Case: 11-30380 Document: 00511758696 Page: 1 Date Filed: 02/14/2012
IN THE UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT United States Court of Appeals
Fifth Circuit
FILED
February 14, 2012
No. 11-30380 Lyle W. Cayce
Clerk
CUTTING UNDERWATER TECHNOLOGIES USA, INCORPORATED,
Plaintiff
v.
ENI U.S. OPERATING COMPANY; ENI PETROLEUM U.S., L.L.C.,
Defendants – Cross Claimants –
Appellants
v.
T. BAKER SMITH, INCORPORATED,
Counter Defendant – Appellee
Appeal from the United States District Court
for the Eastern District of Louisiana
Before KING, WIENER, and HAYNES, Circuit Judges.
PER CURIAM:
Appellants Eni U.S. Operating Company and Eni Petroleum U.S., L.L.C.,
appeal from the district court’s grant of summary judgment in favor of Appellee
T. Baker Smith, Inc. The appeal concerns construction and application of the
Louisiana Oil Well Lien Act, LA. REV. STAT. ANN. § 9:4861, et seq. (2007), on an
issue of first impression. The district court authored a thorough and well-
Case: 11-30380 Document: 00511758696 Page: 2 Date Filed: 02/14/2012
No. 11-30380
reasoned opinion concerning the substantive issues1 presented, which we attach
and adopt as the opinion of this court. Cutting Underwater Techs. USA, Inc. v.
Con-Dive, L.L.C., Civil Action No. 2:09-CV-387, 2011 WL 1103679, 2011 U.S.
Dist. LEXIS 29325 (E.D. La. Mar. 22, 2011).
AFFIRMED.
1
The conclusions in Section III.A. of the district court opinion, concerning evidentiary
objections, were not appealed; we therefore need not express an opinion as to those matters.
2
Case: 11-30380 Document: 00511758696 Page: 3 Date Filed: 02/14/2012
No. 11-30380
UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF LOUISIANA
CUTTING UNDERWATER TECHNOLOGIES *CIVIL ACTION
USA, INC. *
* NO. 09-387
VERSUS *
* SECTION "L"(2)
CON-DIVE, LLC ET AL. *
ORDER & REASONS
Before the Court is a Motion for Summary Judgment (Rec. Doc. No. 83) filed by T.
Baker Smith, Inc. (TBS), a Motion for Summary Judgment (Rec. Doc. No. 75) filed by Eni
U.S. Operating Co. and Eni Petroleum U.S., LLC (collectively Eni), and a Motion to Strike
the Affidavit of Scot Childress (Rec. Doc. No. 101) filed by TBS. The Court has reviewed
the submitted memoranda and the applicable law and is ready to rule. For the following
reasons, TBS’s motion for summary judgment is granted, and Eni’s cross-motion is denied.
In addition, the motion to strike is treated as an objection and sustained in part and overruled
in part.
3
Case: 11-30380 Document: 00511758696 Page: 4 Date Filed: 02/14/2012
No. 11-30380
I. BACKGROUND AND PROCEDURAL HISTORY
This case arises out of contracts for the provision of services in connection with the removal
of a toppled platform on the Outer Continental Shelf (OCS).1 In September 2005, Hurricane Rita
toppled and dismantled the Vermilion Block 313-A platform located offshore Vermilion Parish,
Louisiana. At that time, the platform was no longer in service, the oil and gas wells to which it was
connected had been plugged, and the casings connecting the wells to the platform had been cut. In
March 2007, Dominion Exploration & Production, Inc., the then-lessee, entered into a contract with
Con-Dive, LLC, under which Con-Dive agreed to remove the toppled platform. In turn, Con-Dive
subcontracted various work to T. Baker Smith, Inc. (TBS), Cutting Underwater Technologies USA,
Inc., and Cheramie Marine LLC. In its contract with Dominion, Con-Dive warranted that it would
not allow any liens to be asserted over Dominion’s property.
In June 2007, Dominion conveyed 50 percent of its record title and operating rights in the
lease to Eni Petroleum. Together with Eni Operating, Eni Petroleum also acquired all of Dominion’s
contractual rights and obligations relating to the lease. Con-Dive eventually failed to pay TBS and
the other subcontractors for the services they rendered. In response, in October 2008, Cutting
Underwater filed suit in state court against Con-Dive. In November and December 2008, TBS,
Cutting Underwater, and Cheramie Marine also recorded liens over Eni’s property in the records of
Vermilion Parish. In January 2009, Cutting Underwater amended its state court petition, adding Eni
as defendant. In its petition, Cutting Underwater asked that Con-Dive be held liable for breach of
contract and that its lien over Eni’s property be recognized as valid under the Louisiana Oil Well
Lien Act (LOWLA), La. Rev. Stat. Ann. § 9:4861 et seq.
1
This factual background reflects the allegations made in the pleadings of Eni and
TBS. This section should not be construed as findings of fact.
4
Case: 11-30380 Document: 00511758696 Page: 5 Date Filed: 02/14/2012
No. 11-30380
Eni subsequently removed the suit to this Court on the basis of federal-question jurisdiction
under the Outer Continental Shelf Lands Act, 43 U.S.C. § 1331 et seq. A flurry of pleadings were
then filed, resulting in various additional claims being asserted. In particular, Eni made claims
against Con-Dive for breach of contract and against Cutting Underwater, TBS, and Cheramie Marine
for invalid liens under LOWLA.2 Similarly, TBS and Cheramie Marine asserted claims against Con-
Dive for breach of contract and against Eni for recognition and enforcement of their liens.3 In
September 2009, Cheramie Marine settled all of the claims that were asserted by it and against it,
and in October 2009, Cutting Underwater did the same. This left in place the lien-related claims that
TBS and Eni asserted against each other, as well as the breach-of-contract claims that TBS and Eni
asserted against Con-Dive.
