Howell v. Gould

Bockes, J.

[After stating the facts above.]—The evidence was conñieting. According to the testimony of the plaintiff's witnesses, the contractor performed his agreement so far as he was permitted by the defendant, except, perhaps, in some unimportant particlars, as to which there was evidence of waiver by the latter. According to the proof adduced by the defendant, the contractor was in fault from the first, having omitted performance in almost every particular required of him by the terms of the agreement. Under this conflict of evidence, the case was a proper one for the determination of the jury; and with their verdict the parties must be content, in the absence of any erroneous instruction or ruling by the court bearing on the question of fact which it was their duty to decide.

The case fails to disclose any error in the charge of the judge to the jury. Ho exception was taken to the charge, nor was any instruction asked for which was not given.

At the commencement of the trial the defendant moved the court for a dismissal of the complaint, on the ground that it did not' state facts sufficient to constitute a cause of action. The motion was properly denied. The' complaint set forth a valid agreement, and both non-performance and refusal to perform, by the defendant, was averred, with consequent damages. If not sufficiently specific in any particular, the remedy of the defendant was by special motion, before answer, under section 160 of the Code of Procedure.

When the plaintiff rested, the defendant, by his counsel, again moved for a dismissal of the complaint, on the ground that the plaintiff had not alleged or shown ability to perform the contract on the part of the contractor. This motion was also properly denied. As the case then stood on the evidence, the jury would have been authorized to find that the contractor had performed, on his part, except in so far as he was excused or was prevented from performing by the defendant.

Again: at the close of the case the defendant moved to dismiss the complaint, because it did not appear that the plaintiff (the contractor) was able, ready and willing to perform the *423■contract on his part, and that it did not appear from the evidence that he wholly neglected or refused, and was unable so to do, prior to the said alleged breach by the defendant.

To have granted this mo don would have been manifest error. As rhe case then stood on the evidence, the grounds of dismissal involved questions of fact, not in the province of the court to determine. If, as the evidence on the part of the plaintiff tended to prove, the defendant refused to perform on his part, and actually prevented performance by the contractor, it was unnecessary for the latter to show readiness' and willingness to 'perform on his part. It was enough that the defendant himsc-lf prevented further performance; and, as regards the latter ground stated, it was certainly a question for the jury, on the whole evidence, whether the contractor had neglected or refused performance on his part.

There was no error in the refusal by the court to dismiss the complaint.

. Exceptions were taken to the rulings of the learned judge, as to the admissibility of evidence. But, the consideration of those questions, and the conclusion arrived at in the supremo court, as given in the opinion of Judge Lott, are quite satisfactory.

The judgment should be affirmed, with costs.

All the judges concurred.

Judgment affirmed, with costs.