UNPUBLISHED
UNITED STATES COURT OF APPEALS
FOR THE FOURTH CIRCUIT
No. 10-2245
DORAL BANK PR,
Plaintiff - Appellant,
v.
FEDERAL HOME LOAN MORTGAGE CORPORATION,
Defendant - Appellee.
Appeal from the United States District Court for the Eastern
District of Virginia, at Alexandria. Anthony J. Trenga,
District Judge. (1:09-cv-01420-AJT-JFA)
Argued: December 8, 2011 Decided: April 10, 2012
Before DUNCAN, DAVIS, and WYNN, Circuit Judges.
Affirmed by unpublished opinion. Judge Wynn wrote the majority
opinion, in which Judge Duncan concurred. Judge Davis wrote a
dissenting opinion.
ARGUED: Charles Andrew Patrizia, PAUL HASTINGS LLP, Washington,
D.C., for Appellant. William G. Ballaine, LANDMAN, CORSI,
BALLAINE & FORD, PC, New York, New York, for Appellee. ON
BRIEF: Stephen B. Kinnaird, James E. Anklam, Igor V. Timofeyev,
PAUL HASTINGS LLP, Washington, D.C., for Appellant. Kenton W.
Hambrick, Associate General Counsel, FEDERAL HOME LOAN MORTGAGE
CORPORATION, McLean, Virginia; Mark S. Landman, LANDMAN, CORSI,
BALLAINE & FORD, PC, New York, New York, for Appellee.
Unpublished opinions are not binding precedent in this circuit.
2
WYNN, Circuit Judge:
Under an Interim Servicing Agreement (“ISA”) Doral Bank PR
(“Doral”) agreed to take over the servicing of a portfolio of
mortgages (“portfolio”) owned by the Federal Home Loan Mortgage
Corporation (“Freddie Mac”). However, because the existing
servicer of the portfolio brought court actions that restrained
Freddie Mac from transferring the portfolio to Doral, Freddie
Mac terminated the ISA. Thereafter, Doral brought this action
alleging that Freddie Mac breached the ISA by, among other
things, failing to pay to Doral, pursuant to a provision in the
ISA, an amount equivalent to twenty-four months of Doral’s
anticipated service compensation fees under the ISA.
Upon consideration of cross-motions for summary judgment,
the district court agreed with Freddie Mac that Doral’s damages
were limited to its actual damages in the amount of $124,588.
The district court therefore denied Doral’s claim for twenty-
four months of service compensation fees reasoning that, in
light of Doral’s forecast of evidence on damages, the ISA’s
provision for liquidated damages amounted to an unenforceable
penalty. For the reasons below, we affirm.
3
I.
Freddie Mac engages pre-approved lenders (“servicers”) to
service its portfolio of mortgages. 1 The servicer performs day-
to-day activities such as collecting payments from borrowers,
accounting for and remitting borrowers’ principal and interest
payments to Freddie Mac, and maintaining tax and insurance
escrows to pay borrowers’ taxes and insurance. Since 1986,
Doral, a commercial bank organized and operating under the laws
of the Commonwealth of Puerto Rico, has been a qualified
servicer of Freddie Mac’s mortgages.
This matter arose in 2008, when Freddie Mac began
implementing its plans to terminate its servicing relationship
with R&G Mortgage Corporation and R-G Premier Bank of Puerto
Rico (collectively, “R&G”). On July 9, 2008, Freddie Mac and
Doral initiated negotiations for Doral to step in for R&G and
serve as Freddie Mac’s “interim servicer” on a portfolio
comprising approximately 46,000 Freddie Mac loans with a total
value of over $3.8 billion, which, up to that point in time, had
been serviced by R&G. Accordingly, on July 11, 2008, Freddie
Mac officially informed R&G that it was being terminated as its
servicer of this portfolio. On that same date, Freddie Mac and
1
Freddie Mac is a corporate instrumentality of the United
States chartered by Congress in 1970. See 12 U.S.C. §§ 1451-59.
4
Doral entered into the ISA under the terms of which Doral agreed
to be its interim servicer of the same portfolio.
The terms of the ISA indicate two dates relevant to this
appeal. First, in the opening paragraph of the ISA, the terms
indicate that the ISA was “effective” July 11, 2008. J.A. 30.
Second, in Section 2.6 of the ISA, “Effective Date” is defined
as:
The effective date for commencement of the servicing
of the Mortgages (“Effective Date”) by the Interim
Servicer [Doral] shall be a date that Freddie Mac
determines and communicates to the Interim Servicer
that Interim Servicer will be servicing the Interim
Portfolio. The Effective Date, when possible, will
correspond to a date when Interim Servicer obtains the
files for the Mortgages.
Id. at 33. Additionally, the ISA defined the “Interim
Portfolio” as “[t]he portfolio of Freddie Mac loans that were
once serviced by a terminated servicer.” Id. at 30.
On July 11 and 12, 2008, a Freddie Mac team met with Doral
representatives. The Freddie Mac team advised Doral to have
personnel ready on Monday, July 14, 2008 to go with Freddie Mac
personnel to R&G’s offices to discuss a plan to initiate a
transfer to Doral of the loans R&G was servicing for Freddie
Mac. On July 14, 2008, Freddie Mac representatives, led by
Russell McKoy, Freddie Mac’s file recovery team leader, went to
R&G’s main offices to meet with R&G management. Although a
Doral representative accompanied Freddie Mac employees, he was
5
told by a Freddie Mac representative to wait outside, while
Freddie Mac spoke with R&G. Consequently, Doral did not join
Freddie Mac and R&G for these discussions.
On July 15, 2008, Freddie Mac returned to R&G’s offices,
and during the course of the meeting, Doral representatives were
invited to join. At this meeting, R&G’s representatives
indicated they would not be able to provide data on the R&G
loans that day and requested that Freddie Mac give R&G an
additional day to compile the servicing files and the mortgage
notes to give to Doral.
Later that day, Freddie Mac was served an ex parte
temporary restraining order (“TRO”) issued by the U.S. District
Court for the District of Puerto Rico, prohibiting Freddie Mac
from terminating its servicing agreement with R&G and from
transferring the portfolio. 2 That same day, Freddie Mac’s
associate general counsel spoke by telephone with a Doral
attorney and a senior Doral executive, advising that all efforts
to transfer servicing were on hold because a TRO had been issued
against Freddie Mac. On July 17, 2008, Freddie Mac sent formal
notification, which confirmed that, because of the TRO, the
2
On July 14, 2008, unbeknownst to Freddie Mac, R&G filed an
action under seal in the U.S. District Court for the District of
Puerto Rico to obtain the ex parte TRO. See R&G Mortg. Corp. v.
Fed. Home Loan Mortg. Corp., 584 F.3d 1, 6 (1st Cir. 2009).
