OPINION OF THE COURT
Petitioner is a domestic corporation that has operated a sand and gravel mine on its 110-acre parcel of land in the Town of Colonie, Albany County. Concededly, the mining operation was subject to regulation by respondent Department of Environmental Conservation (hereinafter DEC) under the Mined Land Reclamation Law (hereinafter MLRL) (ECL 23-2701 et seq.), which went into effect in April 1975 (L 1974, ch 1043, § 2). However, petitioner first applied for a permit from DEC to operate its mine in March 1981. Petitioner’s application sought permission to mine two specifically identified acres of the plot during an initial permit term of one year. In June 1981, petitioner filed an amended application to mine some eight acres for a three-year term. Each application was accompanied by a mined land-use plan and map as required by the statute (see, ECL 23-2713). DEC examined the plan to determine its potential environmental impact pursuant to the State Environmental Quality Review Act (hereinafter SEQRA) (ECL art 8), and found petitioner’s project to be an "unlisted action” (see, 6 NYCRR 617.12) which "will not have a significant effect on the environment”. In March 1982, the permit was granted,
Shortly before the permit’s expiration date, petitioner submitted a formal request for a three-year renewal of its permit, which it designated as a "renewal with amendment application”. In the application, petitioner described the area to be affected by mining in the first year of the renewal period as 16 acres, including continued mining of the 8 acres licensed under the initial permit. At the same time, or soon thereafter, petitioner submitted a new mined land-use plan and maps. On September 27, 1984, DEC responded with a notice of incomplete application in which it advised petitioner that the project would be subject to SEQRA review, that the Town of Colonie was designated as lead agency for that purpose and that the application would not be considered complete until the town determined the environmental significance of the project. The notice also specified some 12 items of additional information to be furnished, including a long-form environmental assessment. Admittedly, the foregoing requirements were based in part on DEC’S application of its so-called "Life of Mine Review Policy”, in which a permit application is subjected to SEQRA review covering the long-term effects of the project over the entire estimated productive period of the mine. Subsequently, the town’s Planning Board sent petitioner a notice of its determination that the project would have a significant impact on the environment, listing 13 specific significant effects, and noted that the applicant proposed to extract sand and gravel from 89 acres of its property. The notice advised that a draft environmental impact statement would be required.
After almost two years of negotiations over the information that the town demanded, petitioner initiated a proceeding in Supreme Court and succeeded in obtaining a judgment declaring that the town lacked jurisdiction to act as lead agency. In January 1987, before the order in the foregoing litigation was granted, petitioner made a written demand on DEC for a decision on its renewal application. DEC responded by letter advising that petitioner’s application was still incomplete, inasmuch as it had never received the information requested in its September 1984 notice and SEQRA review by the town had not yet reached its ultimate conclusion. Thus, according to DEC, petitioner’s demand was premature. By letter of March 3, 1987, petitioner informed DEC of the judgment eliminating the town as lead agency and sent most of the
Turning first to that portion of the petition in which the relief sought is based on petitioner’s claim that it is statutorily exempt from SEQRA review, we agree with Supreme Court’s rejection of this claim, but for a different reason than that of Supreme Court or that advanced by DEC on this appeal. The statutory provision relied upon is the so-called "grandfather clause” of SEQRA, ECL 8-0111 (5) (a), which exempts "[ajetions undertaken or approved prior to the effective date of this article”, i.e., September 1, 1976 (L 1975, ch 612, § 2, as amended by L 1976, ch 228, § 4). Petitioner submitted affidavits that it had continuously operated its sand and gravel mine on the subject property since the 1950’s. DEC contends that the exemption applies only to activities which were otherwise subject to regulation and approved by a regulatory authority before the effective date of SEQRA. Therefore, according to DEC, petitioner is ineligible because of its failure to obtain a permit under MLRL until 1981.
