OPINION OF THE COURT
On October 31, 1986, respondent Commissioner of Environmental Conservation (hereinafter the Commissioner) issued a
The request for permits was filed by the applicant in October 1985 seeking approval for construction of the facility, together with a further request for party status by petitioners in the approval proceeding. On December 6, 1985, an ALJ issued a notice indicating, inter alia, that a preadjudicatory issues conference would be held on January 15, 1986 to rule on petitioners’ request for party status and to narrow the issues which would be presented at the subsequent adjudicatory hearing (see, 6 NYCRR 624.6 [a]). Following the conference, the ALJ granted petitioners’ request for party status and, after a review of the stenographic transcript of the issues conferenced and all the records, documents, lists of witnesses and arguments of counsel, determined that the hearing on the application should be limited to four issues related, generally, to the design of and effect of emissions from the projected facility. Petitioners appealed that decision to the Commissioner (see, 6 NYCRR 624.6 [d]), who affirmed the ALJ’s rulings but found certain deficiencies in the draft supplemental environmental impact statement (hereinafter SEIS) on the proposed facility. The Commissioner ordered the applicant to submit additional information on the facility’s net social and economic benefits and the feasibility of a recycling program, subject to a 30-day comment period, and directed the hearing on the application to go forward on the issues identified by the ALJ.*
Among the various issues raised by petitioners is their contention that the Commissioner was without authority to grant a construction permit because of noncompliance with statutory requirements (see, ECL art 8). Specifically, ECL 27-0707 (2) (b) provides that, preliminarily, an environmental impact statement (hereinafter EIS) be prepared and that "such statement shall include a description and evaluation of the status of the proposed activity in light of the New York state solid waste management plan in effect on the date of the application” (emphasis supplied). The application herein was filed in October 1985 and there was no solid waste management plan in effect at that time. Therefore, petitioners contend that construction permits could not be issued due to noncompliance with statutory requirements.
We find no basis in law or logic to adopt such a construction of ECL 27-0707 (2) (b). There is nothing in the wording of the statute or in its legislative history to suggest that it was the intent of the Legislature to limit the jurisdiction of respondent Department of Environmental Conservation (hereinafter DEC) and place a moratorium on the construction and operation of solid waste management facilities pending the completion of a State-wide solid waste management plan by DEC. It is the Commissioner’s contention that since there was no plan "in effect” at the time of the permit applications, the requirements in ECL 27-0707 (2) (b) did not become operative. We find this interpretation entirely reasonable and rational and it should therefore be upheld by this court (see, Kurcsics v Merchants Mut. Ins. Co., 49 NY2d 451, 459; see also, Matter of Howard v Wyman, 28 NY2d 434, 438; Matter of Toniann’s Limousine Serv. v New York State Dept. of Transp., 132 AD2d 86, 88).
We also find that the Commissioner was correct in his determination of the appropriate emissions operating requirements to be imposed upon the facility. As mandated by statute, they were determined after consultation with and in
Petitioners also contend that the Commissioner acted, arbitrarily in refusing to consider certain issues for adjudication, such as the feasibility of a recycling program, the issue of "tipping fees” and their costs to the taxpayer, the size of the facility, and the disposal of "fly ash” and "bottom ash” generated by the facility. As previously described herein, the issues identified for adjudication were determined subsequent to a preadjudicatory issues conference held for that very
Finally, and equally without merit, is petitioners’ argument that the applicant’s engineering plans were prepared by a person not registered to practice professional engineering in New York. Engineering of the facility is provided by the applicant’s parent company and the facility’s engineer is stated to be Joseph Struzka of the same address as the applicant in Livingston, New Jersey. Struzka is licensed to practice professional engineering in New York. Accordingly, the applicant is in compliance with State regulations (see, 6 NYCRR 360.3 [d] [2] [ii]).
Casey, Levine and Harvey, JJ., concur.
Determination confirmed, and petition dismissed, without costs.
*.
The SEIS was required as part of the environmental review process under the State Environmental Quality Review Act (ECL art 8; 6 NYCRR part 617).