The action is to recover the sum of $615.66 and interest from September 1, 1891, made up of a balance of $300 claimed under a contract and $315.66 for extra work and material.
' The answer alleges nonperformance in conformity with the plans and specifications, and that defendant was obliged to expend $200 to complete the same, and asks judgment for a dismissal of the complaint and for a judgment for $700, including the $200 alleged and $500, the amount fixed by the contract as damages to be paid by the failing party. .
We have examined the case and evidence very carefully for errors alleged to have been committed, and which, it is claimed,have resulted in a judgment against the defendant which the court, on appeal, is called upon to reverse.
The findings of the trial judge award to the defendant the sum of $213.01, to be deducted from any amount found, to be due the plaintiff, and this is in excess of the sum claimed by the defendant in her answer to have been expended in what she terms a completion of the contract, and this is thirteen dollars and one cent more than is claimed in her answer to have been paid.
*205He also finds that the plaintiff performed extra work outside of the contract, amounting in all to the sum of $324.32, as against $315.66, the amount claimed by the plaintiff in his complaint, so that, by a computation of figures, there is a balance in the defendant’s favor on this award of four dollars and forty-five cents in adjusting balances.
We are not disposed to disturb .findings of fact which" embrace mere calculations or additions in figures, nor where the court has determined them after hearing all the evidence in the case.
The notice of lien sufficiently described the defendant and the property, and we cannot say that the defendant has been misled or affected to her injury by anything in the contract or specifications, or any alleged variance between them.
By the terms of the contract the plaintiff agreed “ to furnish all the materials and perform all the necessary labor to complete,” etc., “ according to the plans and specifications,” and the trial judge has found a substantial compliance with the terms of the contract, awarding to the defendant a credit of $213.01 for work claimed by her to have been necessary to complete and restore that portion of the work for which it is claimed by the plaintiff that the elements were responsible, and this adjustment by the trial court of the equities between the parties we are not inclined to vary.
Ho other or further damages were proven by the defendant on account of any alleged nonperformance than the sum allowed to her in the adjustment as made by the findings, and her right to recover anything beyond the credit awarded does not appear.
There is no contention by the defendant but that, with the allowances made in the findings as a credit to the defendant, the contract and specifications were completed and performed, and for this reason we are disinclined to disturb any of the findings or conclusions of the trial judge, which appear to be not unfavorable to the defendant as we have examined them, and are in accord and harmony with the whole case and the evidence adduced on the trial.
*206There does not appear to us anything in the defendant’s request or exceptions calling for a different conclusion than that which was reached by the trial judge.
The judgment should, we think, be affirmed, with costs.
Fitzsimons, J., concurs.
Judgment affirmed, with costs.