6
transferring of the Interim Portfolio from R&G to Doral was on
hold. Notably, at no time were any R&G loan files, documents,
or electronic data transferred from R&G to Doral during the
five-day period spanning from July 11 through July 15, 2008.
On July 22, 2008, the district court converted the
scheduled July 23 preliminary injunction hearing into a
settlement conference. Ultimately, Freddie Mac and R&G entered
into a settlement agreement, signed by the district court,
allowing R&G to continue to service Freddie Mac mortgages until
R&G could sell its servicing rights to a qualified third-party
buyer. See R&G Mortg. Corp. v. Fed. Home Loan Mortg. Corp., 584
F.3d 1, 6 (1st Cir. 2009). Because of these events, Freddie Mac
never transferred the R&G portfolio to Doral.
On August 14, 2008, Doral wrote to R&G, informing R&G that
it would move to intervene in R&G’s pending action against
Freddie Mac unless it was given a copy of the TRO. R&G refused
this request via e-mail, explaining that paperwork in the case
was under seal. “The e-mail advised that Doral’s [ISA] was not
directly at issue in the litigation but that, insofar as that
agreement pertained to R&G’s portfolio of Freddie Mac mortgages,
the TRO rendered Doral ‘unable to perform.’” Id. Thereafter,
Doral attempted to intervene in the R&G action. Doral based its
attempted intervention on its alleged contractual rights under
7
the ISA. Doral’s intervention motion was denied, and the denial
was affirmed on appeal. Id. at 12-13.
In early August 2008, Freddie Mac asked Doral to provide it
with the costs incurred by Doral under the ISA; and on August 5,
2008, Doral transmitted to Freddie Mac its costs incurred
figures, which totaled $124,588. On or about August 13, 2008,
Freddie Mac formally informed Doral that the R&G loans would not
be transferred to Doral for interim servicing under the ISA.
Thereafter, Freddie Mac offered to reimburse Doral for its costs
under the ISA in the amount of $124,588, as well as an
additional sum equivalent to forty percent of Doral’s costs.
Doral, in turn, claimed that it was entitled to twenty-four
months of service compensation fees under the ISA, which
provided at Section 1.1 that:
Interim Servicer [Doral] agrees to provide servicing
for such Interim Portfolio until such time as Freddie
Mac determines to transfer servicing of such Interim
Portfolio. Unless the Interim Portfolio is
transferred pursuant to court order or the Interim
Servicers eleibility [sic] to sell mortgages to or
service mortgages for Freddie Mac is suspended or
terminated pursuant to section 1.3 [of the ISA], the
length of interim servicing will not be less than 24
months. If the length of interim servicing is less
than 24 months, then Freddie Mac will pay to Interim
Servicer the total of 24 months of servicing
compensation fee minus the number of months already
billed by Interim Servicer. Freddie Mac shall not be
responsible for this fee if it is ordered by court to
transfer the Interim Portfolio from the Interim
Servicer before the expiration of 24 months or if
Freddie Mac terminates or suspends the eligibility of
8
the Interim Servicer to sell mortgages to or service
mortgages for Freddie Mac pursuant to section 1.3.
J.A. 30. In response, Freddie Mac rejected Doral’s claim for
damages under Section 1.1, arguing that the “Effective Date”
provision under Section 2.6—i.e., the “effective date for
commencement of the servicing of the Mortgages”—had not
occurred. Specifically, Freddie Mac maintained that the
obligations and liabilities in Section 1.1 were not triggered
because Freddie Mac never “determine[d] and communicate[d] to
[Doral] that [Doral] w[ould] be servicing the Interim
Portfolio,” as required by Section 2.6. J.A. 33.
On December 29, 2009, Doral brought an action in the
Eastern District of Virginia alleging that Freddie Mac either
partially or totally breached the ISA “by failing to pay Doral
the servicing compensation fees due to Doral” for twenty-four
months. Doral also asked for a declaration of the respective
rights of Doral and Freddie Mac. J.A. 27. Freddie Mac
responded by moving to dismiss Doral’s complaint, pursuant to
Federal Rule of Civil Procedure 12(b)(6), for failure to state a
claim upon which relief could be granted. The district court
denied Freddie Mac’s motion, concluding that it was unable to
determine the parties’ contractual intent from the face of the
ISA, that discovery regarding the circumstances of the
transaction was appropriate, and that custom and practice
9
evidence might be relevant to understanding the parties’
obligations under the ISA.
Following discovery, Doral filed an amended complaint,
which left unchanged its contractual claims but amended certain
factual allegations. After Freddie Mac answered the amended
complaint, the parties filed cross-motions for summary judgment
on both liability and damages. The district court granted
summary judgment in favor of Doral as to its liability claims
for breach of contract and as to its damage claims to the extent
of $124,588, but denied claims as to all other damages
(including, specifically, servicing fees, ancillary fees, and
“on hold” costs). Freddie Mac’s motion for summary judgment was
denied as to liability but granted as to all damages other than
the amount of $124,588. Doral’s claim for declaratory relief
was dismissed. Doral appealed.
II.
This Court reviews the district court’s decision granting
summary judgment de novo. See Cont’l Airlines, Inc. v. United
Airlines, Inc., 277 F.3d 499, 508 (4th Cir. 2002). Summary
judgment is appropriate if “the pleadings, depositions, answers
to interrogatories, and admissions on file, together with
affidavits, if any, show that there is no genuine issue as to
any material fact and that the moving party is entitled to
10
judgment as a matter of law.” Fed. R. Civ. P. Rule 56(c).
Summary judgment is appropriate only if there are no material
facts in dispute and the moving party is entitled to judgment as
a matter of law. See Celotex Corp. v. Catrett, 477 U.S. 317,
322 (1986) (citing Fed. R. Civ. P. 56(c)).
Doral argues on appeal that the district court erred by
misreading ISA Section 2.6 to require a separate communication
of an “Effective Date” and by failing to find—if such a separate
communication was required—that such communication was given.
We disagree. As further explained below, we conclude that: (1)
the ISA unambiguously creates—as the district court found—an
“Effective Date” under Section 2.6 for the purposes of
commencement of the interim servicing rights and obligations of
Doral and Freddie Mac, which is separate and distinct from the
ISA’s “effective date” for other contractual obligations,
including, for example, rights and obligations during the pre-
servicing period (e.g., Freddie Mac’s obligations to reimburse
Doral for actual expenses incurred during this pre-servicing
period under Section 2.5(c) of the ISA); and (2) irrespective of
whether Freddie Mac “determined and communicated” to Doral by
words, acts, or deeds that the interim servicing period had
commenced under Section 2.6—and thus irrespective of whether the
Effective Date provision was triggered—we agree with the
district court that Doral’s forecast of damages under Section
11
1.1, which is over 87 times greater than Doral’s actual damages,
fails to provide a reasonable forecast of Doral’s loss.
Accordingly, we conclude, as the district court concluded, that
the liquidated damages established by Section 1.1 are properly
characterized as an unenforceable penalty.
