Brett v. Harlan & Hollingsworth Co.

O’BRIEN, J.

This action is brought by the owners of the barkentine Eleanor M. Williams to recover from the defendant, the charterer of said vessel, freight and demurrage due under a charter party. The defendant did not contest the freight money, and for the amount thereof a verdict was directed by the court. Its liability for demur-rage was contested, and presents the only question upon this appeal.

Under the charter, the vessel went to Wilmington, Del., loaded there, and took a cargo of car material for two railway companies, and sailed thence for Santos, in South America, where she arrived on or about the 6th of February, 1891. On the 10th the captain of the vessel gave written notice to Hampshire & Co. (defendant’s agents at Santos, and consignees of the cargo) that the vessel was ready to discharge. The agents refused to accept the notice, upon the ground that it could not be given until the vessel had been berthed at the pier or wharf, ready to discharge cargo. It .is conceded that when such notice was given the vessel was in the stream, and there remained until about the 24th of March, when, for the first time, she reached the railway pier, and was berthed, ready to discharge the cargo. There she remained only two days, engaged in discharging, when, yellow fever having broken out in Santos, the vessel was ordered to quarantine, where she lay several weeks before again reaching the wharf and discharging the cargo, which latter was completed on the 20th of June. The testimony shows that there was but one wharf at Santos, suitable, by reason of depth of water and size, to *1114afford facilities for discharging, and that this was owned or controlled by the Sao Paulo Railway, and was “the railroad company’s pier at Santos” mentioned in the charter party. At such railway wharf there were nine berths for vessels of the size of the Williams, and it would appear that during the time from the 10th of February to the 16th of March, while the vessel was in the stream, there were berths vacant at the railway wharf. No satisfactory explanation is given why, under these conditions, the vessel was not berthed, except that both parties claimed that the duty of procuring a berth rested upon the other,—the plaintiffs, on the one hand, insisting that it was the fault of the agents of the defendant, who had control of the pier; and the defendant, that its agents had no such control, and that it was under no obligation, under the charter party, to procure a berth for the vessel. The question of fact thus presented, as to whether or not the agents of the defendant had control of the railway wharf, we think, must be resolved in the defendant’s favor. The master of the vessel assumed that the defendant’s agents were obliged to procure him a berth, and that, having control of the pier, they should have done so; but, beyond this, there is no evidence in the case tending to show that the agents of the defendant, who were the consignees, had any supervision, direction, or control of the railway wharf. When the plaintiffs’ witnesses were asked the question, directly, as to whether Hampshire & Co., defendant’s agents, had any control of the pier, they answered that it was called the “Sao Paulo Railway Pier,” but that they did not know whether Hampshire & Co. had any control, or anything whatever to do with the pier; and it is conceded that the Sao Paulo Railway was not one of the railways for which any portion of the cargo was intended. In the absence of evidence showing that defendant’s agents had such control, the fact cannot be assumed, and we cannot proceed to determine the question upon plaintiffs’ theory, that, having the control and management of the pier, it was the duty of such agents to facilitate, and not delay, the berthing of the vessel. The question of fact thus disposed of we think important, because if it had appeared that, having the right to determine what vessels should use the pier for the purpose of unloading, if they had permitted vessels arriving after the Williams (which it appears those who owned the pier did) to unload, thus giving a preference and causing the delay, they would have been, upon the ground that it was due to their default, legally chargeable with demurrage.

This brings us to a consideration of the question of law which must determine the rights of the parties upon this appeal,—as to whether, under the contract between the parties, the lay days during which it was agreed the defendant should unload the vessel should commence to run from the time that the vessel arrived in the stream at Santos, and gave notice of readiness to discharge, or whether such time only began to run when the vessel was berthed alongside the railway wharf, and ready to discharge her cargo. Upon this subject the charter party says:

“It is agreed that the lay days for loading and discharging shall be as follows (if not sooner dispatched), commencing from the time the vessel is *1115ready to receive or discharge cargo, the captain having given written notice to that effect: Thirty-five running days, Sundays excepted, for loading and discharging. * * * The cargo to be received alongside, within reach of ship’s tackle, and to be delivered alongside, within reach of vessel’s tackles, •on the railroad company’s pier at Santos, where she can safely lay afloat. Lighterage, if any be necessary, to be at expense of consignees. Vessel to :haul once only to loading or discharging wharf at her own expense. If required to move a second time, charterers to pay towage. * * * Vessel to ■be allowed free wharfage at Wilmington.”

It further provided:

“Bills of lading to be signed as presented, without prejudice to this charter.”

The charter party, then, with the bills of lading, constitutes the contract between the parties; but, as seen from the provision just •quoted, the bills of lading are subject to the charter party. If resort may be had to the bills of lading, upon this question of when the lay days commenced to run, there will be found therein this statement: “Goods to be discharged at railway wharf.” As the bills •of lading were, under the charter party, to be made subject thereto, we think the question here presented is to be determined by the construction of the charter party itself, and we are to gather therefrom what were the obligations, respectively, of the parties, as to berthing the vessel at the railroad pier. If this obligation was upon the defendant, then, clearly, upon the vessel’s arrival in the stream at Santos, and giving notice of readiness to discharge, the lay days would commence to run, and for any time thereafter occupied the ■defendant would be liable for demurrage. On the other hand, if the voyage was not completed, and the plaintiffs’ duty fulfilled, until the vessel was permanently berthefi at the railway wharf at Santos, and ready to deliver her cargo, then the delay that ensued in procuring such berth, unless, as already said, plaintiffs were prevented 'by the defendant or its agents while in the ownership or control of ■the pier, would not make the latter liable for demurrage.

We have been referred to many eases where the construction of ■charter parties was involved, but as these turn upon the construction of contracts, similar it may be, but not in all respects like, to the one here involved, no advantage can be gained from collating and discussing them; thinking, as we do, that, with respect to questions arising upon contracts of this character, just as in the construction -of wills or other written instruments, each must stand upon its own language, and upon the intent of the parties, to be gathered therefrom,—the intent, if susceptible of ascertainment, to control. By ■express language, the defendant undertook the obligation of providing a berth at the place of loading, and the absence of any express •.agreement to provide one at the place of discharge is significant. Moreover, the language already quoted from the charter party, showing that, at a berth to be provided by the defendant, the cargo- was to be received by the plaintiffs within reach of ship’s tackle, and “To be delivered alongside, within reach of vessel’s tackles, on the railroad company’s pier at Santos,” seems to us, clearly, to point out that, for the compensation provided, the plaintiffs undertook an ■employment and a voyage which was not completed until the vessel *1116had secured a berth alongside the railroad company’s pier at Santos. It will thus be seen that our conclusion agrees with that of the-learned trial judge,—that under the charter party the voyage was-not completed, and the lay days did not commence to run, until the-vessel was permanently berthed at the railway wharf at Santos, and ready to deliver her cargo alongside, within reach of her tackles, on-the railway wharf, and the captain had given notice to that effect.

It is unnecessary to discuss the question of the defendant’s duty in respect to providing lighterage, because the evidence shows that,, if the cargo had been placed upon lighters, the latter would have been required to be berthed at the pier before the cargo could have been delivered to the consignees, and it was not shown that there were any greater facilities for securing a berth for the lighters than-there were for procuring a berth for the vessel itself. We think that the exceptions should be overruled, and the motion for a new trial denied, with costs, and a judgment is ordered to be entered: upon the verdict as directed. All concur.