United States Court of Appeals
For the First Circuit
No. 09-2565
REDONDO CONSTRUCTION CORP.,
Plaintiff-Appellant,
v.
JOSÉ M. IZQUIERDO, in his individual capacity and in his official
capacity as Secretary of the Puerto Rico Department of
Transportation and Public Works, et al.,
Defendants, Appellees.
APPEAL FROM THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF PUERTO RICO
[Hon. Francisco A. Besosa, U.S. District Judge]
Before
Lipez, Leval,* and Thompson,
Circuit Judges.
Luis Cotto-Román, with whom Yolanda Benítez de Alegría and
José A. Cabiya-Morales were on the brief, for appellant.
María E. Villares-Señeriz, for appellees Puerto Rico Highway
and Transportation Authority and José Izquierdo, in his official
capacity as Secretary of the Puerto Rico Department of
Transportation and Public Works.
Roberto Ruiz Comas, for appellee Puerto Rico Buildings
Authority.
Eliezer A. Aldarondo-López, with whom Eliezer Aldarondo-Ortiz
was on the brief, for appellees the Governor of Puerto Rico, in his
official capacity; José Izquierdo, in his individual capacity;
Fernando Fagundo, in his individual capacity; and José Lluch-
García, in his individual capacity.
*
Of the Second Circuit, sitting by designation.
October 25, 2011
LEVAL, Circuit Judge. Plaintiff Redondo Construction
Corporation (“Redondo”) appeals from the adverse judgment of the
United States District Court for the District of Puerto Rico in its
suit against the Puerto Rico Highway and Transportation Authority
(the “Highway Authority”), the Puerto Rico Public Buildings
Authority (the “Buildings Authority”) (collectively, the
“Authorities”), and various officials of the Puerto Rican
government. Redondo alleges that the defendants unlawfully applied
a Puerto Rico statute retroactively to breach settlement agreements
entered into by Redondo and the Authorities before the statute was
enacted. Redondo claims that the defendants’ breach of the
agreements impaired the obligation of those contracts in violation
of the Contracts Clause of the federal Constitution and constituted
breaches of contract under Puerto Rico law.
The district court granted the defendants’ motions for
summary judgment on the Contracts Clause claim, accepting their
argument that the obligation of the agreements had not been
impaired because Redondo was not prevented from obtaining damages
if it established breaches of the agreements. Having dismissed the
sole federal claim on the merits, the district court declined to
exercise supplemental jurisdiction over Redondo’s breach of
contract claims under Puerto Rico law and dismissed them without
prejudice.
-3-
We find that the district court correctly concluded that
Redondo cannot establish its constitutional claim and therefore
affirm that portion of the judgment. We agree with Redondo,
however, that the district court exceeded its discretion in
declining to exercise jurisdiction over Redondo’s remaining claims.
Accordingly, we vacate the judgment with respect to those claims
and remand for further proceedings consistent with this opinion.
Background
On April 15, 1999, Redondo entered into a plea agreement
in United States v. Redondo Construction Corp., No. 95-391
(D.P.R.), a criminal prosecution arising out of its conduct during
performance of a construction project funded by the Federal Highway
Administration (“FHWA”). Pursuant to the agreement, Redondo
admitted to aiding and abetting the making of false statements to
the U.S. Department of Transportation and to Banco Santander de
Puerto Rico, in violation of 18 U.S.C. §§ 2, 1014, and 1020. The
agreement barred Redondo, for a one-year period beginning July 30,
1999, from bidding on, or receiving any benefit from, any contract
funded in whole or part by the FHWA. In addition, for the two
years following the one-year debarment, the agreement conditioned
Redondo’s eligibility to participate in FHWA-funded projects on
supervision by a monitor selected by the FHWA and paid for by
Redondo.