A.
Initially, Doral argues that the “Effective Date” provision
under Section 2.6 has no meaning which is separate and distinct
from the July 11, 2008 effective date clause on the face of the
ISA. We disagree.
“If the terms of the contract are clear and unambiguous,
then we must afford those terms their plain and ordinary
meaning; however, if the terms are vague or ambiguous, then we
may consider extrinsic evidence to interpret those provisions.” 3
Providence Square Assocs., L.L.C. v. G.D.F., Inc., 211 F.3d 846,
3
ISA Section 2.26 provides that the ISA is “governed by and
construed in accordance with the law of the United States.
Insofar as there may be no applicable precedent, then Virginia
laws are deemed reflective of the federal law.” J.A. 40.
Neither the validity nor the interpretation of the ISA’s choice
of law provision is at issue on appeal. We note that, under
federal common law, contracts are interpreted under “standard
principles of contract law-more precisely, the core principles
of the common law of contract that are in force in most states.”
S & O Liquidating P’ship v. C.I.R., 291 F.3d 454, 459 (7th Cir.
2002) (quoting United States v. Nat. Steel Corp., 75 F.3d 1146,
1150 (7th Cir. 1996)).
12
850 (4th Cir. 2000) (citing Shoup v. Shoup, 31 Va. App. 621, 525
S.E.2d 61, 63-64 (2000)).
The first step for a court asked to grant summary
judgment based on a contract’s interpretation is,
therefore, to determine whether, as a matter of law,
the contract is ambiguous or unambiguous on its face.
If a court properly determines that the contract is
unambiguous on the dispositive issue, it may then
properly interpret the contract as a matter of law and
grant summary judgment because no interpretive facts
are in genuine issue.
Goodman v. Resolution Trust Corp., 7 F.3d 1123, 1126 (4th Cir.
1993) (citation omitted). An unambiguous contract should be
construed by the Court as a matter of law, without reference to
extrinsic evidence. See World-Wide Rights Ltd. P’ship v. Combe
Inc., 955 F.2d 242, 245 (4th Cir. 1992). The proper
interpretation of a clear and unambiguous contract is that which
assigns the plain and ordinary meaning to the contract terms.
See Providence Square Assocs., 211 F.3d at 850.
Under Section 2.6 of the ISA, the “effective date for
commencement of the servicing of Mortgages (Effective Date)”
would be determined and communicated by Freddie Mac. J.A. 33.
Although the ISA was “effective” July 11, 2008, the date on
which it was signed, ISA Section 2.6 specifically provides for
the establishment of a separate “Effective Date” on which Doral
would actually commence servicing the R&G loans for Freddie Mac
and begin to earn servicing compensation fees. As the district
court pointed out in its Memorandum Opinion, “the role that the
13
‘effective date’ under Section 2.6 plays with respect to certain
rights, duties and obligations on the part of Doral, apart from
Section 1.1, makes clear that the parties contemplated the
‘effective date’ as a date communicated to Doral as the start of
its obligations with respect to the servicing of the loan
portfolio.” J.A. 1532
We agree with the district court that Section 2.6 is
unambiguous, and that the only reasonable interpretation of
Section 2.6–and the ISA as a whole—is that the parties intended
the “Effective Date” to “be a date that Freddie Mac would
communicate to Doral as the date when Doral would begin its
servicing obligations.” Id. It was “not just the date on which
Freddie Mac [told] Doral that it will at some point be the
interim servicer.” Id. Because we find that the language of
the ISA and Section 2.6 in particular, is clear and unambiguous,
we must disregard extrinsic evidence. See Providence Square
Assocs., 211 F.3d at 850.
B.
Next, Doral contends that, even if this Court upholds the
district court’s interpretation that a separate “Effective Date”
communication from Freddie Mac to Doral was required under
Section 2.6 of the ISA, this Court should nevertheless conclude
that Freddie Mac did in fact determine and communicate the
14
Effective Date to Doral. Doral further contends that such
communication triggered the parties’ rights and obligations
under, among other provisions, Section 1.1, which includes
Freddie Mac’s obligation to pay Doral an amount equivalent to
twenty-four months of service compensation fees in the event of
early termination. Doral argues on appeal that the district
court’s finding that there were genuine issues of material fact
“concerning whether Freddie Mac, through word or deed,
‘communicated’ a date that would serve as the ‘Effective Date’
for the purposes of [ISA Section] 2.6,” J.A. 1532-33, cannot be
reconciled with Freddie Mac’s actions and statements after July
11, 2008, when the ISA became effective. 4 We disagree.
Indeed, as explained below, the district court’s relevant
conclusion of law—namely, that Freddie Mac’s potential liability
to pay liquidated damages to Doral under Section 1.1 is an
unenforceable penalty—may be reconciled both with circumstances
4
According to Doral, Freddie Mac determined and
communicated the Effective Date for the purposes of Section 1.1:
(1) as early as July 11, 2008, when the ISA was executed; or (2)
no later than July 14, 2008, when Doral was told to appear with
Freddie Mac at the offices of R&G to begin the process of
transferring the portfolio; or (3) in no event later than July
15, 2008, when Doral continued to meet with Freddie Mac and plan
for the transfer of the portfolio from R&G to Doral. As
explained, resolution of Doral’s factual allegations is not
material to the legal conclusion of the district court, as well
as our holding today, that the liquidated damages established by
Section 1.1 are an unenforceable penalty.
15
where Freddie Mac determined and communicated the Effective Date
to Doral, as well as with circumstances where no such Effective
Date was determined or communicated by Freddie Mac. Given that
the district court concluded, as we conclude today, that the
liquidated damages established by Section 1.1 are, as a matter
of law, an unenforceable penalty, it follows that whether
Freddie Mac did, as a matter of fact, determine and communicate
the Effective Date to Doral is not material to either the
district court’s legal conclusions and our holding today.
Thus, regardless of Doral’s contentions, there is no need
to address the merits of Doral’s arguments of whether Freddie
Mac communicated to Doral an Effective Date. Even assuming,
arguendo—as the district court assumed—that the twenty-four
month servicing fee provision of Section 1.1 was triggered, we
find—as the district court found—that, as a matter of law, the
provision would amount to an unenforceable penalty.
1.
As a threshold matter, Doral contends the district court
erred in concluding that Section 1.1 of the ISA is a liquidated
damage provision, which is subject, under appropriate
circumstances, to characterization as an unenforceable penalty.
Instead, Doral asks this Court to construe Section 1.1 as a
16
provision establishing, among other things, an “alternative
performance contract.” We decline to do so. 5
“[T]he primary objective of an alternative contract is
performance, and it thus looks to a continuation of the
relationship between the parties, rather than its termination,
whereas a liquidated damages provision provides for an agreed
result to follow from nonperformance.” 24 Williston on
Contracts § 65:7 (4th ed.); see also In the Matter of Cmty. Med.
