We have heretofore held that it was irregular, within the meaning of the act of *2761858, (Laws of 1858, ch. 338,) to do several things which are complained of in this petition; among which are the following: .
[New York General Term, June 1, 1868.Geo. G. Barnard, Ingraham, and Sutherland, Justices.
1st. The contract and specifications did not provide for taking up the gutter stones and paving in their place with Belgian pavement, but on the contrary required the contractor to readjust the gutter stones wherever necessary, without charge. In violation of this he removed the gutter stones and substituted the pavement, under the assent of the water purveyor, at the request of some of the owners. There was no authority for this, and it was outside of the contract.
2d. The assessors were wrong in including in their assessment a charge for making the assessment. This we held some time since to be erroneous.
3d. It was irregular and erroneous for the commissioners of the croton board to certify the work to have been completed and accepted, when they had rejected the whole street for a distance of one block. The taking a bond to do the work, and withholding part of the money, did not obviate the difficulty. That work has not been done to the time of the trial, and yet the owners have been assessed for it.
We do not, under this proceeding, inquire whether the work is well done, or done according to the contract, so far as relates to the material or workmanship; and if this were all, there would be no ground for our interference on that account; hut when it appears that the certificate was given with a full knowledge that the work was not finished, it was a violation of the contract, which prohibited the contractor from receiving payment until the whole work was completed, and was unjust to the owners who were assessed for its payment.
The application should be granted, and the assessment vacated.