-4-
The day after Redondo entered into the plea agreement,
the Highway Authority notified Redondo that it was revoking the
bids it had awarded to the company before the guilty plea, that it
was immediately suspending the company from participating in any
bids it awarded for 30 days, and that it intended to extend the
suspension for an undetermined period. A few weeks later, on May
10, 1999, the Buildings Authority notified Redondo that it was also
barring the company from participating in any bids it awarded.
Redondo challenged both suspensions.
Redondo challenged the Buildings Authority’s suspension
in an administrative proceeding. On April 5, 2000, before
Redondo’s administrative action was resolved, Redondo and the
Buildings Authority entered into a settlement agreement that
allowed Redondo to begin bidding for Buildings Authority contracts
on April 16, 2000.
Redondo contested the Highway Authority’s suspension in
a separate administrative proceeding. On May 7, 1999, Redondo
moved for reconsideration of the suspension before the Puerto Rico
Department of Transportation and Public Works (“DTOP”). While
Redondo was challenging the Highway Authority’s suspension, Redondo
and the FHWA were negotiating an agreement (the “Monitoring Plan”)
that would govern Redondo’s obligations between July 30, 2000 and
July 30, 2002, the two-year period during which Redondo’s
eligibility to participate in FHWA-funded projects was conditioned
-5-
on supervision by an outside monitor. In late 2000, the Highway
Authority joined these talks. On November 14, 2000, while the DTOP
administrative proceeding was still pending, Redondo, the FHWA, and
the Highway Authority executed the Monitoring Plan. The same day,
Redondo and the Highway Authority entered into a settlement
agreement and jointly requested the termination of the DTOP
administrative proceeding. The agreement allowed Redondo to
participate, beginning December 11, 2000, on bids awarded by the
Highway Authority if it complied with the conditions set forth in
the Monitoring Plan.
On December 29, 2000, Puerto Rico passed Law 458. P.R.
Laws Ann. tit. 3, §§ 928-928i. The statute prohibits a government
official from awarding contracts to any natural or juridical person
who has been convicted of a crime constituting fraud, embezzlement,
or the misappropriation of public funds.1 The statute also
requires the rescission of any government contract entered into
with a party convicted of a specified offense, § 928c, and provides
that all government contracts are deemed to include a term
authorizing rescission if the counterparty is convicted of a
specified offense, § 928e. The statute expressly provides that it
does not apply to contracts entered into before it took effect:
“The provisions of this chapter shall not apply retroactively nor
1
The prohibition extends to 20 years from the date of
conviction of a felony, and to 8 years from the date of conviction
of a misdemeanor. § 928d.
-6-
shall they interfere with contracts in effect . . . .” § 928h.
Redondo had successfully bid on fourteen Buildings
Authority projects after the settlement agreement between it and
the Buildings Authority became effective on April 16, 2000. But
after Law 458 was passed, the Buildings Authority canceled ten of
the bids, including one for which it had already executed a
contract with Redondo. The Buildings Authority cited lack of
project funding as its reason for canceling the bids.
On February 14, 2001, the Highway Authority informed
Redondo that it was withdrawing its consent to the settlement
agreement and the Monitoring Plan due to Redondo’s failure to make
timely compliance with a term requiring it to deposit $25,000 into
an escrow account to fund the services of the outside monitor.
Deposition testimony of a Highway Authority official, however,
suggests that agency officials decided to terminate the settlement
agreement in an attempt to further the policy of Law 458, despite
their knowledge that the statute could not lawfully be applied
retroactively. After notifying Redondo of its decision, the
Highway Authority asked DTOP to reopen the administrative
proceeding and schedule a hearing to determine the length of
Redondo’s suspension. Redondo deposited $25,000 into the escrow
account the same day, but DTOP nonetheless granted the Highway
Authority’s request.