In January 2010, TBS filed a motion for summary judgment on its breach-of-contract claim
against Con-Dive. In February 2010, the Court granted the motion as unopposed and, on the motion
of TBS, entered judgment pursuant to Federal Rule of Civil Procedure 54(b). Since then, however,
Con-Dive has not satisfied that judgment. As a result, the dispute between TBS and Eni regarding
the validity of TBS’s lien remains pending, and it is that which is the subject of the present motions.4
2
Although Eni styled its claims against TBS and Cheramie Marine as counterclaims,
they are more appropriately viewed as third-party claims, for TBS and Cheramie Marine were
not parties in this case before Eni asserted claims against them and thereby impleaded them
as third-party defendants. See Fed. R. Civ. P. 14.
3
TBS’s pleading does not expressly name Eni as a counter-defendant, but paragraph
17 of its counterclaim and its prayer for relief indicate that it has instituted an action against
Eni for the recognition and enforcement of its lien under LOWLA. See TBS Answer (Rec. Doc.
No. 30). Eni has understood TBS to have asserted such a claim, and accordingly, it has filed
an answer to that claim. See Eni Answer (Rec. Doc. No. 31).
4
In seeking recognition and enforcement of its lien, TBS also asserts that it is entitled
to the cost of preparing and filing the lien and to attorney’s fees pursuant to La. Rev. Stat.
Ann. § 9:4862(B). The Court does not reach these issues, which were not addressed in the
parties’ motions.
5
Case: 11-30380 Document: 00511758696 Page: 6 Date Filed: 02/14/2012
No. 11-30380
II. PRESENT MOTIONS
A. Cross-Motions for Summary Judgment
In its Motion for Summary Judgment and its opposition to TBS’s cross-motion, Eni argues
that TBS’s lien is invalid because it did not perform an “operation” within the meaning of LOWLA.
La. Rev. Stat. Ann. §§ 9:4861(4)(a), 9:4862(A)(1). In particular, Eni asserts that the work undertaken
by TBS was neither performed “for the purpose of . . . abandoning a well” nor done “on a well site.”
Id. § 9:4861(4)(a). Eni argues that the wells attached to the Vermilion Block 313-A platform had
been plugged and that the casings that connected the platform to the wells had been cut in 1999.
According to Eni, this forecloses a finding that any work subsequently performed involves
“abandoning a well.” Id. Eni also contends that for work to be performed “on a well site,” it must
have been “physically carried out” on such a site.
In its own Motion for Summary Judgment and its opposition to Eni’s cross-motion, TBS
asserts that its lien is valid under LOWLA, and it disputes both of the arguments raised by Eni. TBS
states that the work that it performed was a necessary part of “abandoning a well” within the
meaning of the statute. TBS emphasizes that once wells connected to a platform are no longer in
production, the applicable federal regulations require the lessee not only to plug the wells, but also
to remove the production platform. TBS argues that in light of this requirement, the work that it
performed is part and parcel of the process by which Eni abandoned the depleted wells. In addition,
TBS asserts that the work it performed was on a “well site” as defined by LOWLA because it was
present in Vermilion Block 313 near the vicinity of the platform in order to deliver the survey and
positioning services that it was asked to provide.
6
Case: 11-30380 Document: 00511758696 Page: 7 Date Filed: 02/14/2012
No. 11-30380
B. Motion to Strike the Affidavit of Scot Childress
Separately, TBS has filed a Motion to Strike the Affidavit of Scot Childress, which
Eni has supplied along with its Motion for Summary Judgment (Rec. Doc. No. 75-6). TBS
specifically objects to paragraph 11 of the affidavit on the ground that it states an ultimate
conclusion in this case. TBS also challenges paragraphs 7 through 13 of the affidavit on the
ground that the statements are not based on personal knowledge. Eni opposes the motion. Eni
argues that Mr. Childress’s statement in paragraph 11 does not state an ultimate conclusion.
It also asserts that given Mr. Childress’s employment with Dominion and Eni, he has
personal knowledge to testify as to the matters addressed in paragraphs 7 through 13 of his
affidavit.
III. LAW AND ANALYSIS
TBS’s Motion to Strike affects the scope of the record that is to be considered in
deciding the parties’ cross-motions for summary judgment. Accordingly, the Court will first
address that motion and then discuss the cross-motions.
A. Motion to Strike the Affidavit of Scot Childress
Rule 56 of the Federal Rules of Civil Procedure allows a party to provide an affidavit
to support or oppose a motion for summary judgment. See Fed. R. Civ. P. 56(c)(1)(A). Such
affidavits, however, “must be made on personal knowledge, set out facts that would be
admissible in evidence, and show that the affiant . . . is competent to testify on the matters
stated.” Id. 56(c)(4). Prior to December 1, 2010, the proper method by which to attack an
affidavit was by filing a motion to strike. See, e.g., Rushing v. Kan. City S. Ry. Co., 185 F.3d
7
Case: 11-30380 Document: 00511758696 Page: 8 Date Filed: 02/14/2012
No. 11-30380
496, 506 (5th Cir. 1990), superseded on other grounds by Fed. R. Evid. 103(a); see also 10B
Charles Alan Wright & Arthur R. Miller, Federal Practice and Procedure § 2738 (3d ed.
2004). Under the now-applicable Rule 56(c)(2),5 however, it is no longer necessary for a
party to file such a motion; instead, the party may simply object to the material. See Fed. R.
Civ. P. 56 advisory committee’s note to 2010 amendments (“There is no need to make a
separate motion to strike.”). In light of this change, TBS’s Motion to Strike will be treated
as an objection.
As noted above, TBS objects to paragraph 11 of Mr. Childress’s affidavit on the
ground that it states an ultimate conclusion. Though resisted by Eni, this argument has merit.
Indeed, “ultimate or conclusory facts and conclusions of law . . . cannot be utilized on a
summary-judgment motion.” Wright & Miller, supra, § 2738; see also Galindo v. Precision
Am. Corp., 754 F.2d 1212, 1221 (5th Cir. 1985). Here, one of the questions that is presented
by the cross-motions is whether the work that TBS performed is an “activity for the purpose
of drilling, completing, testing, producing, reworking, or abandoning a well” and thus an
“operation” within the meaning of LOWLA. See La. Rev. Stat. Ann. § 9:4861(4)(a)(i).
Answering this question requires the Court to interpret the statutory phrase “abandoning a
well” and then apply that interpretation to the facts of this case.6
5
Rule 56(c)(2) provides that “[a] party may object that the material cited to support
or dispute a fact cannot be presented in a form that would be admissible in evidence.” Fed. R.
