he said he knew he lost not less than $2,000 on the contract; he was glad it was finished”; that it was then arranged that another meeting of the parties should be held at the architect’s office to figure up the amount due plaintiff, and settle the whole matter; and that in pursuance of this arrangement the parties met, the amount due plaintiff was figured up and agreed to be, including the extra work, $1,395.50; and that after that the architect called plaintiff’s attorney aside, “and spoke in a low tone, and said that he wanted plaintiff to pay him $100; that he had been to a great deal of trouble in superintending
1. The first and most important question presented relates to the amended complaint, and the plaintiff’s right to obtain relief thereunder. It is contended for appellants that an action in general assumpsit will only lie where nothing remains to be done except to ascertain and determine the amount of money due the plaintiff, and that where, as in this case, the action is based on a special contract, the plaintiff must allege and prove the performance of all conditions precedent before he can recover. And it is said that all the conditions precedent were not performed here, because, under the contract, the last payment was not to be due until the buildings should be completed and accepted by the architect. It has been frequently held in this state that, notwithstanding the requirement that the facts constituting the cause of action should be stated in ordinary and concise language, the common counts may be used: Freeborn v. Glazer, 10 Cal. 337; Wilkins v. Stidger, 22 Cal. 235, 83 Am. Dec. 64; Abadie v. Carrillo, 32 Cal. 172; Friermuth v. Friermuth, 46 Cal. 42; Magee v. Kast, 49 Cal. 141.. In De Boom v. Priestly, 1 Cal. 206, there was a special contract for the erection of a building, which was deviated from by instructions from the defendants. The action was brought on a quantum meruit, and testimony was admitted of
2. There was evidence introduced by the defendants conflicting on some points with that introduced by the plaintiff. The record, however, shows only a conflict; and, in view of the well-settled rule in such cases, we cannot disturb the verdict on the ground that it was not justified by the evidence.
3. The court refused to give to the jury certain instructions asked by defendants, and then read to them its own charge. The charge covered the whole ease, and stated the law applicable thereto very fully, clearly, and, as we think, correctly. It also included all the points found in the instructions refused, which were correct statements of the law, and were applicable to the case. We therefore see no error in the refusal, or in the charge given.
4. It is contended that the decision in Loup v. Railroad Co., supra, on the authority of which the former judgment was reversed, has become the law of this case, and that, under it,
5. No point is made by counsel on the statute of limitations, and we therefore find it unnecessary to consider the question as to whether the action was barred or not. Looking at the whole record, we find nothing calling for a reversal, and therefore advise that the judgment and order be affirmed.
We concur: Vanclief, C.; Gibson, C.
For the reasons given in the foregoing opinion the judgment and order are affirmed.