Ctr., 623 F.2d 864, 867 (3rd Cir. 1980) (explaining that, in an
alternative performance contract, “either one of two
performances may be given by the promisor and received by the
promisee as the agreed exchange for the return performance by
the promisee”).
5
The dissent’s characterization of Section 1.1 as an
alternative performance provision that must be enforced if the
“Effective Date” was communicated to Doral is misplaced. To the
extent that Freddie Mac did communicate the “Effective Date,”
under the ISA’s express terms, Doral is specifically precluded
from recovering 24 months of damages. Section 1.1 provides:
“Freddie Mac shall not be responsible for this [24-month damage]
fee if [Freddie Mac] is ordered by [a] court to transfer the
Interim Portfolio from [Doral] before the expiration of 24
months.” Here, of course, Freddie Mac’s decision was not based
on an economic calculus—as the dissent suggests—but rather a TRO
(issued by the United States District Court for the District of
Puerto Rico) prohibiting Freddie Mac from terminating its
servicing agreement with R&G and transferring the portfolio to
Doral. See R&G Mortg. Corp., 584 F.3d at 6. As a consequence,
the dissent’s characterization of Section 1.1 as an alternative
performance provision does not change the outcome and,
therefore, this matter was properly resolved by the district
court on summary judgment.
17
Here, Section 1.1 of the ISA cannot reasonably be construed
as a provision that “looks to a continuation of the
relationship.” By its terms, this provision would apply only if
Freddie Mac were to terminate the ISA by transferring the
Interim Portfolio away from Doral after commencement of
servicing but before it has had an opportunity to service the
loans for the full twenty-four month period. Rather than an
alternative performance provision, we agree with the district
court’s finding that Section 1.1 plainly reflects the parties’
advance agreement to a liquidated sum that Freddie Mac would owe
to Doral, under certain conditions, for its termination of
Doral’s servicing of the portfolio before expiration of a
twenty-four month term under the ISA. See Williston on
Contracts § 65:7 (“[O]ne of the principal characteristics of a
stipulated damages provision is that it is agreed upon in
advance by the parties as a remedy for breach. This
characteristic provides the basis on which a liquidated damages
provision is distinguishable from provisions for alternative
performance of a contract, which are otherwise similar.”) 6
6
Doral also asserts that Section 1.1 is simply a
“contractual option.” According to Doral, the ISA thus provides
for an option allowing Freddie Mac’s early termination of the
contract without breach subject to its payment of compensation
to Doral pursuant to Section 1.1. The district court, however,
declined to interpret Section 1.1 as a contractual option. We
(Continued)
18
2.
Next, in the alternative, Doral asserts that even if
Section 1.1 is a liquidated damages clause, the district court
erred by finding this provision to be an unenforceable penalty.
Doral argues that in granting summary judgment to Freddie Mac,
the district court erred by requiring Doral to present detailed
support for its damage estimates. We disagree.
We review the district court’s “determination de novo as to
whether a contractual provision is an unenforceable penalty,
unconscionable, or void on account of public policy.” NML
Capital v. Republic of Argentina, 621 F.3d 230, 236 (2d. Cir.
2010) (internal citations omitted); see also Midwest Oilseeds,
Inc. v. Limagrain Genetics Corp., 387 F.3d 705, 715 (8th Cir.
2004) (“[T]he question whether a contract provision is a valid
liquidated damages provision or an unenforceable penalty is a
question of law for the court.” (citation omitted)); Colorado
Interstate Corp. v. CIT Group/Equip. Finan., Inc., 993 F.2d 743,
751 (10th Cir. 1993) (“[T]he determination of whether a
contractual provision is an unenforceable penalty is a matter of
law.” (citation omitted)); see also Scarborough v. Ridgeway, 726
F.2d 132, 135 (4th Cir. 1984) (“[I]nterpretation of a written
agree, as the language of Section 1.1 does not support Doral’s
contention.
19
contract is a question of law subject to de novo appellate
review.” (citation omitted)). 7
“To recover damages in any case, a plaintiff must prove
with reasonable certainty the amount of his damages and the
cause from which they resulted.” Parkridge Phase Two Assocs. v.
Lockheed Martin Corp., 172 F.3d 44, 1999 WL 44173, *2 (4th Cir.
1999) (unpublished) (citing Hale v. Fawcett, 214 Va. 583, 202
S.E.2d 923, 925 (Va. 1974)).
Damages for breach by either party may be liquidated
in the agreement but only at an amount that is
reasonable in the light of the anticipated or actual
loss caused by the breach and the difficulties of
proof of loss. A term fixing unreasonably large
liquidated damages is unenforceable on grounds of
public policy as a penalty.
Restatement (Second) of Contracts § 356. 8 If a liquidated
damages provision is intended to punish a party for breach, the
7
Virginia law also treats the question of whether a
contractual provision is an unenforceable penalty as a matter of
law. See Teachers’ Ret. Sys. v. Am. Title Guar. Corp., 1996 WL
1065475, *2 (Va. Cir. Ct. 1996) (“Because this particular clause
calls for damages in excess of Plaintiff's actual damages, I
find that, as a matter of law, it constitutes an unenforceable
penalty.”); cf. Perez v. Capital One Bank, 522 S.E.2d 874, 875-
76 (Va. 1999) (“[W]hen the damages caused by the breach are
prone to definite measurement or when the stipulated amount
would grossly exceed actual damages, courts of law usually
construe such a provision as an unenforceable penalty.”
(citation omitted)).
8
Federal courts use the Restatement of Contracts in
determining federal common law of contracts. In re Peanut Crop
Ins. Litig., 524 F.3d 458, 470 (4th Cir. 2008) (“The Restatement
of Contracts reflects many of the contract principles of federal
(Continued)
20
provision is unenforceable. Id. at § 356, cmt. a; see also
Comstock Potomac Yard, L.C. v. Balfour Beatty Const., LLC, 694
F. Supp. 2d 468, 484 (E.D.Va. 2010) (“Under Virginia law, a
clause for liquidated damages ‘will be construed as a penalty
when the damage resulting from a breach of contract is
susceptible of definite measurement, or where the stipulated
amount would be grossly in excess of actual damages.’” (quoting
Brooks v. Bankson, 248 Va. 197, 208, 445 S.E.2d 473 (1994)); see
also WRH Mortg., Inc. v. S.A.S. Assocs., 214 F.3d 528, 534 (4th
Cir. 2000) (“[C]ontract provisions calling for breach of
contract damages grossly in excess of actual damages generally
are unenforceable as penalties or forfeitures.” (citation
omitted)).
Here, Doral’s forecast of evidence of its damages pursuant
to Section 1.1 consisted of a model that it created to calculate
its anticipated servicing compensation fees. 9 The model
multiplied the per-loan servicing fee, as specified in Exhibit C
to the ISA, by the number of loans in the portfolio, with an
common law.” (quoting Long Island Sav. Bank, FSB v. United
States, 503 F.3d 1234, 1245 (Fed. Cir. 2007))).
