The plaintiff, by the terms of the written agreement made between himself and the defendants, agreed “'to do the following" work on the premises ,116 and 119 •Greene street, and 27 and 29 West Third street, viz.: To complete four skylights made of galvanized iron No. 24; four ventilators with dampers; two gutters and leaders; and ■ guarantee the same tobe well finished and with good material, for the sum. total of $250.” The defendants paid on account of such work and materials the sum of $180, leaving a balance of $70, for the recovery of which this action was brought.
From the testimony of the plaintiff it appears that he complied with the conditions of the contract on his part; that he constructed the skylight according to the directions given him, and that he used the material approved by the defendants or their representative. The testimony on the part of the defendants, on the other hand, tended to show that the plaintiff, instead of using No. 24 galvanized iron, as called for by the contract, used an. entirely different kind, known as No. 26, a kind of iron lighter and of less power of resistancethat the' skylight was so-improperly constructed that It leaked, and that' the plaintiff did not work in accordance with the defendants’ instructions.
'The facts were fairly submitted to the jury, which determined the conflict .of testimony-in plaintiff’s favor. We are • satisfied from a careful examination of the evidence that it is sufficient to sustain -the verdict of the jury, and we find no reason to interfere with their determination of the facts in the absence of the elements which are requisite. to review the same. :-
The' defendants’ exceptions taken to the rulings of the court are, in our opinion, without merit; and for the fore- ■ going, reasons we think the judgment should be affirmed, with costs-.
Bisohoff,. J., concurs.
, Judgment affirmed, with costs.