DTOP held the hearing requested by the Highway Authority
-7-
in late 2003. On June 22, 2004, the hearing examiner issued a
report and recommendation concluding that Redondo had not breached
the Monitoring Plan, and that the Highway Authority’s termination
of the settlement agreement and the Monitoring Plan should be
deemed ineffective. The Secretary of DTOP initially adopted the
examiner’s report, but later granted a motion for reconsideration
by the Highway Authority and determined that the Highway Authority
had validly withdrawn its consent to the settlement agreement and
the Monitoring Plan. Redondo appealed DTOP’s determination to the
Puerto Rico Court of Appeals.
On May 31, 2005, the Court of Appeals ruled that it was
not clear that Redondo had breached the Monitoring Plan, and that
even if Redondo had not timely deposited the $25,000 into the
escrow account, its breach was not sufficiently serious to justify
the Highway Authority’s unilateral termination of the settlement
agreement. The Court of Appeals ordered the Highway Authority to
comply with the terms of the settlement agreement and the
Monitoring Plan as soon as its judgment became final and
enforceable. The Highway Authority petitioned for certiorari in
the Supreme Court of Puerto Rico, but that court denied the
petition and two motions for reconsideration.
In December 2001, while Redondo was litigating the
Highway Authority’s actions in the Puerto Rico courts, it brought
this federal action challenging the actions of both the Highway
-8-
Authority and the Buildings Authority. Redondo alleged that both
Authorities had unlawfully applied Law 458 to breach their
settlement agreements with Redondo -– the Highway Authority by
withdrawing its consent to the settlement agreement and the
Monitoring Plan, and the Buildings Authority by canceling the bids
it had awarded to Redondo after the settlement agreement between
them became effective. Redondo claimed that the Authorities’
actions violated the Contracts Clause of the federal Constitution.
Redondo also asserted breach of contract claims under Puerto Rico
law, claiming that the Authorities’ actions breached the settlement
agreements and that the Buildings Authority’s cancellation of the
bids it had awarded to Redondo constituted independent breaches of
contract. Redondo sought monetary and injunctive relief.2
In January 2003, the district court granted the Highway
Authority’s motion to stay proceedings pending resolution of the
administrative proceeding before DTOP. Proceedings in the district
court resumed after the Puerto Rico Court of Appeals ruled in May
2005 that the Highway Authority’s termination of the settlement
agreement was invalid. But the case stalled for a year and a half
while it was successively reassigned to three judges. The district
court eventually issued a scheduling order in January 2007 granting
the parties until April 30, 2007 to submit dispositive motions.
2
Redondo filed for bankruptcy protection on March 19, 2002,
in the United States Bankruptcy Court for the District of Puerto
Rico.
-9-
The parties engaged in extensive discovery and, pursuant to the
scheduling order, exchanged expert reports. Of the 15 depositions
Redondo took, all but a few were taken in English.
On April 30, 2007, the Highway Authority and the
Buildings Authority each moved for summary judgment on Redondo’s
Contracts Clause claim and argued that the district court should
decline to exercise supplemental jurisdiction over Redondo’s local
law claims if it dismissed the federal claim.
The motions remained pending in December 2007. On
December 24, 2007, Redondo wrote a letter to the district court
explaining that the parties could not submit a joint proposed pre-
trial order by early January, as the court had ordered, without a
ruling on the summary judgment motions. In a brief order, the
court instructed the parties to submit the proposed order by early
January even if it had not yet ruled on the pending motions. After
spending considerable time reaching agreement on factual
stipulations and exhibits to be offered at trial, the parties
submitted a proposed pre-trial order on January 11, 2008.
At a pre-trial conference on January 16, the court
scheduled a final settlement conference for January 25. Trial was
to begin February 11 and was expected to take three weeks. At the
settlement conference on January 25, the court reaffirmed the
February 11 trial date and instructed the parties to submit marked
exhibits to a deputy clerk by February 6. To meet the deadline,
-10-
Redondo’s counsel reviewed hundreds of documents and commissioned
the translation of some that had not yet been translated into
English. In preparation for the impending trial date, Redondo also
incurred expenses to serve subpoenas on several witnesses and make
travel arrangements for others.