Civ. P. 56(c)(2).
6
This matter is on cross-motions for summary judgment. Ordinarily, this would
require the Court to resolve the disputed facts in favor of TBS with respect to Eni’s motion and
to resolve the disputed facts in favor of Eni with respect to TBS’s motion. As noted below,
however, the facts that are determinative of this question are not disputed.
8
Case: 11-30380 Document: 00511758696 Page: 9 Date Filed: 02/14/2012
No. 11-30380
In paragraph 11 of his affidavit, Mr. Childress states that none of the work performed
by TBS “involved drilling, completing, testing, producing, reworking, or abandoning any of
the wells.” Eni’s Ex. 2 para 11 (Rec. Doc. No. 75-6). Eni contends that a statement by Mr.
Childress that TBS performed an “operation” would be an ultimate conclusion, but that his
statement that TBS did not do work that involved “abandoning any of the wells” is merely
“a statement of the facts as [Mr. Childress] understands them.” This is not a persuasive
argument. Given how remarkably close Mr. Childress’s statement tracks the language of the
relevant statute, it is difficult not to understand his averment as one that directly states an
answer to the critical question in this case.7 To the extent that paragraph 11 thus states an
ultimate conclusion, it is not proper summary judgment evidence and must be disregarded.
TBS also challenges paragraphs 7 through 10, as well as paragraphs 12 and 13, of Mr.
Childress’s affidavit on the ground that Mr. Childress does not have the personal knowledge
to make the statements contained in those paragraphs. This contention is unavailing. Personal
knowledge may be demonstrated by showing that the facts stated “reasonably” fall within the
“‘sphere of responsibility’” of the affiant as a corporate employee. DIRECTV, Inc. v. Budden,
420 F.3d 521, 530 (5th Cir. 2005) (quoting Hodges v. Exxon Corp., 563 F. Supp. 667, 669
(M.D. La. 1983)); see also Rutledge v. Liab. Ins. Indus., 487 F. Supp. 5, 7 (W.D. La. 1979)
(“An official title alone is enough to indicate the basis of personal knowledge . . . .”).
Moreover, personal knowledge does not necessarily mean contemporaneous knowledge. See
7
It would be a different situation had Mr. Childress stated in his affidavit that, for
instance, the term “abandoning a well” has a particular technical meaning and that the work
performed by TBS does not fall within the scope of that technical meaning.
9
Case: 11-30380 Document: 00511758696 Page: 10 Date Filed: 02/14/2012
No. 11-30380
Dalton v. FDIC, 987 F.2d 1216, 1223 (5th Cir. 1993). Here, Mr. Childress’s affidavit and his
deposition indicate that during the relevant time period, he has been the manager of
production operations for the lease at issue. See Eni’s Ex. 2 (Rec. Doc. No. 75-6); Eni’s Ex.
2 (Rec. Doc. No. 110-1). This is a sufficient basis upon which to infer that Mr. Childress has
personal knowledge of the facts contained in those paragraphs.
In addition, the record reveals that Mr. Childress was designated as the representative
of Eni under Rule 30(b)(6) of Civil Procedure. See Eni’s Ex. 2 (Rec. Doc. No. 110-1). Under
that rule, a corporate designee “does not testify as to his personal knowledge or perceptions.”
Brazos River Auth. v. GE Ionics, Inc., 469 F.3d 416, 434 (5th Cir. 2006). Rather, “he testifies
‘vicariously,’ for the corporation, as to its knowledge and perceptions.” Id. (quoting
Resolution Trust Corp. v. S. Union, 985 F.2d 196, 197 (5th Cir. 1993)). There is no
indication, beyond the mere fact that Mr. Childress had not reviewed certain documents, that
he was unprepared to testify as to the matters addressed in paragraphs 7 through 10, as well
as 12 and 13, of his affidavit. Thus, Mr. Childress’s status as the designee of Eni further
indicates that these statements constitute competent summary judgment evidence.
Accordingly, the Court concludes that TBS’s objection to the affidavit of Mr. Childress
under Rule 56(c)(2) is to be sustained as to paragraph 11, but overruled in all other respects.
B. Cross-Motions for Summary Judgment on the Validity of TBS’s Lien
Having addressed TBS’s Motion to Strike, the Court is now ready to discuss the cross-
motions for summary judgment. The Court will first describe the generally applicable
10
Case: 11-30380 Document: 00511758696 Page: 11 Date Filed: 02/14/2012
No. 11-30380
standard of review for motions for summary judgment. The Court will then analyze the
applicable law and answer the two key questions that the parties have raised in their briefs.
1. Standard of Review
A district court can grant a motion for summary judgment only when “the movant
shows that there is no genuine dispute as to any material fact and the movant is entitled to
judgment as a matter of law.” Fed. R. Civ. P. 56(a). When considering a motion for summary
judgment, the district court “will review the facts drawing all inferences most favorable to
the party opposing the motion.” Reid v. State Farm Mut. Auto. Ins. Co., 784 F.2d 577, 578
(5th Cir. 1986). The court must find “[a] factual dispute . . . [to be] ‘genuine’ if the evidence
is such that a reasonable jury could return a verdict for the nonmoving party . . . [and a] fact
. . . [to be] ‘material’ if it might affect the outcome of the suit under the governing
substantive law.” Beck v. Somerset Techs., Inc., 882 F.2d 993, 996 (5th Cir. 1989) (citing
Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986)).
“If the moving party meets the initial burden of showing that there is no genuine issue
of material fact, the burden shifts to the non-moving party to produce evidence or designate
specific facts showing the existence of a genuine issue for trial.” Engstrom v. First Nat'l
Bank of Eagle Lake, 47 F.3d 1459, 1462 (5th Cir. 1995). The mere argued existence of a
factual dispute will not defeat an otherwise properly supported motion. See Anderson, 477
U.S. at 248. “If the evidence is merely colorable, or is not significantly probative,” summary
judgment is appropriate. Id. at 249-50 (citations omitted).