9
During negotiations with Freddie Mac, Doral instructed its
then-Senior Vice President of Investor Relations, Roberto Reyna,
to create a model projecting revenue, expenses, and profits
associated with servicing the Interim Portfolio for two years.
21
assumption of an annual thirteen percent decrease in the number
of loans in the portfolio from year one to year two. Doral
asserts that the sum of this formula, $10,876,954, encompasses
the agreed damages under Section 1.1 for twenty-four months.
Bearing in mind that Doral’s actual damages, as calculated by
Doral, total a mere $124,588, Doral’s model mandates damages
that are 87.3 times greater than Doral’s own estimate of its
actual damages. Notably, only five days elapsed between the
execution of the ISA and the date of a TRO that prohibited
Freddie Mac from transferring the portfolio to Doral. Moreover,
given that the servicing had not yet begun, the Section 1.1
penalties were in their most extreme form (e.g., as compared to
a hypothetical termination of the ISA after twenty-one months of
servicing, which under Section 1.1 would have required Freddie
Mac to pay Doral for only three months of servicing fees).
Furthermore, it appears from the record that Doral seeks an
award without a reduction based on its estimated costs
associated with servicing the loan portfolio. The district
court pointed out that “incurred but unrecovered out of pocket
costs can be determined and in fact, Doral makes such a claim in
the amount of $124,588.” J.A. 1538. We agree with the district
court that Doral’s forecast of its damages under Section 1.1,
which would award Doral twenty-four months of servicing
22
compensation fees without any reduction for Doral’s costs and
expenses, amounts to an unenforceable penalty.
Thus, even if Section 1.1 is applied, and it is assumed
that the “Effective Date” in Section 2.6 was triggered by the
acts and deeds of Freddie Mac, Doral’s forecast of damages
pursuant to Doral’s own model posits that Doral would reap a
windfall exceeding $10 million in damages without any deduction
for expenses. 10 Any such recovery would be grossly out of
proportion to Doral’s actual incurred costs of $124,588, and far
in excess of what it might have reasonably expected to earn if
it had actually incurred the significant cost of servicing more
than 46,000 loans for a period of twenty-four months. In sum,
Doral has failed to present a reasonable forecast of the loss
caused by the breach. See Kraft Foods N. Am., Inc. v. Banner
Eng’g Sales, Inc., 446 F. Supp. 2d 551, 573 (E.D.Va. 2006).
10
In addition to expenses of $124,588 that Doral actually
incurred in preparing to service the loan portfolio, it contends
that it is entitled to service compensation fees of $10,876,954
for the twenty-four month period under the ISA, ancillary fees
it would have earned from late and back check fees of $3,776,376
and the expense of remaining on hold after the TRO per Freddie
Mac’s request. Similar to its holding that the model was
inadequate, the district court found Doral’s figures with
regards to these claims to be speculative and unsupported by the
facts in the record.
23
III.
For the foregoing reasons, we affirm summary judgment as to
Doral’s breach of contract claim and damages entered in favor of
Doral in the amount of $124,588.
AFFIRMED
24
DAVIS, Circuit Judge, dissenting:
The majority holds that § 1.1 of the parties’ Interim
Servicing Agreement (“ISA”) constitutes a liquidated damages
clause, and that the payment Freddie Mac agreed to make pursuant
to that clause is an unenforceable penalty. My examination of
the record persuades me, however, that Freddie Mac could satisfy
its obligations under the ISA with any of several alternative
means of performance. Accordingly, when viewed in light of the
full scope of the parties’ interests and incentives, § 1.1 is
enforceable. Because § 1.1 is enforceable and because (as the
district court concluded) there exists a genuine dispute as to
whether Freddie Mac “determine[d] and communicate[d]” to Doral
that Doral would be servicing the portfolio, I would vacate the
judgment and remand the case for a trial on that question.
Respectfully, therefore, I dissent.
I.
I begin by briefly describing the context in which the
parties entered negotiations with each other. Sometime prior to
2008, Freddie Mac contracted with R&G Financial Mortgage
Corporation (together with affiliated entities, “R&G”) to
service approximately 46,000 mortgage loans with a face value of
$3.8 billion, secured by property located mostly in Puerto Rico.
Pursuant to that agreement, R&G agreed to assume what is known
25
as the portfolio’s “recourse obligation”: in the event any of
the loans in the portfolio were to default (or if some other
“triggering event” were to occur), R&G would absorb the loss by
repurchasing the delinquent loans and repaying Freddie Mac the
associated value. In 2008, Freddie Mac itself calculated the
value of the recourse obligation as $106 million; at any given
time the entity assuming the recourse obligation carried an
estimated liability of $106 million on its books. R&G’s
compensation for servicing the portfolio’s loans and bearing the
recourse obligation was set at a percentage of the borrower’s
monthly interest payments.
In mid-2008, with the nationwide mortgage crisis coming to
a head, R&G faced serious financial difficulties. Freddie Mac,
as the owner of the debt, worried that an R&G collapse would
create two problems: (1) the portfolio would be left without a
servicer and (2) the $106 million recourse obligation would
revert to Freddie Mac. To ensure continuity in the servicing of
the portfolio and prevent the recourse obligation from reverting
to Freddie Mac, Freddie Mac began working to terminate R&G as
servicer of the portfolio and to find another qualified
servicer. One of the banks Freddie Mac approached to take R&G’s
place was Doral, a large bank with numerous branches in Puerto
Rico.
26
Doral found the opportunity worth pursuing: as servicer, it
would not only collect servicing fees but also would have
substantial “cross-selling” opportunities, i.e., opportunities
to sell other banking services to the huge number of new
customers who would pass through Doral’s bank branches to make
their monthly payments. (Apparently, borrowers in Puerto Rico
customarily make mortgage payments in person at banks, at least
at rates substantially higher than in the mainland U.S.) Doral
was concerned, however, that an increasing number of loans in
the portfolio would default, and so recourse loomed as a
particularly unsavory risk. Doral determined that the risk of
assuming the recourse obligation would only be worthwhile if
Freddie Mac would allow Doral to collect a greater percentage of
the portfolio’s revenue than apparently is typical.
Freddie Mac thought the premium Doral demanded was too
high, but it desperately needed a servicer, and Doral -- a large
financial institution with a substantial presence in Puerto Rico
and over ten years of experience servicing Freddie Mac mortgages
-- fit the bill. Thus, the parties agreed that Doral would be an
“interim” servicer: it would service the loans but would not
carry the recourse obligation. The recourse obligation,
meanwhile, would revert to Freddie Mac. But Freddie Mac was also
wary of the risk that more and more borrowers would default,
forcing Freddie Mac to swallow losses potentially over $100
27
million. Thus, Freddie Mac, in exchange for allowing Doral to
forgo the recourse obligation, demanded the ability to transfer
the portfolio to a “permanent” servicer, i.e., one willing to
accept the recourse obligation, at any time, so long as it gave
Doral 30 days’ notice.
