Allen v. Carman

By the Court. Daly, J.

This judgment was erroneous. The respondent, Allen, worked from October to March, 1852, upon certain buildings which one Smith had contracted to build for Carman, the appellant; upon which work there was due to him, from Smith, a balance amounting to $78 70. In May, 1852, his work having been finished in the March preceding, he filed the usual notice of lien, and claimed in the action below, to recover the $78 70 from Carman, as a lien upon the fund in his hand, due to Smith under the contract. It appeared by the contract that Smith was to finish the buildings for $5,000; that in March, before Allen filed his lien, Smith notified Carman of his inability to go on and complete the buildings, and that, in consequence, Carman employed one Angevine to finish'them, at a cost of $3,497 14. When Smith gave this notice, he had received $2,972 under the contract, $2,000 of which consisted of a claim Carman had against him for lumber supplied before the making of the contract, for which Smith was given credit by Carman on general account. He thus received $972 in cash, and the balance, $2,000, went to discharge the claim which Carman had against him for the lumber. This appears to have been the position of Carman and Smith, as owner and contractor, when Allen filed his lien in May; and if the $2,000 was good as a payment under the contract, then it may fairly be presumed that Smith was fully paid up when he abandoned the work in March, inasmuch as it cost Carman $3,497 14 to get it completed; $1,269 14 more than Smith was to receive for doing it.

Upon this state of facts, the justice rendered judgment for the plaintiff, Allen, for the sum of $78 70, upon the grounds, as appears by his opinion,

1. That the application of the money due under the contract, in discharge of the debt due by Smith to Carman, though made bona fide, and a sufficient discharge as between the parties, could not be deemed a payment affecting the lien subsequently docketed by Allen.

*6942. That the owner having concluded to go on with the work himself, was not authorized to make payments for the work subsequently done to the prejudice of Allen, the plaintiff.

3. If the contract was put an end to, and the owner took upon himself the completion of the building, he had then the benefit of the plaintiff (Allen’s) work, and was liable to Allen on the quantum meruit, as to any moneys payable under the contract at the time of the filing of the lien, which had not been actually, in good faith, paid by the owner to the contractor.

It was held by the court, in Doughty v. Devlin, general term, May, 1852, (ante, p. 625,) that all sub-contractors with the contractor, must, so far as they rely upon the owner or his house, as security under the mechanics’ lien law, be deemed to do so in subordination to the owner’s contract, and upon the credit which the terms of such contract offer for their reliance. That the owner cannot be compelled to pay any greater sum than the contract price, and that all payments made by him to the contractor in good faith, before notice of the lien, are to be allowed to him, in determining whether any balance remains due to the contractor to which the lien may attach. Now, the giving of Smith credit for $2,000, was equivalent to a payment. It was not to be expected that having a claim against Smith to that amount, Carman should make a payment in cash, (see Owens v. Ackerson, ante, p. 691, and Miner v. Hoyt, 4 Hill, 193,) when the two first payments were due under the contract, of $1,100 each. They did what was natural and proper, applied one debt, as far as it went, in payment of another. That is, Carman having an account against Smith for lumber, to $2,000, gave Smith credit on that account, to $2,200, by which adjustment Carman remained Smith’s debtor to $200. He subsequently paid the $200, and $772, making altogether, of payments on the contract, $2,972, leaving $2,028 as the balance of the contract price of $5,000,—$1,469 less than the sum Carman had to pay to get the work finished. If this affords any presumption, it is, that Smith was over paid at the time he threw up the contract; *695that nothing was coming to him, to which the lien of Allen would attach.

In respect to the second ground, assigned by the judge below, it is simply necessary to say, that all that Allen could acquire, was a lien upon any moneys in the hands of Carman, due to the contractor. If there was nothing due to him when the lien was docketed, and nothing became due afterwards in consequence of his throwing up the contract, Allen, of course, could acquire nothing. Carman does not become responsible for the payment of Allen’s claim because he is compelled to get the house finished by others. It would be preposterous, indeed, if after paying the contractor for all that he has done, the owner is to become responsible to all whom the contractor has neglected to pay, when liens are docketed after the payment is made ; because, in consequence of the refusal, neglect, or inability, of the contractor to complete his contract, the owner is compelled to employ some body else to do so.

The last reason assigned for this judgment would scarcely seem to require a serious answer. It is enough to say, that if the owner has the benefit of the plaintiff’s work upon the building, he has paid for it to the # contractor, before he had notice of the non payment by the contractor of the plaintiff’s claims, and upon no principle can he be required to pay for it over again.

Judgment reversed.