11
Case: 11-30380 Document: 00511758696 Page: 12 Date Filed: 02/14/2012
No. 11-30380
2. The Validity of the Lien
a. The applicable law
This Court has subject matter jurisdiction over the instant matter pursuant to the Outer
Continental Shelf Lands Act (OCSLA). See 43 U.S.C. § 1349(b)(1). In enacting that statute,
Congress declared that the United States has jurisdiction over the seabed and subsoil of the
OCS. See id. § 1332(1). Congress also “extended” the application of federal law to the OCS
“as if the [OCS] were an area of exclusive Federal jurisdiction located within a State.” Id.
§ 1333(a)(1). Finally, Congress declared that “[t]o the extent that they are applicable and not
inconsistent with [federal law],” the laws of the adjacent states are “the law[s] of the United
States” on the OCS. Id. § 1333(a)(2)(A). As the Supreme Court has explained, this last
provision reflects Congress’s recognition that “the Federal Code was never designed to be
a complete body of law in and of itself,” Rodrigue v. Aetna Cas. & Sur. Co., 395 U.S. 352,
358 (1969), and that as a consequence, there is a need “to fill the substantial ‘gaps’ in the
coverage of federal law,” Gulf Offshore Co. v. Mobil Oil Corp., 453 U.S. 473, 480 (1981).
Thus, under the OCSLA, state law may be applicable to disputes arising out of the OCS,
albeit “only as surrogate federal law.” Rodrigue, 395 U.S. at 357.
The Louisiana Oil Well Lien Act (LOWLA) was significantly revised in 1995. See
La. Rev. Stat. Ann. § 9:4861 historical and statutory notes; see also Patricia H. Chicoine, Lien on
LOWLA; It’s a Privilege: Recent Revisions to the Louisiana Oil Well Lien Act, 57 La. L. Rev. 1133,
1133 (1997). The revisions have not, however, disturbed the view of the Fifth Circuit that
LOWLA is applicable as federal surrogate law under the OCSLA. Compare Wilson Indus.,
12
Case: 11-30380 Document: 00511758696 Page: 13 Date Filed: 02/14/2012
No. 11-30380
Inc. v. Aviva Am. Inc., 185 F.3d 492, 493-94 & nn. 1 & 3 (5th Cir. 1999) (applying revised
statute), with Gardes Directional Drilling v. U.S. Turnkey Exploration Co., 98 F.3d 860, 864-
66 (5th Cir. 1996) (applying previous statute), and Union Tex. Petroleum Corp. v. PLT
Eng’g, Inc., 895 F.2d 1043, 1050-51 (5th Cir. 1990) (same). Both TBS and Eni have also
assumed that LOWLA applies. Accordingly, the Court concludes that LOWLA is applicable
as federal law in this case.
Under LOWLA, a subcontractor may assert a lien over the property of an operator or
lessee in order to secure “the price of his contract for operations.” La. Rev. Stat. Ann. §
9:4862(A)(1).8 By making available this privilege, the statute aims to “protect
[subcontractors] from the default of those who engage them.” Guichard Drilling Co. v.
Alpine Energy Servs., Inc., 657 So.2d 1307, 1312 (La. 1995). As the Louisiana Supreme
Court has observed, the statute reflects the “policy decision that the lease owners are in a far
better position to ensure payment for the subcontractor’s services than is the subcontractor,
and that the onus should be on the lease owners to ensure that the contractor it hires is solvent
and that it actually makes payment to the subcontractor.” Id. at 1313. The statute “clearly
8
The statute refers to “contractors,” La. Rev. Stat. Ann. § 9:4862(A)(1), but it broadly
defines that term as including “a person . . . who, by subcontract with a contractor of the
operator . . . , contracts to perform all or part of the operations contracted for by the operator,”
id. § 9:4861(10). The term “operator” means “a lessee who is personally bound by contract . .
. to a contractor from whom the claimant’s activities giving rise to the privilege emanate.” Id.
§ 9:4861(7). A “lessee” is “a person who owns an operating interest.” Id. § 9:4861(6). Eni and
TBS do not disagree that Eni is a “lessee” within the meaning of LOWLA. In addition, if the
platform removal project is an “operation,” then Eni is an “operator” and TBS is a “contractor”
within the meaning of the statute.
13
Case: 11-30380 Document: 00511758696 Page: 14 Date Filed: 02/14/2012
No. 11-30380
place[s] the risk of the contractor’s insolvency or failure to pay on those with an interest in
the lease.” Id. at 1312-13.
Of course, LOWLA applies only to “operations” encompassed by the statute. La. Rev.
Stat. Ann. § 9:4862(A)(1). Here, the critical question is whether TBS has performed such
“operations.” Id. The statute defines that term as including “every activity conducted by or
for a lessee on a well site for the purpose of drilling, completing, testing, producing,
reworking, or abandoning a well.” Id. § 9:4861(4)(a)(i). In this case, TBS and Eni dispute
whether the work that TBS performed falls within this definition. In particular, Eni argues
that the work that TBS performed was neither done “for the purpose of . . . abandoning a
well” nor performed “on a well site.” Id. TBS rejects this contention. It asserts that the work
it performed was done “for the purpose of . . . abandoning a well” and done “on a well site.”
Id. The Court will address these issues in turn.
b. Whether the work done was “for the purpose of . . . abandoning a well”
In their briefs, Eni and TBS have presented divergent views of the statutory phrase
“every activity . . . for the purpose of . . . abandoning a well.” Id. As noted above, Eni argues
that the process of abandoning wells does not encompass the removal of the platform to
which the wells were connected. Eni contends that once the wells are plugged and the
conductors are cut, any additional work that is performed on the former site of production
is not work that involves “abandoning a well” within the meaning of LOWLA. TBS advances
a different view of the statutory phrase. TBS notes that once the wells that are connected to
a production platform are depleted, lessees are required by federal regulations to implement
14
Case: 11-30380 Document: 00511758696 Page: 15 Date Filed: 02/14/2012
No. 11-30380
a number of decommissioning obligations, including plugging the wells, cutting the
conductors, removing the platform, and clearing the site. TBS asserts that in light of these
requirements, work done to remove a platform is in fact part and parcel of the process of abandoning
the wells that were connected to the platform.
