Appeal from an order of the Court of Claims (Collins, J.), entered October 7, 2015, which granted defendant’s motion to dismiss the claim.
Claimant is a contractor that was authorized to perform certain highway improvement work pursuant to five highway
A claim for breach of contract must be filed in the Court of Claims within six months after the accrual of the claim, or within two years from such accrual where the claimant has filed a timely notice of claim (see Court of Claims Act § 10 [4]). A claim to recover damages to property must be filed either within 90 days after accrual of the claim or within two years after accrual where a timely notice of claim has been filed (see Court of Claims Act § 10 [3]; Ro Jo Lo Partners v State of New York, 226 AD2d 896, 896 [1996]). “A claim accrues when damages are ascertainable” (Ro Jo Lo Partners v State of New York, 226 AD2d at 896 [internal quotation marks, brackets and citation omitted]; see Waters of Saratoga Springs v State of New York, 116 AD2d 875, 877 [1986]).
Claimant alleges in its notice of claim that it did not perform any work after DOT issued a stop work order in May 2008, which claimant points to as the breach of “the contract” that obligated its surety for an allegedly excessive amount. Claim
In our view, even assuming without deciding that there was an agreement between claimant and defendant, the damages for the alleged breach were clearly ascertainable more than six months prior to March 2013 and more than two years prior to December 2014. As for the property damage claim, claimant alleges in its notice of claim that the flooding first occurred in July and August 2006, prior to the date when the work was completed. With the work completed in November 2008, any alleged damages must have been ascertainable years in advance of the claim. Absent a timely filed claim or notice of claim, the Court of Claims did not have subject matter jurisdiction to resolve the claim (see Lyles v State of New York, 3 NY3d 396, 400 [2004]; Matter of Best v State of New York, 42 AD3d 699, 700 [2007]; Conner v State of New York, 268 AD2d 706, 707 [2000]). Accordingly, we find that the claim was properly dismissed. The parties’ remaining arguments need not be addressed.
Ordered that the order is affirmed, without costs.
*.
Although the Court of Claims granted defendant’s motion to dismiss pursuant to CPLR 3211 (a) (7), the alternative ground — that the court lacked subject matter jurisdiction — was raised and is properly before us (see Ullmannglass v Oneida, Ltd., 121 AD3d 1371, 1372 [2014]).