Gaskill v. Davis

Bleckley, Justice.

1. For a mechanic to have, under §1959 of Irwin’s Code, a lien upon improvements, where he could have none upon the premises as against the true owner, the improvements must have been made by him. Are improvements made until they are brought to a state of completion fit for use ? Are naked brick walls and the other4>rick-work of a house improvements made, or are they improvements partially made, that is, commenced and somewhat advanced ?

2. A mechanic whose lien is upon such incomplete structure as the’ walls and chimneys of a house, and does not attach to the land, cannot enforce the same by levy and sale unless he proceeds whilst the subject of his lien is substantially as he left it. If, after it has been carried on to completion by others, he has a remedy, it is by the methods of equity rather than by those of law; but neither law nor *646equity" will mutilate a building by selling the brick-work separately from the plastering, roof, floors and general finish.

3. In May, 1872, premises were leased for a term extending from that date till the expiration of the year 1876. The rent reserved was, for the first year, thirty dollars per month; for the second year, thirty-five dollars per month; for the third, forty dollars per month ; and for the fourth and fifth, forty-five dollars per month. Payments were to be made monthly in advance. Eor default two months, the lessor had a right to re-enter, and avoid the lease. All improvements were to belong to him. The houses upon the premises were to be returned by the lessee as good as when received, wear and tear as usual excepted. Until Christmas, 1873, the lessee had a concjitional right to purchase the premises at $5,000.00, half cash, and the other half on time. The condition annexed to this right was, that the property should happen to be released from certain attachments that were resting upon it. The contract was in writing, and was signed by both parties. The lessee being in possession, a mechanic, under a contract with him, erected upon the premises the walls and other brick-work of a two-story brick house. Iiis work was completed the first of December, 1872, and he recorded his claim of lien on the 4th of February following. The amount of the debt was upwards of $900.00. In the claim of lien, the premises were treated as the absolute property of the lessee, and the lien was claimed upon the house and lot, “for furnishing brick and building said house.” The mechanic had no concern with the plastering or other work subsequently done to complete the building. He declared on his lien, and obtained judgment against the lessee, the date of the judgment being April 8th, 1875. Execution issued, andwas twice levied. The first levy was made June 5th, 1875, and was upon the lot and the building, as the property of the lessee. A claim was interposed, not by the lessor directly, but by his children, for whose benefit he held the title in trust. The second levy was upon *647the leasehold interest (duly described) of the lessee, in the house and lot. It was made June 1st, 1876; and on the first Tuesday in January, 1877, the sheriff attempted a sale under this levy, but no bid was obtained, the lessee’s term having then expired. The claim case was tried in June, 1878, on a special issue, in which the plaintiff in fi. fa. averred that the improvements, consisting of the “ walls ” of the house, were subject to the fi-. fa., “ being the improvements placed upon the lot by him.” .The issue concluded with a prayer that the verdict and judgment might be so moulded as to subject “ said improvements.” No facts were alleged, further than appears in this brief description of the issue, and no equitable principle was invoked as the basis of a special judgment. The jury found “the brickwork and walls ”, put on the premises by the plaintiff, subject to the lien. The court adjudged and decreed that “ the brick-work and walls” are subject to the lien, and that they be sold under the fi. fa. A motion for a new trial was made by the claimants, on the ground, among others, that the verdict was contrary to law. The motion was overruled. The court erred in not granting it.

Judgment reversed.