This is a close question, one that appears to be res nova, and both parties have
presented strong arguments. The Court, however, is persuaded that TBS has the correct view
of the statute. As one commentator has observed, “[t]he definition of ‘operations’ has been
drafted broadly.” Chicoine, supra, at 1137. Indeed, the statutory phrase is aimed at
encompassing “all typical well site activities,” including “[w]ork associated with the
abandonment of wells.” Id. at 1137-38. As further explained below, it is clear that in light
of the applicable federal regulations, the removal of a platform after the depletion of the
wells that are connected to that platform is a common well site activity, one that is, in effect,
part of the process of abandoning the wells. Accordingly, the Court concludes that work done
to remove a platform following the depletion of wells properly falls within the ambit of the
statutory term “operations.”
Federal regulations have long indicated that following well depletion, the removal of
a platform is a typical well site activity and that it is integral to the process of abandoning the
depleted wells connected to the platform. In particular, the federal regulations that have been
in effect since 2002 – and that were thus applicable at the time that TBS participated in the
project at issue – provide that “[w]hen [the] facilities are no longer useful for operations,”
the lessee “must,” among other things, “[p]ermanently plug all wells” and “[r]emove all
15
Case: 11-30380 Document: 00511758696 Page: 16 Date Filed: 02/14/2012
No. 11-30380
platforms and other facilities.” 30 C.F.R. § 250.1703.9 The predecessor regulations -- which
took effect in 1997 and were thus applicable in 1999 when the wells attached to Platform
313-A were plugged -- delineated, in a similar fashion, the decommissioning obligations of
a lessee.10 Under the heading “Abandonment of Wells,” the regulation provided that
“[l]essees must plug and abandon all well bores [and] remove all platforms or other
facilities.” Surety Bonds for Outer Continental Shelf Leases, 62 Fed. Reg. 27948, 27955
(1997) (codified at 30 C.F.R. § 250.110(b)).11 These provisions demonstrate that,
notwithstanding revisions over time, the applicable regulations have carried forward a
longstanding requirement that idle platforms be removed once oil and gas production ceases.
See, e.g., Interpretation Concerning Authority to Depart from OCS Requirements, 48 Fed.
Reg. 31397, 31397 (1983) (noting that “the rules governing OCS operations require the
removal of platforms and other structures no longer in use for oil and gas recovery”).
9
The regulations exempt lessees and operators from the requirement of removing
platforms if the structure becomes part of an artificial reef program. See 30 C.F.R. 250.1730.
10
The term “decommissioning” is the new term for “abandonment.” See Oil and Gas
and Sulphur Operations in the Outer Continental Shelf—Decommissioning Activities, 65 Fed.
Reg. 41892, 41893 (2000). Compare also Mariner Energy, Inc. v. Devon Energy Prod. Co., 690
F. Supp. 2d 558, 564 (S.D. Tex. 2010) (“Decommissioning means permanently plugging all
wells, removing all platforms and other facilities . . . and clearing the seafloor of
obstructions.”), with Howard R. Williams & Charles J. Meyers, Manual of Oil and Gas Terms
(14th ed. 2009) (defining “abandonment” as “[p]lugging a well, removal of installation, and
termination of operations for production from the well”).
11
This provision was later redesignated as 30 C.F.R. § 250.700(b), see Redesignation
of 30 C.F.R. Part 250 – Oil and Gas and Sulphur Operations in the Outer Continental Shelf,
63 Fed. Reg. 29478, 29479 (1998), and eventually removed and reserved when its now-
applicable version was codified at a different subpart of the Code of Federal Regulations in
2002, see Oil and Gas and Sulphur Operations in the Outer Continental Shelf –
Decommissioning Activities, 67 Fed. Reg. 35398, 35405 (2002).
16
Case: 11-30380 Document: 00511758696 Page: 17 Date Filed: 02/14/2012
No. 11-30380
A variety of reasons underlie the requirement that lessees remove a platform once the
wells to which it is connected are depleted. The Bureau of Energy Management, Regulation
and Enforcement (BOEMRE), which was spun off from the now-defunct Minerals
Management Service (MMS), has made the general observation that “idle infrastructure
poses a potential threat to the OCS environment.” BOEMRE, Notice to Lessees and
Operators No. 2010-G05, Decommissioning Guidance for Wells and Platform 1 (2010)
[hereinafter BOEMRE, NTL]. In particular, the presence of idle platforms may harm
navigation safety. See, e.g., National Research Council, Disposal of Offshore Platforms 53
(1985) (“The Coast Guard is especially concerned about the threat to navigation safety of
permitting offshore platforms to remain in place when they are no longer actively being used
to produce oil and gas.”). BOEMRE has also observed that if not removed in a timely
manner, an idle platform can become “a financial liability . . . if subsequently destroyed or
damaged in a future event such as a hurricane.” BOEMRE, NTL, supra, at 1.
Under the federal regulations, platform removal has become a common activity on the
Gulf of Mexico OCS. The official statistics compiled by BOEMRE underscore this reality.
See BOEMRE, Installation and Removals – Offshore Production Facilities in Federal Waters,
available at http://www.boemre.gov/stats/PDFs/OCSPlatformActivity.pdf (accessed March
22, 2011) [hereinafter BOEMRE, Statistics]. The statistics show that while the number of
platform installations dwarfed the number of platform removals for several decades,
platforms removals eventually increased such that they outnumbered platform installations
in 1992 and 1993. See id. at 1. Those were the years when the Louisiana State Law Institute
17
Case: 11-30380 Document: 00511758696 Page: 18 Date Filed: 02/14/2012
No. 11-30380
began to update LOWLA in order to make it “compatible with the ever changing character
of oil and gas operations.” Chicoine, supra, at 1134. From 1991 to 2000, there were
sufficient platforms removed from the Gulf of Mexico OCS to largely stabilize the number
of platforms in the region. See BOEMRE, Statistics, supra, at 1. And over the last decade,
platform removal has substantially outpaced platform installation, causing the number of
platforms on the Gulf of Mexico OCS to drop from a peak of 4,045 in 2001 to 3,409 in 2010.
Id.