On February 7, 2008, four days before trial was scheduled
to begin, the district court granted the Authorities’ summary
judgment motions and dismissed the complaint. The court
acknowledged that the lawfulness of the Highway Authority’s
termination of the settlement agreement had been fully litigated in
the Puerto Rico courts and that the Puerto Rico Court of Appeals’
judgment that the Highway Authority had breached the settlement
agreement was conclusive. Nevertheless, the court ruled, Redondo
had no claim under the Contracts Clause because neither Law 458,
nor any other government action, absolved the Authorities of the
duty to pay damages for breach of the settlement agreements. Thus,
Redondo could not show that an obligation of either contract had
been impaired. Noting that “[i]t is well settled that a district
court may decline to exercise supplemental jurisdiction when all
federal law claims have been dismissed,” the court dismissed
without prejudice Redondo’s claims under Puerto Rico law.
On February 22, 2008, Redondo moved under Federal Rule of
Civil Procedure 59(e) for reconsideration of the judgment. The
-11-
district court denied the motion on September 28, 2009. Redondo
timely appealed.
Discussion
Redondo argues that the district court erred in awarding
summary judgment to the defendants on its Contracts Clause claim
and in declining, on the eve of trial, to exercise supplemental
jurisdiction over its claims under Puerto Rico law. Because the
district court’s analysis of the Contracts Clause claim was
correct, we affirm the judgment on that claim. We vacate the
judgment on the other claims, however, because we conclude the
district court was not at liberty under these unusual circumstances
to decline to adjudicate the local law claims.
A. The Contracts Clause Claim
We review de novo a grant of summary judgment. Alliance
of Auto. Mfrs. v. Gwadosky, 430 F.3d 30, 34 (1st Cir. 2005). We
will uphold the judgment if the evidence, viewed in the light most
favorable to the party against whom it was entered, demonstrates
that there are no genuine issues of material fact and that judgment
is warranted as a matter of law. Fed. R. Civ. P. 56(c); Auto
Mfrs., 430 F.3d at 34.
Redondo claims that the Authorities breached the
settlement agreements in a de facto attempt to retroactively
enforce Law 458 against it. Redondo contends that although neither
Authority cited Law 458 as the reason for its alleged breach, there
-12-
is sufficient evidence in the record from which a jury could
reasonably find that the Authorities’ true motive for breaching the
contracts was a desire to apply Law 458 to Redondo, notwithstanding
the statute’s express proviso against its retroactive application.
Therefore, Redondo argues, the district court erred in granting
summary judgment to the defendants on its Contracts Clause claim.
Redondo misunderstands the nature of the restriction
imposed by the Contracts Clause. Article I, § 10 of the
Constitution prohibits a state from “pass[ing] any . . . Law
impairing the Obligation of Contracts.”3 The clause does not bar
a state from merely breaching a contract, which is the prerogative
of any private party, subject to liability for the breach. See TM
Park Ave. Assocs. v. Pataki, 214 F.3d 344, 348-49 (2d Cir. 2000);
Horwitz-Matthews, Inc. v. City of Chicago, 78 F.3d 1248, 1250 (7th
Cir. 1996) (“It would be absurd to turn every breach of contract by
a state or municipality into a violation of the federal
Constitution.”). A contract creates alternative obligations:
performance or payment of damages for breach. See Oliver Wendell
Holmes, “The Path of the Law,” 10 Harv. L. Rev. 457, 462 (1897).
If a state breaches a contract but does not impair the
counterparty’s right to recover damages for the breach, the state
has not impaired the obligation of the contract. See Hays v. Port
of Seattle, 251 U.S. 233, 237 (1920); cf. Casey v. DePetrillo, 697
3
The defendants do not contest that the Contracts Clause
binds Puerto Rico, even though it is not a state.
-13-
F.2d 22, 23 (1st Cir. 1983) (holding that public employees’ claim
that breach of their employment agreements constituted a taking of
property without just compensation was “at bottom, a simple action
for breach of contract” because there was no showing that the state
would fail to provide a remedy for a demonstrated breach of
contract).
