It is hereby ordered that the order insofar as appealed from is unanimously reversed on the law without costs, the motion is granted in its entirety and the complaint is dismissed.
Memorandum: Plaintiff commenced this action seeking damages for the alleged breach by defendant of its construction contract with plaintiff and for unjust enrichment. According to plaintiff, it fully and adequately performed the work of the contract, and defendant thus owed plaintiff the sum of $69,205:23, representing $54,500 in liquidated damages based on plaintiffs failure to comply with the contract insofar as it required substantial completion of the work by the contractual deadline, and a retainage amount of $14,705.23 based on the termination of the contract prior to final completion of the work. Defendant contends on appeal that Supreme Court should have granted its motion for summary judgment dismissing the complaint in its entirety, rather than only granting that part of the motion dismissing the claim for lost profits. We agree.
We note at the outset our agreement with defendant that the court erred in denying its motion in part, inasmuch as plaintiff failed to seek the requisite extension of the deadline for substantial completion. “It is well settled that, where parties have set forth their agreement in an unambiguous and complete document, that agreement should be enforced according to its terms” (Westfield Family Physicians, P.C. v HealthNow N.Y., Inc., 59 AD3d 1014, 1015 [2009]; see W.W.W Assoc. v Giancontieri, 77 NY2d 157, 162 [1990]). The dates by which substantial completion and final completion of the project were required were set forth in section 12.02 (A) of the contract, which refers to “Contract Times.” Any adjustment with respect to those dates could be made only by a written “Change Order” or a “Claim” for an adjustment, pursuant to section 12.02 (B) of the contract. Article 12 of the contract sets forth a metric by which any “Claim” for an adjustment of the “Contract Times” was to be covered, but it did not relieve plaintiff of its obligation to seek such an extension in the event that defendant was responsible for the delay. It is undisputed that plaintiff did not request an extension of the “Contract Times,” nor did it achieve substantial completion or final completion of the work of the contract by the contractual deadline.