Thus, the story of Platform 313-A is, at its core, the typical story of a platform
removed in accordance federal regulations following the end of oil and gas production. The
record indicates that by April 1999, the wells that were connected to the production platform
were plugged and the associated conductors cut. Eni’s Ex. 1 (Rec. Doc. No. 75-5). Soon
thereafter, in May 1999, a proposed plan to remove Platform 313-A, which had been first
installed in 1975, was submitted to MMS. See TBS’s Ex. 9 (Rec. Doc. No. 98-2). The
proposal suggested that well depletion was the reason for the removal of the platform. See
id.12 Although a delay subsequently ensued, another proposed plan to remove the platform
was submitted to MMS in March 2005, see TBS’s Ex. 5 (Rec. Doc. No. 98-2). That proposal
also specified that the platform was to be removed because the “[w]ells are depleted.” Id.
While Hurricane Rita caused yet another delay, TBS’s Ex. 3 (Rec. Doc. No. 98-2), in
2008, after permission to leave the platform as an artificial reef was denied, see Eni’s Ex. 2
12
The proposal states that the “[p]latform is depleted.” See TBS’s Ex. 9 (Rec. Doc. No.
98-2). The only reasonable way of understanding that statement is to conclude that it refers
to the wells themselves.
18
Case: 11-30380 Document: 00511758696 Page: 19 Date Filed: 02/14/2012
No. 11-30380
(Rec. Doc. No. 75-6), a proposal to remove the platform was once again submitted, see
TBS’s Ex. H (Rec. Doc. No. 83-3). Thus, the record demonstrates that before the platform
was eventually removed, the successive lessees of Vermilion Block 313 remained aware of
and repeatedly sought to meet their obligation to remove the platform given that the wells
that were connected to it had been depleted. See, e.g., Eni’s Ex. 2 (Rec. Doc. No. 75-6) (“The
Platform had been scheduled to be decommissioned as required by [MMS] . . . .”); TBS’s Ex.
A (Rec. Doc. No. 83-3) (acknowledging that BOEMRE “require[s] the removal of platforms
when wells are depleted”).
What may perhaps make the story of Platform 313-A somewhat unusual is the
substantial amount of time that lapsed between the plugging of the wells and the removal of
the platform that was connected to them. As noted above, the plugging of the wells took
place in 1999, but it was not until 2008 that the platform was removed. The intervention of
Hurricane Rita in 2005 may also distinguish the story of Platform 313-A from those of
others. Neither of these, however, changes the fact that under the applicable federal
regulations, the removal of a platform following the depletion of the wells that are connected
to it is a typical well site activity, one that is largely inseparable from the plugging of the
wells and thus, in effect, part and parcel of the process of abandoning the depleted wells.
In its brief, Eni argues that the wells that were connected to the platform were
“plugged and abandoned” in 1999, and it contends that any further work on the former site
of production cannot be considered part of the process of “abandoning a well.” Eni thus
suggests that the term “abandoning a well” should be equated with the term “plugging and
19
Case: 11-30380 Document: 00511758696 Page: 20 Date Filed: 02/14/2012
No. 11-30380
abandoning.” This argument does not take Eni very far, however, because the contours of the
term “plug and abandon” are unclear. As the record demonstrates, “plug and abandon,” on
the one hand, may entail only the placing of cement plugs in a well and the cutting of the
conductors. See Eni’s Ex. 11 (Rec. Doc. No. 96-25). On the other hand, as evidenced by a
host of documents prepared by Eni itself, the term may also be used to encompass a broader
swath of decommissioning activities, such as the disposal of a platform. See, e.g., TBS’s Ex.
3 (Rec. Doc. No. 98-2) (“The platform was secured for P&A prior to Rita.”); TBS’s Ex. 4
(Rec. Doc. No. 98-2) (“[T]he platform . . . was planned for P&A but was not removed due
to the hurricane.”).
The inconsistent use of the term “plug and abandon” is evident elsewhere. For
instance, other industry players have used the term to denote the full range of
decommissioning activities mandated by federal regulations. See, e.g., TBS’s Ex. 12 (Rec.
Doc. No. 98-2) (“If CNGP were to P&A the Vermilion 313 ‘A’ platform”); Mariner Energy,
Inc. v. Devon Energy Prod. Co., 690 F. Supp. 2d 558, 570 (S.D. Tex. 2010) (considering a
contract that defined “plugging and abandonment costs” as “including . . . removal and
abandonment of platforms [and] wells”). Courts too have sometimes used the term to refer
to the package of decommissioning obligations that OCS lessees must satisfy. See, e.g., In
re Tri-Union Dev. Corp., 314 B.R. 611, 615 (Bankr. S.D. Tex. 2004) (using the term
“Offshore P & A Obligations” to denote the “obligations to plug and abandon [the] offshore
wells, remove offshore oil and gas platforms, pipelines, facilities, conduct site clearance
operations, and perform additional decommissioning activities”).
20
Case: 11-30380 Document: 00511758696 Page: 21 Date Filed: 02/14/2012
No. 11-30380
Ultimately, the elusive nature, and potentially expansive scope, of the term “plug and
abandon” is perhaps most clearly demonstrated by the definition supplied in a leading
reference for this area of law. That reference defines “plug and abandon” as “the placing of
a plug in a dry hole, then abandoning the well.” Howard R. Williams & Charles J. Meyers,
Manual of Oil and Gas Terms (14th ed. 2009). What it means to place a plug in a dry hole
is, of course, fairly clear. See id. (defining “dry hole” as “[a] completed well which is not
productive of oil and/or gas or which is not productive of oil and/or gas in paying
quantities”). The definition, however, begs the question of what it then means to “abandon[]
the well.” Id. It, in effect, brings us back to the very initial question. Given the lack of clarity
that surrounds the term “plug and abandon,” the Court is reluctant to simply equate the
statutory phrase “abandoning a well” with that somewhat elusive term. Moreover, it should
be noted, to the extent that “plugging and abandoning” does denote the full range of
decommissioning activities, it indicates that platform removal does fall within the ambit of
the statute.
