Pregenzer v. Burleigh

GIEGERICH, J.

This action was brought to recover damages, in the nature of demurrage, for the defendants’ delay in loading the plaintiff’s canal boat. The terms of the agreement are disputed: The plaintiff testified that the defendants’ agent in Hew York agreed to “load him” for the return trip “immediately, without delay,” on his arrival either at Plattsburgh or Port Henry. The agent denied that anything was said as to time, and claims that the agreement was not to “load him,” but to “give him a load.” The justice decided the issue in favor of the plaintiff, and, while a different conclusion might have been reached, there was sufficient evidence to support the view taken by the court below. Therefore, for the purposes of this appeal, it will be considered that the defendants’ contract (entered into in Hew York during the latter part of May, and before the upward trip was begun) was to load plaintiff’s boat immediately upon its arrival at Plattsburgh or Port Henry. When the plaintiff reached Whitehall with his boat, on June 5th, the defendants’ agent gave him an order upon third persons, at Port Henry for a load of iron ore; but this •order was not honored, when presented. He then communicated the fact by letter to the defendants at Whitehall, and on June 10th received a second order, on a different firm of shippers, at Plattsburgh, to which place he made his way as soon as a steam *36vessel could be procured to tow his boat Finally, on July 8thr he was given a load upon this order, but the cargo was of a different material, and to a different destination, from that promised. On these orders were printed the words, “No claims for demurrage allowed;” but this stipulation is ineffectual, as it constituted no part of the original agreement, nor, under the circumstances, can it be regarded as a modification of the same.

The defendants’ position that they were not responsible for the delays is untenable. Having agreed to load the plaintiff’s boat immediately, they are liable for all damages arising from the neglect, omission, or failure of other persons upon whom they depended for such performance, and whom they constituted their agents, as it were, pro hac vice. Van Etten v. Newton, (Com. Pl. N. Y.) 6 N. Y. Supp. 531, affirmed 134 N. Y. 144, 31 N. E. 334; Wordin v. Bemis, 85 Amer. Dec. 255.

The defendants’ counsel argue strenuously that mere detention of vessels, without proof of some fault on defendants’ part, does not entitle the plaintiff to recover, and cite many cases in support of their position. They are all, however, cases in which there was no express contract, and consequently are not relevant as authorities, as here there was a special contract, viz. to load plaintiff’s boat immediately. Contracts in which lay days are specified are analogous to the one in hand, and in such cases liability attaches when the time fixed has expired, whether the defendants have caused the delay or not. Abb. Shipp, p. 307 et seq., and cases-cited; Cross v. Beard, 26 N. Y. 85. At any rate, in the present instance, the defendants made an unconditional contract to do a certain thing at a certain time, and must answer in damages, for-the failure to perform their agreement. Stewart v. Stone, 127 N. Y. 500, 507, 28 N. E. 595, and cases cited. Besides, no evidence-was given of any excuse for nonperformance. Neither does it appear that the plaintiff was.remiss in any way. On the contrary, he presepted the orders with diligence, and gave prompt notice of the dishonor of the first one.

The judgment must be impeached, however, because the damages-awarded are too great, in any aspect of the evidence. At most, there was a delay of only 31 days, viz. from June 8th, the time of' presenting the first order, to July 8th, when the load was received. One of these days must be allowed for loading. Therefore, the defendants are chargeable with 30 days only. Now, the plaintiff' himself testified that $3 per day was a fair price for the use of a boat during the period for which he was detained. Other witnesses for the defendants testified to a lower figure. But there-is additional evidence that $3 per day would have been about the-daily profits of the plaintiff, had the cargo been furnished as agreed. The justice was warranted, then, in the conclusion he evidently reached,—that $3 was a fair measure of damage for each day of" detention; and the rule of damages followed was, to this point,, the correct one. Ashburner v. Balchen, 7 N. Y. 262. This, with-' out more, would justify the judgment rendered, which was for $90.. Now, this sum can be arrived at only by taking all the testimony-*37most strongly in favor of the plaintiff. But it is shown, further, on plaintiff’s admission and on other evidence, that the net profits realized on the cargo which was furnished at last were about $20 more than what would have been made on the one promised, and the time required was substantially the same in either case. No deduction was made for this excess, and in this we think error was committed; otherwise, the plaintiff would be placed in better financial condition than he would have been had no delay occurred. This is contrary to the theory of " damages. “The sole object is to furnish compensation. In ordinary cases of contract, the remuneration must be less. In cases of tort, it may be more.” Sedg. Dam. p. 37. We think that the excess of profits should be treated as though it were money earned independently during the period of delay, and consequently, on a familiar principle of law, should be subtracted. Shannon v. Comstock, 21 Wend. 456; Heim v. Wolf, 1 E. D. Smith, 70. The damages awarded should therefore be reduced to $70, and the judgment, as thus modified, should be affirmed, but without costs to either party.