In July 2005, claimant submitted notice forms called force account daily reports to the project’s engineer-in-charge (hereinafter EIC) for the drilling claim. In August 2006, claimant submitted force account daily reports pertaining to the two-stage and barrier claims. Defendant denied all three claims, and claimant commenced this action asserting breach of contract. Defendant moved for summary judgment dismissing the action, and claimant cross-moved for summary judgment. The Court of Claims granted defendant’s motion as to the two-stage claim and the barrier claim, finding that claimant had not complied with the contract’s notice and reporting requirements for either, and the two-stage claim did not constitute extra work. The court found that claimant had provided timely notice of the drilling claim, denied defendant’s motion as to that claim, and denied claimant’s cross motion for summary judgment on all three claims. Claimant appeals.1
The Court of Claims correctly determined that claimant failed to comply with the contract’s notice provisions. Pursuant to the contract, if claimant believed that it had been ordered to perform extra work, it was required to notify the EIC in writing within 10 days, with copies to other specified officers. The contract further required claimant to submit force account
Claimant did not meet this burden. First, as to the two-stage claim, there is no merit in claimant’s contention that the contract permitted corrugated metal pipe casings to be left permanently in place. The plain language of the specification in question explicitly requires the removal of such casings. A note on the project plans repeating this requirement with particular reference to drilling through rock does not, as claimant contends, replace the general specification or limit the removal requirement to drilling through rock. Contrary to claimant’s assertion, a provision in the specifications stating that the various components of the contract complement one another in a declining order of preference, beginning with the project plans, does not cause the note to supersede the specification; the two provisions simply repeat the same requirement, and do not conflict with one another.
As to the notice requirements, the subject contract explicitly provides that strict compliance with its notification and record-keeping provisions is required as a condition precedent to any recovery, and that claims for extra work are deemed waived in the absence of such compliance. When such a condition is expressly agreed upon by the contracting parties, it “must be literally performed” (Oppenheimer & Co. v Oppenheim, Appel, Dixon & Co., 86 NY2d 685, 690 [1995]). “ ‘[N]o action for breach of contract lies where the party seeking to enforce the contract
Nor did claimant demonstrate that defendant frustrated its efforts to comply with the notice provisions (see A.H.A. Gen. Constr. v New York City Hous. Auth., 92 NY2d 20, 30-31 [1998]; Bogdan & Faist v CAP Wireless Sys., 295 AD2d 849, 852-853 [2002]). Even if, as claimant alleges, a project inspector refused to sign its force account reports, the contract required such forms to be signed by the EIC, rather than the inspector, and claimant did not explain how the inspector’s alleged refusal prevented it from submitting the unsigned reports until almost a year later, rather than within one day as required by the contract, or from timely filing the other required notices and reports.2
Finally, we reject claimant’s contention that defendant was not prejudiced. The purpose of notice provisions in public contracts is to “provide public agencies with timely notice of deviations from budgeted expenditures . . . and allow them to take early steps to avoid extra or unnecessary expense, make any necessary adjustments, mitigate damages and avoid the waste of public funds” (A.H.A. Gen. Constr. v New York City Hous. Auth., 92 NY2d at 34). Claimant’s failure to provide defendant with the required notice prevented defendant from taking steps to mitigate the cost of the alleged extra work while it was being performed and therefore caused inherent prejudice. Accordingly, the Court of Claims properly granted partial summary judgment to defendant.
Spain, J.E, Rose, Kavanagh and Stein, JJ., concur. Ordered that the order is affirmed, without costs.
1.
Claimant’s brief limits its arguments on appeal to the dismissal of the two-stage and barrier claims, and we therefore deem any challenge to the denial of its cross motion to be abandoned (see Czynski v State of New York, 53 AD3d 881, 882 n [2008], lv denied 11 NY3d 715 [2009]).
2.
The inspector submitted an affidavit denying that he had refused to sign any records pertaining to disputed work or extra work.