In its brief, Eni sets forth a related, but distinct argument. Eni notes that after the wells
were plugged and the conductors cut, the wells connected to Platform 313-A were deemed
to be “permanently abandoned.” Eni contends that having thus carried out its obligations
under what is now 30 C.F.R. §§ 250.1710-.1717, any additional work that is performed
cannot be considered as part of “abandoning a well” within the meaning of LOWLA. Eni
thus argues that the phrase “abandoning a well” is limited to the work that is required under
those sections of the Code of Federal Regulations. This argument appears to have some
21
Case: 11-30380 Document: 00511758696 Page: 22 Date Filed: 02/14/2012
No. 11-30380
force. Like the Court’s analysis above, it recognizes that LOWLA is applied in this case as
surrogate federal law, and it seeks to construct LOWLA in the light of the surrounding body
of federal law. See, e.g., La. Civ. Code art. 13 (“Laws on the same subject matter must be
interpreted in reference to each other”); Branch v. Smith, 538 U.S. 254, 281 (2003) (plurality
opinion) (noting that it is “the most rudimentary rule of statutory construction . . . that courts
do not interpret statutes in isolation, but in the context of the corpus juris of which they are
a part, including later-enacted statutes”).
But the weakness in Eni’s argument is that it does not take into account the shift in
terminology that has occurred in the applicable federal regulations. It is true that previously,
the Code of Federal Regulations had used the term “permanent abandonment.” See Oil and
Gas and Sulphur Operations in the Outer Continental Shelf, 53 Fed. Reg. 10596, 10733
(1988) (codified at 30 C.F.R. § 250.112).13 The regulations had even used the phrase “plug
and abandon.” See Surety Bonds for Outer Continental Shelf Leases, 62 Fed. Reg. 27948,
27955 (1997) (codified at 30 C.F.R. § 250.110(b)).14 But in 2002, the federal regulations
were revised, and both of these terms were discarded. See Oil and Gas and Sulphur
Operations in the Outer Continental Shelf – Decommissioning Activities, 67 Fed. Reg.
35398, 35406-35409 (2002). Since then, the applicable regulations, including those to which
13
This provision was redesignated as 30 C.F.R. § 250.702, see Redesignation of 30
C.F.R. Part 250 – Oil and Gas and Sulphur Operations in the Outer Continental Shelf, 63 Fed.
Reg. 29478, 29479 (1998), and eventually removed and reserved when the revised and now-
applicable version took effect, see Oil and Gas and Sulphur Operations in the Outer
Continental Shelf – Decommissioning Activities, 67 Fed. Reg. 35398, 35405 (2002).
14
The subsequent history of this provision is discussed in footnote 11.
22
Case: 11-30380 Document: 00511758696 Page: 23 Date Filed: 02/14/2012
No. 11-30380
Eni has drawn the Court’s attention, simply use the phrase “permanently plug” instead of
“permanently abandon” or “plug and abandon.” See, e.g., 30 C.F.R. § 250.1703 (noting that
the lessee must “[p]ermanently plug all wells”); see also id. §§ 250.1710-.1717 (same).
This shift in terminology is telling. Indeed, it appears to reflect the recognition that
depleted wells that are attached to a production platform are not properly abandoned until the
full range of decommissioning activities – including the plugging of the wells and the
removal of the platform – is carried out and that, accordingly, it would be inaccurate and
confusing to use the term “permanent abandonment” to denote only one aspect of the
decommissioning process. Eni’s attempt to find significance in the term “permanent
abandonment” is therefore not persuasive. The federal regulations have evolved to make it
clear that the abandonment of wells attached to a platform consists of more than just the
plugging of the wells. While there are discrete decommissioning tasks that a lessee must
perform, they are largely inseparable and, in effect, constitute a single process by which
lessees are to abandon the wells once they are depleted.
Finally, in its brief, Eni invokes the principle that lien statutes are, in general, subject
to strict construction, and it argues that a fundamental distinction must therefore be made
between the plugging of wells and the subsequent removal of a platform. Once again, this
argument has some force, but ultimately, it is also unavailing. The Louisiana Supreme Court
has indeed acknowledged that “[a]s a general rule, lien statutes are stricti juris and should
thus be strictly construed.” Guichard Drilling, 657 So.2d at 1313. But, in the same breadth,
it has also indicated that courts should interpret LOWLA “in a manner which will effectuate
23
Case: 11-30380 Document: 00511758696 Page: 24 Date Filed: 02/14/2012
No. 11-30380
its purposes” and that the courts should not “erect artificial barriers to its enforcement.” Id.;
cf. Phillips Petroleum Co. v. Best Oilfield Servs., Inc., 48 F.3d 913, 916 (5th Cir. 1995)
(noting that a “reasonable construction” must be considered before adopting a strict
construction). The court has thus cautioned that the narrowest construction of the statute is
not invariably the correct one.
While LOWLA may not be “a model of clarity,” Ogden Oil Co. v. Servco, Div. of
Smith Int’l, Inc., 611 F. Supp. 572, 576 (M.D. La. 1985), it is aimed at encompassing “all
typical well site activities,” including “[w]ork associated with the abandonment of wells,”
Chicoine, supra, at 1137. As discussed above, the applicable federal regulations that govern
oil and gas operations on the OCS clearly indicate that the removal of a platform following
the depletion of the wells that are connected to it is a typical well site activity that it is, in
effect, part and parcel of the process of abandoning the depleted wells. In light of this
regulatory scheme, it is clear that to accept Eni’s contention that LOWLA does not
encompass any work that is performed subsequent to the plugging of the wells would be to
establish the sort of “artificial barrier” against which the Louisiana Supreme Court has
warned. Guichard Drilling, 657 So.2d at 1313.
