Zenith Energy Terminals Joliet Holdings LLC v. CenterPoint Properties Trust

                   IN THE SUPERIOR COURT OF THE STATE OF DELAWARE

        ZENITH ENERGY TERMINALS                               )
        JOLIET HOLDINGS LLC, et al.,                          )
                                                              )
                                Plaintiffs,                   )     C.A. No.: N19C-10-054 EMD CCLD
                                                              )
                        v.                                    )
                                                              )
        CENTERPOINT PROPERTIES TRUST,                         )
                                                              )
                                Defendant.


         Upon Defendant’s Motion for Leave to File Amended Answer to Assert Counterclaim
                            GRANTED in part and DENIED in part

           Upon consideration of Defendant’s Motion for Leave to File Amended Answer to Assert

Counterclaim (the “Motion”) filed by Defendant CenterPoint Properties Trust (“CenterPoint”);

Plaintiffs Zenith Energy Terminals Joliet Holdings LLC and Joliet Bulk, Barge & Rail LLC’s

Opposition to CenterPoint Properties Trust’s Motion for Leave to File Amended Answer to

Assert Counterclaim (the “Opposition”) filed by Plaintiffs Zenith Energy Terminals Joliet

Holdings LLC and Joliet Bulk, Barge & Rail LLC1 (collectively, “Plaintiffs”); the letter dated

October 25, 2021 from F. Troupe Mickler IV, Esq., to the Honorable Eric M. Davis; the letter

dated October 26, 2021 from Christopher Viceconte, Esq., to the Honorable Eric M. Davis; the

arguments made at the hearing held on October 18, 2021 (the “Hearing”); the entire docket of

this civil proceeding,

           1.       The standard of review on a motion for leave to file an amended complaint is

well-settled. Superior Court Civil Rule 13(f) states that “[w]hen a pleader fails to set up a

counterclaim through oversight, inadvertence, or excusable neglect, or when justice requires, the


1
    Joliet Bulk, Barge & Rail will be individually referred to as “JBBR.”
pleader may by leave of court set up the counterclaim by amendment.”2 Superior Court Civil

Rule 15(a) provides that for an amendment to the pleadings, “a party may amend the party's

pleading only by leave of court or by written consent of the adverse party…and leave shall be

freely given when justice so requires.”3 Delaware Courts generally grant motions to amend

liberally, but it is not automatic.4 The Court may deny an amendment when there is evidence of

undue delay, bad faith, or dilatory motive on part of the movant, repeated failure to cure

deficiencies, or prejudice.5 The Court also considers the proposed amendment’s impact on a

scheduled trial date.6

        2.       Plaintiffs filed their Complaint on October 7, 2019.7 CenterPoint moved to

dismiss the Complaint on November 19, 2019.8 The Court held a hearing on the motion to

dismiss on January 28, 2020.9 At the conclusion of the January 28, 2020 hearing, the Court

denied the motion to dismiss.10

        3.       On February 21, 2020, CenterPoint filed its Answer.11 CenterPoint did not assert

any counterclaims as part of its Answer. In the Answer, CenterPoint addresses the issue of

JBBR and the Final Completion Certificate; however, CenterPoint does not contend that JBBR’s

failure to issue the Final Completion Certificate constituted an actionable contract or tort cause




2
  Super. Ct. Civ. R. 13(f).
3
  Super. Ct. Civ. R. 15(a).
4
  See, e.g., Fulton Bank, N.A. v. River Rock, LLC, 2018 WL 3854099 (Del. Super. Aug. 13, 2018) (denying motion
to amend under Civil Rule 13(f) and/or Rule 15(a)); Sokol Holdings, Inc. v. Dorsey & Whitney, LLP, 2010 WL
59930, at *2 (Del. Super. Feb. 19, 2010) (Parkins, J.).
5
  Hess v. Carmine, 396 A.2d 173, 177 (Del. Super. 1978).
6
  See, e.g., Spady v. Keen, 2006 WL 2559853, at *3 (Del. Super. Aug. 25, 2006).
7
  D.I. No. 1.
8
  D.I. No. 9.
9
  D.I. No. 25.
10
   D.I. No. 27.
11
   D.I. No. 28.