Applying these principles, any breach of the settlement
agreements by the Authorities did not violate the Contracts Clause,
even if committed in an attempt to unlawfully enforce Law 458
retroactively against Redondo. To establish a Contracts Clause
claim, Redondo must show more than a breach of the settlement
agreements; it must show that the defendants have somehow impaired
its ability to obtain a remedy for a demonstrated breach. See
Crosby v. City of Gastonia, 635 F.3d 634, 640 (4th Cir. 2011)
(explaining that the Contracts Clause “provides no basis to
complain of an alleged impairment in the first instance,” but
supports a claim “where a state . . . has foreclosed the imposition
of an adequate remedy for an established impairment”). Redondo has
not alleged any such impairment, and we see evidence of none in the
record.
No action of the defendants, and nothing in Law 458,
prevents Redondo from obtaining a remedy for a demonstrated breach
of the settlement agreements. Redondo is free to sue the
Authorities for breach of the settlement agreements, and has indeed
-14-
done so by bringing the local law claims asserted in this action.
Neither Authority has asserted as an affirmative defense that it is
excused by Law 458, or any other Puerto Rico legislative action,
from compensating Redondo in damages if Redondo establishes a
breach of contract. Nor has any court ruled that Redondo has no
entitlement to compensation in damages if it succeeds in showing
breach of the settlement agreements. Accordingly, there has been
no violation of the Contracts Clause and the district court
properly granted summary judgment to the defendants on the
Contracts Clause claim.
B. The Claims Under Puerto Rico Law
The district court explained its dismissal of Redondo’s
claims under Puerto Rico law by noting, “It is well-settled that a
district court may decline to exercise supplemental jurisdiction
when all federal claims have been dismissed.” While this is so in
most circumstances, it is not an altogether correct statement of
the law.
The Supreme Court indeed said in United Mine Workers v.
Gibbs, 383 U.S. 715, 726 (1966), that “if the federal claims are
dismissed before trial, . . . the state claims should be dismissed
as well.” The Supreme Court, however, has repeatedly clarified
that its statement in Gibbs “does not establish a mandatory rule to
be applied inflexibly in all cases.” Carnegie-Mellon Univ. v.
Cohill, 484 U.S. 343, 350 n.7 (1988); see also Rosado v. Wyman, 397
-15-
U.S. 397, 403-05 (1970). Rather, a district court must exercise
“informed discretion” when deciding whether to assert supplemental
jurisdiction over state law claims. Roche v. John Hancock Mutual
Life Ins. Co., 81 F.3d 249, 256-57 (1st Cir. 1996). No categorical
rule governs the analysis; a court must weigh concerns of comity,
judicial economy, convenience, and fairness. See id. at 257;
Carnegie-Mellon, 484 U.S. at 350 (observing that this analysis is
prescribed by Gibbs).
It is true that “in the usual case in which all federal-
law claims are eliminated before trial, the balance of factors
. . . will point toward declining to exercise jurisdiction over the
remaining state-law claims.” Carnegie-Mellon, 484 U.S. at 350 n.7
(emphasis added) (explaining that the Gibbs court was referring to
the usual case, not every case, when it stated that state law
claims should be dismissed if the federal claims are dismissed
before trial). But that observation does not relieve the district
court of its obligation to consider the relevant factors to
determine whether the exercise of supplemental jurisdiction is
appropriate in the particular case before it. As we have stressed,
the proper inquiry is “pragmatic and case-specific.” Roche, 81
F.3d at 257.
Here, in our view, the relevant factors did not merely
support the propriety of the exercise of supplemental jurisdiction.
Interests in judicial economy, convenience, and fairness weighed
-16-
overwhelmingly in favor of the court’s exercising its jurisdiction.
The district court declined to exercise supplemental jurisdiction
only four days before trial was scheduled to begin, when the action
had been pending in federal court for more than six years, the
summary judgment record had been complete for nearly a year, and
the parties were almost completely prepared for trial.