In light of the foregoing, the Court therefore concludes that work performed to remove
a platform following the depletion of the wells connected to that platform constitutes work
done to “abandon[] a well” under LOWLA. La. Rev. Stat. Ann. § 9:4861(4)(a)(i). The
application of this statutory phrase to the facts of this case is straightforward. Here, the
undisputed facts show that along with several other subcontractors, TBS took part in a
24
Case: 11-30380 Document: 00511758696 Page: 25 Date Filed: 02/14/2012
No. 11-30380
project to remove Platform 313-A after the wells to which it was connected had become
depleted. See, e.g., TBS’s Ex. D-A (Rec. Doc. No. 83-3). The Court therefore concludes that
the work performed by TBS is done “for the purpose of . . . abandoning a well” within the
meaning of LOWLA. La. Rev. Stat. Ann. § 9:4861(4)(a)(i).
b. Whether the work was done “on a well site”
The remaining question is whether TBS performed work “on a well site.” Id. §
9:4861(4)(a). LOWLA defines the term “well site” as “the area covered by the operating
interest,” id. § 9:4861(12)(a), a term that denotes “a mineral lease . . . or an interest in a lease
. . . that gives the lessee, either singly or in association with others, the right to conduct the
operations giving rise to the claimant’s privilege,” id. § 9:4861(5)(a). One commentator has
observed that this definition provides “broader” coverage than the previous version of
LOWLA, “which tied the provision of services or equipment to the ‘well or wells’”
themselves. Chicoine, supra, at 1142. Under the now-applicable statute, “the well site is not
restricted to the exact physical location of a well.” Id.
In this case, the essential facts that are relevant to the question of whether TBS
performed work “on a well site” are not in dispute. La. Rev. Stat. Ann. § 9:4861(4)(a). The
parties agree that Eni is the owner of 50 percent of the record title and operating rights in the
lease that encompasses Vermilion Block 313, see Eni’s Ex. 2 (Rec. Doc. No. 75-6); that Eni
has thereby acquired the right to drill, produce, and abandon oil and gas wells in Block 313,
see TBS’s Ex. A (Rec. Doc. No. 83-3); and that the toppled platform that was removed,
Platform 313-A, was located in the block encompassed by the lease, see id.
25
Case: 11-30380 Document: 00511758696 Page: 26 Date Filed: 02/14/2012
No. 11-30380
The undisputed evidence also shows that under its subcontract, TBS conducted a sonar
survey of the site prior to the removal of the toppled platform; assisted with the positioning of
vessels, divers, and equipment during the removal operation; and conducted a post-salvage survey
of the site. See TBS’s Ex. D-A (Rec. Doc. No. 83-3); TBS’s Ex. D-B (Rec. Doc. No. 83-3);
Eni’s Ex. 2 (Rec. Doc. No. 75-6). The performance of these tasks required TBS personnel
to be in Vermilion Block 313. See TBS’s Ex. D-A (Rec. Doc. No. 83-3); TBS’s Ex. D-B
(Rec. Doc. No. 83-3). Thus, TBS personnel was onboard the M/V OCEAN COMMANDER,
which was used as a primary vessel for the removal project and deployed to Vermilion Block
313. See, e.g., Eni’s Ex. 2 (Rec. Doc. No. 75-6); TBS’s Ex. D-B (Rec. Doc. No. 83-3). In
light of these undisputed facts, and given that “the well site” under LOWLA “is not restricted
to the exact physical location of a well,” Chicoine, supra, at 1142, it is clear that TBS
rendered services “on a well site” within the meaning of the statute.
In its brief, Eni cites several cases for the contrary proposition, but all of these cases
are distinguishable. In both Matte Services Corp. v. ONYX Consulting Engineers, LLC, No.
06-3020, 2007 WL 1087592 (E.D. La. 2007), and J. Ray McDermott, Inc. v. Berry
Contracting L.P., Nos. 03-2054 & 03-2099, 2004 WL 224583 (E.D. La. 2004), the
subcontractors were given contracts to construct decks that were to be subsequently installed
on structures on the OCS. See Matte Servs., 2007 WL 225483, at *1; J. Ray McDermott,
2004 WL 224583, at *1. The subcontractors conceded that most, if not all, of the work that
they performed was done onshore. See Matte Servs., 2007 WL 225483, at *3; J. Ray
26
Case: 11-30380 Document: 00511758696 Page: 27 Date Filed: 02/14/2012
No. 11-30380
McDermott, 2004 WL 224583, at *8. Here in contrast, it is undisputed that TBS provides its
labor and services in Vermilion Block 313 in the vicinity of Platform 313-A.
The third and last case cited by Eni is also distinguishable. In Samedan Oil Corp. v.
Ultra Fabricators, Inc., 737 So.2d 846 (La. Ct. App. 3d Cir. 1999), the court considered the
application of the former version of LOWLA, see id. at 853. Given that the now-applicable
version of LOWLA provides a “broader” conception of the term “well site,” Chicoine, supra,
at 1142, the conclusion of the court in Samedan Oil that the lien holder did not perform work
at the requisite location is of little significance. Furthermore, Samedan Oil is factually
distinguishable because the party that asserted the lien in that case merely leased cranes for
the construction of platforms and structures, id. at 848, and those cranes were placed at an
onshore site, id. at 853. As noted above, TBS in this case provided labor and services
offshore in Vermilion Block 313.
In sum, the Court concludes that by providing survey and positioning services in
Vermilion Block 313 in order to help remove a platform following well depletion, TBS
performed “operations” under LOWLA. La. Rev. Stat. Ann. § 9:4861(4)(a). The work that
it did was both “on a well site” and involved “abandoning a well” within the meaning of the
statute. Id. Accordingly, the lien that it has asserted is valid and enforceable. See id. §
9:4862(A)(1).
27
Case: 11-30380 Document: 00511758696 Page: 28 Date Filed: 02/14/2012
No. 11-30380
IV. CONCLUSION
For the foregoing reasons, IT IS ORDERED that TBS’s Motion to Strike the
Affidavit of Scot Childress (Rec. Doc. No. 101) is treated as an objection and hereby
SUSTAINED IN PART AND OVERRULED IN PART as set forth above.
IT IS FURTHER ORDERED that TBS’s Motion for Summary Judgment (Rec. Doc.
No. 83) is hereby GRANTED. As noted above, the Court does not reach the issue of
miscellaneous relief claimed by TBS under La. Rev. Stat. Ann. § 9:4862(B).
IT IS FURTHER ORDERED that Eni’s Motion for Summary Judgment (Rec. Doc.
No. 75) is hereby DENIED. Eni’s claim that the TBS lien is invalid and unenforceable is
hereby DISMISSED with prejudice.
New Orleans, Louisiana, this 22nd day of March, 2011.
________________________________
UNITED STATES DISTRICT
JUDGE
28