This argument is, in our view, precluded by our interpretation of the statutory exemption in Matter of Northeast Solite Corp. v Flacke (91 AD2d 57, 60). Nonetheless, the exemption does not apply upon "proof of change in the level of operation so substantial as to be sufficient to remove an activity from the exclusion clause * * * notwithstanding that the basic nature of the activity remains unchanged” (Matter of Salmon v Flacke, 61 NY2d 798, 800). Here, the interveners submitted
Next to be considered is petitioner’s claim for relief on the ground that the Life of Mine Review Policy is invalid as being unauthorized under and inconsistent with the statutory framework and because it constitutes a rule or regulation unenforceable in the absence of DEC’S compliance with the filing requirements of the NY Constitution (see, NY Const, art IV, § 8). The Life of Mine Review Policy, as described in a DEC internal memorandum, in substance requires a full SEQRA review of environmental effects during the entire estimated productive period of the mine, until the completion of reclamation, for (1) all applications for a new permit, and (2) renewal applications concerning mines which had not previously been subjected to such review. In essence, the policy will require one comprehensive examination of the long-term environmental effect of each mining operation subject to MLRL regulation.
We find nothing in that policy which is in conflict with the statutory scheme. MLRL project permit applications unquestionably are subject to SEQRA, and SEQRA review is an element of the permit and permit renewal process except, of course, for projects statutorily exempt from SEQRA, as previ
Likewise, the Life of Mine Review Policy is not invalid because of DEC’S failure to follow the constitutionally required procedure for promulgating a rule or regulation. As previously described, the policy merely requires DEC to consider in the permit process the long-term environmental effects of a mining project throughout its planned productive life, including reclamation. The Life of Mine Review Policy does not dictate the result of that review, either in terms of whether an environmental impact statement will be required or whether a permit will be issued. As such, the policy is not "a fixed, general principle to be applied by an administrative agency without regard to other facts and circumstances relevant to the regulatory scheme of the statute it administers” (Matter of Roman Catholic Diocese v New York State Dept. of Health, 66 NY2d 948, 951) and, hence, need not have been filed as a rule or regulation.
Petitioner’s final argument is that, as a permit renewal application which DEC did not timely determine to constitute a material change from the original permit application, as required by the ECL’s Uniform Procedures Act (see, ECL 70-0115 [2] [b]) and which, in fact, was not such a material change, DEC was barred from subjecting the application to comprehensive review under SEQRA and its Life of Mine Review Policy. Again, petitioner contends that our decision in
Petitioner further argues that, even if its 1984 proposal did involve a material change from the original permit, DEC’s failure to make an express determination thereof and to treat the application as a new application within 15 days of submission, as required under ECL 70-0115 (2) (b), precludes consideration of any such changes, again relying on Matter of Atlantic Cement Co. v Williams (supra). We disagree. First, the express statutory effect of a failure to make a timely determination that a renewal application involves a material change is that "the provisions of paragraph (b) of subdivision three of section 70-0109 of this chapter shall apply” (ECL 70-0115 [2]). ECL 70-0109 (3) (b) provides in substance that if DEC fails to make a decision on a permit application within the relevant statutory time period, the applicant may serve written notice of the default, after which the failure of DEC to render a decision
Moreover, there was another regulatory basis upon which DEC could subject petitioner’s 1984 application to full environmental review. On that application (and the later, revised application submitted), petitioner quite properly and accurately designated it as an application "with amendment” (emphasis supplied), in view of the significant expansion of the project sought by petitioner. Under the regulations, such an amendment application is subject to the same requirements as a completed application for a new permit (6 NYCRR 421.4 [c]). That includes, where appropriate, the filing of an environmental impact statement (6 NYCRR 421.1 [c] [5]), the furnishing of which constitutes the thrust of petitioner’s challenge here. Although the regulations require DEC to give written notice if it deems a proposed change in a permit to be sufficiently significant to require an amendment, this was unnecessary here, since petitioner itself expressly characterized the application as one for an amendment.
We have considered petitioner’s remaining points and find them equally without merit. Accordingly, the dismissal of the petition should be affirmed.