Doral was willing to accept Freddie Mac’s condition, but
not without imposing its own condition. Freddie Mac was asking
Doral to rapidly ramp up its operations to service a huge number
of loans, all in a matter of days. Doral was incurring far too
many up-front costs to give Freddie Mac carte blanche to
terminate the ISA at will. If Freddie Mac were to terminate the
ISA quickly, Doral’s up-front expenditures would be for naught.
As Doral’s General Counsel explained, Doral “did not want to be
a stopgap,” allowing Freddie Mac to “shop around the portfolio”
while Doral did “all the setup,” only to have to “fire a lot of
people” once Freddie Mac found a permanent servicer. J.A. 376.
An early termination by Freddie Mac would also prevent Doral
from “cross-selling” its other banking services -- a benefit
that was crucial to making the ISA worthwhile for Doral in the
first place.
Thus, the parties’ risk-allocation calculus came down to
the following: Freddie Mac wanted to retain the right to
transfer the portfolio to a permanent servicer as soon as
possible, in order to minimize the time during which it would
28
carry the recourse obligation. Accordingly, it proposed a month-
to-month arrangement. Doral wanted to service the portfolio as
long as possible in order to maximize its servicing fees and
cross-selling opportunities. The question was how long Doral
would need to service the portfolio in order to make entering
the ISA economically worthwhile.
Doral instructed its then-Senior Vice President of Investor
Relations, Roberto Reyna, to create a model projecting revenue
and expenses associated with servicing the portfolio. Reyna
determined that only with a guaranteed two-year servicing term
would Freddie Mac’s proposal be economically advantageous to
Doral. Doral saw the two-year term as an essential, non-
negotiable requirement of entering the ISA. A two-year deal
would give Doral time to recoup the costs it would expend to
service the loan, and, perhaps even more important, give it
sufficient time to cross-sell its other banking services and
thereby potentially make a profit. Doral estimated that over the
course of the 24-month interim servicing term it would receive
$10,876,954 in service compensation fees. It does not appear to
have estimated the revenue it would generate from cross-selling
to the portfolio’s borrowers.
The compromise the parties reached was memorialized in §
1.1. Doral agreed to service the portfolio, and be compensated
with a per-month, per-mortgage fee, “until such time as Freddie
29
Mac determines to transfer servicing” to a permanent servicer.
J.A. 30, 45. The parties also agreed that, unless (a) “the
Interim Portfolio is transferred pursuant to a court order,” or
(b) Doral’s eligibility to sell or service mortgages were
suspended or terminated, “the length of the interim servicing
will not be less than 24 months.” J.A. 30. In the crucial term
at issue, which I will call the “early transfer provision,”
Freddie Mac agreed that, “[i]f the length of interim servicing
is less than 24 months, then Freddie Mac will pay to Interim
Servicer the total of 24 months of servicing compensation fee
minus the number of months already billed by Interim Servicer.”
Id.
This carefully negotiated early-transfer provision struck a
compromise between Doral’s and Freddie Mac’s concerns: it
allowed Freddie Mac the flexibility to transfer the portfolio,
at any time, to a permanent servicer (and thereby take the $106
million recourse obligation liability off its books), while
ensuring that Doral would either (1) have 24 months to service
the loans, collect servicing fees, and cross-sell other banking
services, or (2) lose the cross-selling opportunities but still
collect the servicing fees it would have received.
None of the early-transfer language would be relevant,
however, if the ISA never went into effect. According to § 2.6,
30
the “Effective Date” for “commencement of the servicing of the
Mortgages” was agreed to be the following:
a date that Freddie Mac determines and communicates to
the Interim Servicer that Interim Servicer will be
servicing the Interim Portfolio. The Effective Date,
when possible, will correspond to a date when Interim
Servicer obtains the files for the Mortgages.
J.A. 33 (emphases added). Once the requisite “determin[ation]
and communicat[ion]” were made, Doral’s obligation to service
the loans would commence, along with its right to collect
servicing fees.
II.
The primary question in this appeal is whether § 1.1 of the
ISA is (1) an alternative-performance provision, (2) an
enforceable liquidated damages clause, or (3) an unenforceable
penalty. In holding that § 1.1 is an unenforceable penalty, the
majority, in my view, oversteps its role and undermines a
carefully negotiated compromise among sophisticated parties. I
would hold that § 1.1 is enforceable as an alternative-
performance provision. The second question presented, which the
majority does not reach (and as to which Freddie Mac has not
filed a cross-appeal), is whether a reasonable jury could find
that Freddie Mac “determine[d] and communicate[d]” to Doral that
Doral “will be servicing the Interim Portfolio.”
31
A.
The first component of whether § 1.1 is enforceable is
whether it is an alternative-performance clause or a liquidated
damages clause. An alternative-performance provision is one in
which “either one of the two alternative performances is to be
given by the promisor and received by the promisee as the agreed
exchange.” 11-58 Corbin on Contracts § 58:18. A liquidated
damages clause is one that fixes an amount of damages to be paid
in the event of “breach.” Restatement (Second) of Contracts §
356 (1981). If ISA § 1.1 is an alternative performance
provision, it is enforceable according to its terms. 24 Richard
A. Lord, Williston on Contracts § 65:7 (4th ed. 2002). If it is
a liquidated damages provision, it still is enforceable, but
only if the liquidated amount is “reasonable in the light of the
anticipated or actual loss caused by the breach and the
difficulties of proof of loss.” Restatement (Second) of
Contracts § 356.
To determine whether a contract provides for alternative
performances or liquidated damages, we look to “the substance of
the agreement.” Id. § 356, cmt. c. As the majority correctly
notes, one distinction between alternative performances and
liquidated damages is whether the provision “looks to a
continuation of the relationship between the parties, rather
than its termination,” or instead serves as a stipulated
32
calculation of damages by the parties “as a remedy for breach.”
Williston § 65:7 (emphasis added); see also 11-58 Joseph M.
Perillo ed., Corbin on Contracts § 58.1 (a liquidated damages
provision “determine[s] in advance what damages will be assessed
in the event of a breach”). In addition, crucial factors in
assessing the distinction between these two types of contractual
provisions include “[1] whether the promisor had a ‘true option’
on which alternative to perform, [2] whether the money payment
is equivalent to performance of the option, and [3] the relative
values of the performances.” 14 Williston on Contracts § 42:10;
see also Restatement (Second) of Contracts § 356 cmt. c (“In
determining whether a contract is one for alternative
performances, the relative value of the alternatives may be
decisive.”). For a contractual provision to be one for
alternative performance, at the time the parties entered the
contract there must have been “a reasonable relationship between
the alternatives.” 14 Williston on Contracts § 42:10. That is,
the promisor must have “conceived [it to be] possible that at
the time fixed for performance, either alternative might prove
the more desirable.” Id.
