The action was brought to recover damages occasioned by the neglect and refusal of the defendants to perform ail award in favor of the plaintiff, upon a submission to arbitration between the parties.
The complaint sets out the award in substance, and alleges that the defendants had neglected and refused to perform
The exception to that part of the charge in which construction is given to the award, is not well taken.
The judge, I think, gave the true construction to the award, according not only to its terms, but to the intention of the arbitrator. The plaintiff claims that, by the terms and true meaning of the award, the defendants were bound to remove all the sediment and deposits (including a small island) which had accumulated in the reservoirs, pond and race-way, at the time of the submission, so as to restore the whole to their original condition and capacity. The judge held and charged that they were only bound under the award to clear out so much of the sediment and deposits in the race-way, reservoirs and pond, which had accumulated there at the time of the award, as obstructed and impeded the due flow of water .through that water-way.
That they were not required to excavate for the purpose of keeping back and treasuring a supply of water. This claim of the plaintiff is expressly negatived by the arbitrator in his award, for he says that the result of the filling up of the pond, race and reservoirs with sediment did not enter into the minds of the original parties, and was not contemplated by them in making the deed, but was one of the inevitable accidents referred to in the deed as an exception to the obligations of the defendants. Whether the arbitrator gave the right construction to the covenants and obligations in the deed, is not the question. The question is, how did he award and determine in regard to them ? On this question, I think, the judge was clearly right.
The other exception, to the other portion of the charge, is equally untenable. There was evidence tending to show that the defendants went on after the award and made a portion
This was clearly right. The things to be done by the respective parties under the award were in the nature of concurrent acts, or concurring covenants.
The defendants were the first to perform, but were entitled to one-third of the cost of performance immediately thereupon. The things to be done by the respective parties are not in the nature of separate and independent covenants. In such a case it has been held, in an action upon an award, upon demurrer, that in order to make out a cause of action, it was incumbent on the plaintiff to aver performance on his part, or an offer to perform. (Huy v. Brown, 12 Wend., 591.) And so it seems it is a good answer by way of defence, and in excuse of performance of the award on which the action is brought, that the defendant tendered performance at the day, and has always been ready to perform, and that the plaintiff discharged him from the performance, or hindered him from performing, or had himself omitted to perforin a condition precedent. (Watson on Arb. & Aw., 368, 869.)
Here, if, as the jury may have found, the defendants offered to perform, and the plaintiff, after part performance by them, not only refused to pay his portion for such part, but gave them notice that if they went on and performed he would not perform or fulfill on his part, their neglect to perform fur
The case was properly disposed of at the Circuit, and a new trial should be denied, and judgment ordered for the defendants on the verdict.