Georgia Southwestern & Gulf Railroad v. Georgia-Alabama Power Co.

Atkihson, J.

1. In a suit for damages and to enjoin a continuing nuisance, where the defendant’s answer raised several issues of fact on which evidence was introduced at an interlocutory hearing, a bill of exceptions assigning error on the judgment refusing to enjoin tern*173porarily the alleged nuisance, in which it is stated that the judgment was based on the sole ground that “ the injunction prayed for would be mandatory in its nature, and no injunction can be granted plaintiff which is not mandatory,” and that as to all other matters he held with the plaintiff, and the bill of exceptions states that “ no evidence was introduced by either side as to what acts defendants would have to perform if the injunction were granted,” and that “none of the evidence introduced before said judge is material to elucidate the error complained of in this bill of exceptions,” the bill of exceptions will not be dismissed, on motion of the defendant in error, on the ground that the brief of the evidence submitted at the interlocutory hearing was not brought to the Supreme Court. Civil Code, § 6140; Lamar v. Gardner, 113 Ga. 781 (39 S. E. 498). In such case the allegations in the petition and admissions in the answer may be considered as a basis for the judge’s decision, and the question as to the correctness of the judge’s ruling that the injunction prayed for would be mandatory will be decided on the basis of the pleadings.

2. Where a power company maintains a dam equipped with floodgates-across a stream, which causes water to overflow and pond under a bridge of a railroad company further up the stream, continuance of which will injure the supporting piers of the bridge and render it-unsafe, and the depth of the water is such as to render impossible the making of repairs or the renewal of the piers, an order restraining the power company from continuously maintaining the overflow under the railroad bridge so high as to prevent the railroad company from making reasonable and necessary repairs to the piers would not amount to a mandatory injunction, although in order to obey such restraining order it might be necessary for the power company to open the floodgates in the dam at intervals for the purpose of enabling the railroad company to make reasonable and necessary repairs to the bridge. Goodrich v. Georgia Railroad Co., 115 Ga. 340 (41 S. E. 659); Macon, Dublin & Savannah R. Co. v. Graham, 117 Ga. 555 (43 S. E. 1000); Mackenzie v. Minis, 132 Ga. 323 (63 S. E. 900, 23 L. R. A. 1003, 16 Ann. Cas. 723); Oostanaula Mining Co. v. Miller, 145 Ga. 90 (88 S. E. 562); Sweetman v. Owens, 147 Ga. 436 (94 S. E. 542). Under the admissions in the pleadings, the judge would have been authorized to grant an injunction of the nature stated in this note; and it was erroneous to hold as a matter of law that an injunction that was not mandatory could not be granted, and on such basis alone to refuse any injunction.

Judgment reversed.

All the Justices concur, except Hill, ./., absent, and.