                                                       2
of action.12 CenterPoint did not assert an affirmative defense based on a material breach by

Plaintiffs. CenterPoint did “reserve” its right to amend the Answer “as this action progresses.”13

          4.      On August 27, 2021, Plaintiffs moved to amend the Complaint.14 Plaintiffs

proposed amendments were minor—no new causes of action, no additional facts. Plaintiffs

sought to amend the Complaint to add, what Plaintiffs contend, is a copy of the “Description of

Work and Services” (Ex. G) that was part of the Ragnar Contract. Plaintiffs asserted that when

they filed the Complaint, they attached the Ragnar Contract but did not append the Description

of Work and Services. CenterPoint opposed the motion to amend.15 The Court granted the

motion to amend without a hearing.16 Plaintiffs filed the Amended Complaint on September 10,

2021.17

          5.      On September 24, 2021, CenterPoint filed its Answer and Affirmative Defenses

to Amended Complaint (the “Amended Answer”). The Amended Answer does not change

CenterPoint’s answers to the Amended Complaint’s factual allegations regarding the Final

Completion Certificate.18 CenterPoint makes no factual response that the Certificate of

Completion was wrongfully withheld by JBBR. CenterPoint does add an additional affirmative

defense, Seventh Affirmative Defense, that contends that Plaintiffs claims are barred, in whole or

in part, because JBBR materially breached its obligations under “Construction Management

Agreement when it withheld, conditioned and delayed issuance of the Final Completion

Certificate.”19



12
   See, e.g., Ans. at 15-17, 19-20 and 26-27.
13
   Id. at 30.
14
   D.I. No. 86.
15
   D.I. No. 87.
16
   D.I. No. 88.
17
   D.I. No. 89.
18
   See. e.g., Am. Ans. at 15-17, 19-20 and 26-27.
19
   Id. at 30-31.

                                                    3
         6.       On September 24, 2021, CenterPoint filed the Motion.20 The Motion seeks to

amend the Amended Answer to assert a breach of contract counterclaim. The proposed

counterclaim asserts a claim (the “Proposed Counterclaim”) against Plaintiffs because JBBR

purportedly “breached its obligations under the Construction Management Agreement when it

unreasonably withheld, conditioned and delayed issuance of the Final Completion Certificate.”21

         7.       The Proposed Counterclaim arises out of the transaction and occurrence that is the

basis of Plaintiffs’ Complaint. Accordingly, the Proposed Counterclaim is a compulsory

counterclaim and should have been first asserted with the Answer on February 21, 2020.22

         8.       CenterPoint contends that the Court should grant the Motion because: (i)

CenterPoint just learned of “new” facts underlying the Proposed Counterclaim on September 22,

2021; and (ii) Plaintiffs will not suffer any prejudice. Plaintiffs oppose the Motion. Plaintiffs

contend CenterPoint cannot satisfy Civil Rule 13(f). In addition, Plaintiffs argue that the

Proposed Counterclaim is futile because it is barred by the statute of limitations.

         9.       The Court is troubled by the lateness of the Proposed Counterclaim. CenterPoint

is contending that JBBR first breached the Construction Contract on or about October 29, 2015

when JBBR improperly withheld consent to the issuance of the Final Completion Certificate.23

JBBR purportedly continued this conduct for several months/years.24 In fact, Ragnar sued JBBR

over a similar issue on January 23, 2017—more than three years before CenterPoint filed its

original Answer.




20
   D.I. No. 91.
21
   Mot. at ¶ 13.
22
   Super. Ct. Civ. R. 13(a).
23
   Mot. Ex. A at 34-36.
24
   Id.

                                                   4
        10.     The Court notes that CenterPoint does not make a claim of excusable neglect,

oversight or inadvertence. Instead, CenterPoint contends that new evidence was discovered in a

deposition held on September 22, 2021 that supports the Proposed Counterclaim. The Court has

difficulty with this argument given that Ragnar knew enough to assert a similar claim against

JBBR in early 2017.

        11.     The Court will follow the reasoning in Fulton Bank, N.A. v. River Rock, LLC.25

In Fulton, the Court denied leave to amend the pleadings to add a compulsory counterclaim

because the proposed counterclaim was untimely.26 The defendant in Fulton seemingly

possessed facts to support its proposed counterclaim but failed to assert the claim until six

months after the filing of defendant’s answer. The Court held that this unexcused delay meant

the request to amend was untimely under either Civil Rule 13(f) or Civil Rule 15.27

        12.     Here, CenterPoint knew or should have known of the facts underlying the

Proposed Counterclaim no later than January 23, 2017. Under Civil Rule 13(a), CenterPoint

needed to assert the Proposed Counterclaim with its Answer filed on February 21, 2020. Instead,

CenterPoint chose to wait another twenty months before seeking relief under Civil Rule 13(f).

CenterPoint seems to entirely rely on the “when justice so requires” standard. Under the

circumstances here, the Court finds that CenterPoint cannot meet that standard.




25
   2018 WL 3854099 (Del. Super. Aug. 13, 2018)
26
   Id. at *1.
27
   Id. at *3.

                                                 5
       13.     The Court DENIES the Motion for failing to meet the standards under either

Civil Rule 13(f) or Civil Rule 15(a).

IT IS SO ORDERED

Dated: January 27, 2022
Wilmington, Delaware

                                                   /s/ Eric M. Davis
                                                   Eric M. Davis, Judge

cc: File&ServeXpress