The fact that “one of the alternative performances is the
payment of a liquidated sum of money” does not necessarily
transform an alternative-performance clause into a liquidated
damages clause. 11-58 Corbin on Contracts § 58:18; see also 24
33
Williston on Contracts § 65:7, at 263 (The fact that “one of the
alternative performances is the payment of a fixed sum of money”
does not “alone . . . make the contract one for single
performance with a liquidated damage provision for a breach.”).
Indeed, “most instances of alternative contracts involve the
payment of money as an alternative to actual conduct in carrying
out the terms of an agreement.” Matter of Cmty. Med. Ctr., 623
F.2d 864, 867 (3d Cir. 1980). An alternative performance
provision will not be enforced, however, if it is a “disguised”
penalty. Restatement (Second) of Contracts § 356 cmt. c.
B.
Doral argues § 1.1 is a proper alternative-performance
clause because it allowed Freddie Mac to perform its obligations
under the ISA in either of two ways: (1) keeping the portfolio
with Doral for the entire 24-month period, at the cost of having
to bear the potential $106 million default risk for the entire
24 months, while compensating Doral with monthly servicing fees,
or (2) transferring the portfolio to a permanent servicer at
some point during the 24 months, relieving Freddie Mac of the
$106 million default risk, and compensating Doral with the
equivalent of the servicing fees Doral would have earned during
the remainder of the 24 months. I agree. In my view, Freddie Mac
had a true option on which alternative to perform, as the values
of the two options were reasonably equivalent and either option
34
could have proven to be the more desirable one depending on
extrinsic factors. 11
There is no dispute that if Freddie Mac were to transfer
the portfolio early (i.e., if it chose the second option), it
11
The majority declines to explain why it believes Freddie
Mac did not have a true choice between two plausibly desirable
options. Instead, my good colleagues apparently believe that,
assuming § 1.1 is enforceable, the express exception in § 1.1,
which would apply if Freddie Mac had been “ordered by court to
transfer the Interim Portfolio from the Interim Servicer before
the expiration of 24 months,” J.A. 30, excused Freddie Mac from
making the early-transfer payment. The majority asserts that “of
course” the Puerto Rico court’s temporary restraining order
constitutes such a court order. Maj. Op. at 17 n.5. But Freddie
Mac does not argue on appeal that the “ordered-by-court”
exception excused its performance under § 1.1. Rather, its
argument related to § 1.1 is entirely and solely that (1) § 1.1
does not apply because there was no “determin[ation]” and
“communicat[ion]” under § 2.6, or, alternatively, (2) § 1.1 is
unenforceable. Moreover, although Freddie Mac raised in the
district court the argument now relied on by the majority, the
district court easily (and correctly, in my view) rejected it:
While Freddie Mac admits that no such court order to
transfer the loan portfolio was ever issued because R
& G never transferred the files to Doral in the first
place, Freddie Mac contends the TRO should be
considered the same as a court order transferring the
files away from Doral. This argument fails as a matter
of law . . . . [A]s Freddie Mac concedes, the TRO did
not transfer the portfolio from Doral. This Court will
not assume that the TRO is the same as an order
transferring the portfolio for the purposes of Section
1.1. In this regard, it is impossible to determine
what the district court issuing the TRO would have
done had the portfolio, in fact, already been
transferred to Doral.
Doral Bank PR v. Federal Home Loan Mortgage Corp., 2010 WL
3984667, *5 (E.D. Va. Oct. 7, 2010)(emphasis added). Therefore,
the majority’s reliance on the “ordered-by-court” exception to
avoid the requisite economic analysis is misplaced.
35
would end up spending more money on the servicing of the
portfolio than it would have otherwise. For example, if it were
to transfer after 10 months, it would still owe Doral 14 months’
worth of servicing fees but would also have to pay 14 months of
servicing fees to the new permanent servicer. But, crucially, an
early transfer would not necessarily be more expensive to
Freddie Mac when one considers, as one should, the $106 million
recourse obligation. Every month the recourse obligation
remained on Freddie Mac’s books, the company faced the risk that
borrowers with many millions of dollars in loans would default,
and Freddie Mac would bear the full brunt of those losses. This
risk was palpable in mid-2008, just as the proverbial housing
bubble was beginning to burst. At any given time during Doral’s
24-month interim servicing term, Freddie Mac could rationally
have decided that invoking the early transfer clause in § 1.1
would be in its best interests, even if doing so would mean
essentially paying double servicing fees during the remainder of
the 24 months.
When viewed in these terms, I conclude that Freddie Mac had
a “true option” to elect either to leave the portfolio with
Doral for the full 24 months or to transfer it to a permanent
servicer earlier. When one compares “the relative values of the
performances,” it is clear that the “money payment” pursuant to
§ 1.1 (the value of remaining servicing fees) is reasonably
36
equivalent to “performance of the option” (leaving the portfolio
with Doral while retaining the recourse obligation), precisely
because it was in Freddie Mac’s interest to unload the recourse
obligation as soon as possible.
The majority places apparently dispositive weight on three
facts: (1) that the early-transfer payment turned out to be 87.3
times larger than what the majority sees as Doral’s “actual
damages,” i.e., the money Doral expended to prepare to service
the 46,000 loans in the portfolio; (2) that the early transfer
payment was to be the full amount Freddie Mac would have paid
Doral in servicing fees, with no deduction for the expenses
Doral would have incurred if it had continued to service the
loans (and would save if Freddie Mac were to transfer the
portfolio early); and (3) that § 1.1 “would apply only if
Freddie Mac were to terminate the ISA” by transferring the
portfolio to a permanent servicer, thereby ending the parties’
contractual relationship. Maj. Op. at 17-18. But these facts do
not render § 1.1 unenforceable, for the following reasons.
First, the ratio between the expenses Doral incurred in
preparing to service the portfolio and the servicing fees it
would have collected over the 24 months is not relevant to
whether Freddie Mac had a true option between two plausibly
beneficial options. It is true $10.9 million is much larger than
the $124,588 Doral actually expended. But when Freddie Mac
37
arguably transferred the portfolio back to R&G (“arguably”
because there is a genuine dispute whether Freddie Mac
determined and communicated that Doral would be servicing the
portfolio, see infra), Freddie Mac benefited by avoiding any
more time carrying the $106 million recourse obligation. The
question whether § 1.1 provides for alternative performances is
assessed from Freddie Mac’s perspective, because Freddie Mac was
the “promisor” with respect to the early transfer payment. See
14 Williston on Contracts § 42:10 (looking to whether “the
promisor had a ‘true option’ on which alternative to perform”);
11-58 Corbin on Contracts § 58:18 (describing an alternative-
performance contract as one in which “either one of the two
alternative performances is to be given by the promisor and
received by the promisee as the agreed exchange”). The amount
Doral expended on preparations is immaterial to the relative
attractiveness to Freddie Mac, the promisor, of the two
alternative ways it could discharge its obligations under the
ISA.
