Appeals (1) from an order of the Supreme Court (Giardino, J.), entered November 4, 2005 in Schenectady County, which, inter alia, granted defendants’ motion for summary judgment dismissing the complaint, and (2) from the judgment entered thereon.
Town Law § 64 (6) makes abundantly clear that a town cannot be bound contractually unless the contract has been approved by the town board and executed by the supervisor in the town’s name. Absent strict compliance with these requirements, no contract with a town will be found to exist (see e.g. Verifacts Group v Town of Babylon, 267 AD2d 379 [1999]). Moreover, parties dealing with a town are chargeable with knowledge of the statutes regulating its contracting power and are bound by them (cf. Parsa v State of New York, 64 NY2d 143, 147 [1984]).* Inasmuch as the Town Board did not approve the settlement agreement, Supreme Court quite properly granted defendants’ motion for summary judgment dismissing the complaint. We have considered plaintiffs’ remaining contentions and find them equally unavailing.
Carpinello, Mugglin, Lahtinen and Kane, JJ., concur. Ordered that the order and judgment are affirmed, without costs.
*.
It is worth noting that in any civil action in this state, a settlement agreement, unless made between counsel in open court, is not binding upon any party unless it is in writing and subscribed by the party sought to be bound (see CPLR 2104).