In 1884 the people of a certain neighborhood in Warren county erected a bridge over Camp Creek. In November, 1888, the board of roads and revenues of the county, by an order entered on their minutes, received and adopted this bridge as a county bridge. Some time thereafter, perhaps in 1892, the bridge was washed away or largely damaged by a freshet. Whether its destruction was partial or practically total is not clearly shown by the evidence. There is evidence that the flooring and sleepers were washed away, leaving the bents or arches standing. Other parts of the evidence seem to indicate that not all of the flooring and
1. One of the grounds of the motion complains that the judge •erred in charging the jury as follows: “ I charge you, gentlemen, if this bridge was built prior to Dec. 29, 1888, by private individuals, and the county authorities, after the bridge was built and prior to Dec. 29, 1888, adopted said bridge as a county bridge, and if the plaintiff’s mules and surrey were damaged by said bridge falling in while said mules and surrey were passing over it, and said damage occurred because of said bridge being in a defective condition, or because of not being in reasonably good repair, plaintiff, would be entitled to recover such damages as the evidence shows that he sustained, provided the party in charge of such mules and surrey at the time could not have discovered the condition of such bridge by ordinary care and diligence, and provided said damage did not occur on account of ordinary neglect or fault of said party.” Under the evidence as above recited and under the law, we think the exception to this charge is well taken. Prior to. the act of December 29, 1888, a county was not liable for injuries arising from defective bridges, unless the bridge had been erected under contract and the county had taken no bond from the contractor as required by law; and even then the county was not liable unless the injury •occurred within seven years from the building of the bridge. This bridge was adopted by the county, as above recited, in November, 1888, and was repaired or rebuilt in 1892. The injury sustained by the property of the defendant in error occurred in August, 1900, more than'seven years after the repairing or rebuilding of the bridge, and much more than seven years after it was originally adopted as
2. Another ground of the motion complains that the judge refused a written request, properly made, to charge as follows: “ If you should believe from the evidence that the defendant, Warren County, observed ordinary care in keeping the bridge . . in repair,, or that the plaintiff or his agent in charge of the team could have prevented the injury by observing ordinary care, then I charge you that it would not be liable.” We think that the judge should have instructed the jury as to the matters covered by this request. It-is true that he did cover the latter part of it, as to the result of a want of ordinary care on the part of the driver of the vehicle, but nowhere in his charge did he intimate that the county would escape liability if its authorities had observed ordinary care in examining, looking after, repairing, and maintaining the bridge. While-the Political Code, § 603, makes the county primarily liable for injuries caused by defective bridges, it does not make the counties insurers of the condition of the bridges. It does not require extraordinary care on the part of the county authorities in building or maintaining county bridge's. ' Ordinary care is all that is required of them under the law. Whether the county ‘authorities exercised ordinary care in examining or repairing the bridge was-
judgment reversed.