Moreover, nearly all of the extensive discovery taken was
relevant not only to Redondo’s constitutional claim, but also to
its claims under Puerto Rico law. Redondo’s breach of contract
claims rested on virtually the same factual basis as did its
Contracts Clause claim. Although the federal and Puerto Rico
claims invoked slightly different legal theories, both complained
of the defendants’ violation of Redondo’s contract rights, and both
sought essentially the same relief. See Tomaiolo v. Mallinoff, 281
F.3d 1, 11 (1st Cir. 2002) (finding that exercise of supplemental
jurisdiction “furthered judicial economy” because “all claims arose
from the same core of facts”).
Refusal to exercise jurisdiction over the local law
claims would impose huge burdens on Redondo because the extensive
discovery for the expected federal court trial had been conducted
in English. Puerto Rico’s courts operate in Spanish. Thus, to
litigate the claims in the Puerto Rico courts, Redondo would need
to bear the cost of translating the documents and testimony
produced or taken in English, or of redoing extensive discovery in
-17-
Spanish. In addition, all of Redondo’s trial preparation was done
with a view to a trial conducted in English. Much of its work
would have needed to be redone or translated for use in a Puerto
Rico court.
Given the age and advanced stage of the litigation, the
common factual basis for Redondo’s claims under Puerto Rico and
federal law, and the enormous expense Redondo would incur in
redoing the discovery and trial preparation so as to try the non-
federal claims in courts that operate in a different language, the
district court’s decision to send the parties to the Puerto Rico
courts to begin all over again was both wasteful and enormously
harmful to Redondo.
Consideration of principles of comity does not change the
analysis. As the district court recognized, Puerto Rico courts had
already ruled that the Highway Authority’s “withdrawal of consent”
to the settlement agreement was invalid, leaving unresolved only
the issue of whether Redondo was entitled to damages for the
Highway Authority’s breach, and if so, how much. As for Redondo’s
breach of contract claims against the Buildings Authority, they
raised no thorny or unresolved issues of Puerto Rico law. Federal
courts in Puerto Rico exercising diversity jurisdiction routinely
apply the well-established principles of contract law and damages
calculation that govern Redondo’s breach of contract claims. The
-18-
comity concerns raised by the exercise of supplemental jurisdiction
at this stage are negligible.
In Roche v. John Hancock Mutual Life Ins. Co., 81 F.3d
249, 257 (1st Cir. 1996), we approved the district court’s exercise
of supplemental jurisdiction because “[t]he litigation had matured
well beyond its nascent stages, discovery had closed, the summary
judgment record was complete, the federal and state claims were
interconnected, and powerful interests in both judicial economy and
fairness tugged in favor of retaining jurisdiction.” We therefore
found the district court’s exercise of jurisdiction in that case to
be “squarely within the realm of its discretion.” Id. For very
much the same reasons, as explained above, we conclude that it was
not within the district court’s permissible range of discretion to
decline to exercise jurisdiction over Redondo’s local law claims.4
Conclusion
For the foregoing reasons, we affirm the dismissal of
Redondo’s claim under the Contracts Clause and vacate the dismissal
of its claims under Puerto Rico law. The case is remanded to the
district court for further proceedings consistent with this
4
After the district court dismissed Redondo’s local law
claims, Redondo refiled the claims in a Puerto Rico court. The
defendants argue that Redondo’s appeal of the dismissal of its
local law claims is therefore moot and that, in any event, federal
court abstention is required by the Colorado River doctrine. We
find no merit in either argument.
-19-
opinion.5 Costs are denied at this time pending the conclusion of
the litigation.
So ordered.
5
Redondo’s motion to supplement the record on appeal (which
was styled as a request that we take judicial notice of certain
statements by the Highway Authority) is denied. In any event,
consideration of the submitted statements would not have affected
the disposition of the appeal.
-20-