In an action to recover damages for breach of contract, the defendant appeals from an order of the Supreme Court, Rockland County (Nelson, J.), dated July 1, 2008, which denied its motion for summary judgment dismissing the complaint.
Ordered that the order is affirmed, with costs.
In 2003 the defendant Ramapo Central School District (hereinafter the School District) entered into a contract with Parsippany Construction Co., Inc. (hereinafter PCC), for various school construction work. The plaintiff Zurich American Insurance Company (hereinafter Zurich) issued a payment bond for the contract. In addition to its rights as surety, Zurich took assignment of PCC’s rights against the School District.
On December 5, 2005 PCC submitted various claims to the School District for the adjustment of claims for compensation which were additional to the agreed-upon contract price. Significantly, PCC’s letter did not set a deadline or other ultimatum for the payment of the claim (cf. James McCullagh Co., Inc. v South Huntington Union Free School Dist., 39 AD3d 480, 481 [2007]; Alfred Santini & Co. v City of New York, 266 AD2d 119, 120 [1999]; Dodge, Chamberlin, Luzine, Weber Architects v Dutchess County Bd. of Coop. Educ. Servs., 258 AD2d 434, 435 [1999]). Rather, PCC requested that the claims be submitted to mediation in the event they could not be adjusted (see Matter of Mahopac Cent. School Dist. v Piazza Bros., Inc., 29 AD3d 699, 701 [2006]).
The School District moved for summary judgment, arguing that PCC’s notice of claim was untimely under Education Law § 3813 (1) since it was filed more than three months after the February 7, 2006 letter which, the School District contended, rejected PCC’s claims for payment. The School District also argued that the lawsuit was untimely as it was not commenced within one year after February 7, 2006 (see Education Law § 3813 [2-b]). The Supreme Court denied the motion. We affirm.
Pursuant to Education Law § 3813, no action may be maintained against a school district unless a notice of claim was served within three months of the date on which the claim accrued (see Education Law § 3813 [1]; C.S.A. Contr. Corp. v New York City School Constr. Auth., 5 NY3d 189, 192 [2005]; Parochial Bus Sys. v Board of Educ. of City of N.Y., 60 NY2d 539, 547 [1983]; Angelo Capobianco, Inc. v Brentwood Union Free
Unlike the school district’s letter in Matter of Mahopac Cent. School Dist. v Piazza Bros., Inc. (29 AD3d 699, 700 [2006]), which advised the contractor that there would be “no useful purpose” in pursuing mediation, the February 7, 2006 letter from the School District’s architect to PCC did not unequivocally deny PCC’s formal demand for payment of the claims and the conduct of the School District was not so unambiguous that PCC should have viewed the denial of its claims to be a final determination (see Angelo Capobianco, Inc. v Brentwood Union Free School Dist, 53 AD3d 634, 635 [2008]; Matter of Mahopac Cent. School Dist. v Piazza Bros., Inc., 29 AD3d 699, 701 [2006]; Mitchell v Board of Educ. of City School Dist. of City of N.Y., 15 AD3d 279, 280-281 [2005]). To the contrary, it is apparent from the parties’ correspondence and conduct that they contemplated engaging in voluntary mediation, and thereafter did in fact proceed to mediation, pursuant to the “supplementary conditions” to the contract, as a means of attempting to resolve their dispute (id.). Had it been the position of the School District that the claim was barred by PCC’s failure to serve a notice of claim within three months of the project architect’s letter of February 7, 2006, it would have been disingenuous for the School District to have participated in voluntary mediation.
Under these circumstances, the School District failed to establish that PCC’s claim was finally rejected, either expressly or