Second, even if the relative benefit of the options to
Doral were relevant, Doral would not necessarily have been
better off with an early transfer. While an early transfer would
allow Doral to collect its servicing fees without incurring
expenses from actually servicing the portfolio, an early
transfer would also have stripped Doral of the potentially very
38
significant cross-selling opportunities it would have had during
the remainder of the 24 months. Freddie Mac does not dispute
that a substantial portion of the borrowers in the portfolio
were not existing Doral customers, and that Doral’s new cross-
selling opportunities would have led to new business for Doral.
Indeed, the influx of new customers would have increased Doral’s
mortgage servicing business by nearly one-third. Thus, to the
extent the majority insists on considering the relative benefit
of the options to Doral, the relevant comparison is not between
the $124,588 in preparation expenses and the $10.9 million
early-transfer payment. Rather, it is between (1) the expenses
Doral would have incurred during a particular portion of the 24
months, and (2) the revenue Doral would have received from
cross-selling during those months. There is every reason to
believe the parties saw the value of these two items as roughly
equivalent. Therefore, viewed not only from Freddie Mac’s
perspective but from Doral’s as well, Freddie Mac’s two
alternative means of performance were reasonably equivalent.
Third, the ISA expressly grants Freddie Mac the option to
transfer the portfolio to a permanent servicer within the 24
months. A liquidated damages clause stipulates damages in the
event of a “breach” by one of the parties. Restatement (Second)
of Contracts § 356. Because the ISA expressly allows Freddie Mac
to transfer the portfolio early, an early transfer would not
39
constitute a breach. This is so even though, as the majority
notes, Freddie Mac’s invocation of its early-transfer option
would essentially terminate “the relationship between the
parties.” Maj. Op. at 17 (quoting Williston § 65:7). While the
continuation of a contractual relationship can help demonstrate
that a particular performance is a true alternative rather than
liquidated damages, see, e.g., Cmty. Med. Ctr., 623 F.2d at
865, 12 such a continuation is not necessary. See, e.g., River
East Plaza, LLC v. Variable Annuity Life Ins. Co., 498 F.3d 718,
724 (7th Cir. 2007) (interpreting a contract as one for
alternative performance even though the promisor’s election of
one option effectively terminated the parties’ contractual
relationship) 13; Las Vegas Sands Corp. v. Ace Gaming, LLC, 713 F.
12
In Community Medical Center, the contract at issue was
for the provision of information technology services to the
Center. 623 F.2d at 865. The Center agreed to either (a) pay
InfoMed, the IT company, on a monthly basis for the services it
provided, which were around $3,400 on average, or (b) pay a
minimum monthly fee of $1,500. Id. at 866. The Third Circuit
held that the $1,500 minimum monthly fee was a true alternative
performance, in part because the fee “look[ed] more to a
continuance of the relationship between Info Med and the debtor
rather than termination.” Id. at 867. The court did not,
however, indicate that the continuance of the relationship was a
necessary condition to finding the contract to be one for
alternative performances.
13
In River East, a development company (River East), took
out a $12 million loan to build a large retail store. 498 F.3d
at 719. The loan agreement included a “yield maintenance
prepayment clause,” which provided that, in the event River East
chose to pre-pay the loan, it would have to pay back not only
(Continued)
40
Supp. 2d 427 (D.N.J. 2010) (upholding as an alternative-
performance contract a trademark-licensing agreement that
provided for the contract to continue until the year 2086, but
permitted early termination with the condition that the
terminating party would nevertheless pay the licensing fees due
until the 14th anniversary of the contract plus an additional
one-year “termination fee”).
For these reasons, I would hold that § 1.1 is a true
alternative-performance provision that must be enforced if the
the principal but also the return the lender would have received
if it had invested the remaining balance in Treasuries over the
remaining years on the loan. Id. River East pre-paid and tried
to avoid paying the pre-payment amount, calling it an
unenforceable “penalty.” The Seventh Circuit rejected that
argument, and conducted a detailed analysis of the “relative
value of the alternatives” from the perspective of the parties
at the time they negotiated the loan agreement. Id. at 722-23
(applying Restatement (Second) of Contracts § 356). Because
River East could achieve a substantial benefit by pre-paying,
even though it would also have to pay the pre-payment penalty,
the court concluded that River East had a true choice between
two options; the eventual relative value of the two alternatives
(and thereby River East’s eventual decision whether to
refinance) would depend entirely on whether interest rates
increased or decreased. The clause was not one whose “sole
purpose is to secure performance of the contract.” Id. at 723.
Therefore, the alternative-performance clause was enforceable
according to its terms, notwithstanding the fact that it
operated to terminate the parties’ relationship.
41
condition precedent (the determination and communication from
Freddie Mac) occurred. 14
C.
Because I would hold that the early-transfer provision in §
1.1 is enforceable, I simply highlight the district court’s
treatment of the issue of whether the parties’ obligations under
the ISA became effective. The district court concluded,
correctly in my view, that there was a genuine dispute on this
issue. 15 Manifestly, a reasonable jury could reasonably find that
Freddie Mac “determine[d] and communicate[d]” to Doral that
14
In the alternative, even if § 1.1 is analyzed as a
liquidated damages clause, it would be enforceable for largely
the same reasons. Under federal common law, a liquidated damages
provision is enforceable if, at the time of contracting, (1)
“the harm that would be caused by a breach is difficult to
estimate” and (2) the liquidated amount is “a reasonable
forecast of the loss that may be caused by the breach.” DJ Mfg.
Corp. v. United States, 86 F.3d 1130, 1133 (Fed. Cir. 1996); see
also O’Brian v. Langley School, 507 S.E.2d 363, 365 (Va. 1998)
(applying the same test under Virginia law). As discussed, one
aspect of the harm to Doral of an early transfer was the loss of
cross-selling opportunities, the precise value of which was very
difficult to calculate. Moreover, the early-transfer payment was
a reasonable forecast of the value of those opportunities.
Although § 1.1 does not deduct the amount Doral would have
expended over the remaining months, it is reasonable to conclude
that the parties considered Doral’s servicing expenses as
roughly equivalent to the value of Doral’s cross-selling
opportunities. Therefore, in my view, even construed as a
liquidated damages clause, § 1.1 is enforceable.
15
I agree with the majority that the “Effective Date”
described in § 2.6 is distinct from the effective date clause on
the face of the ISA.
42
Doral would “be servicing the Interim Portfolio.” Accordingly, I
would remand this case for trial.
As the majority explains, on Friday, July 11, 2008, Freddie
Mac instructed Doral to come to the R&G offices to facilitate
transfer of loan files to Doral on the following Monday. That
same day, a Freddie Mac team arrived in Puerto Rico intending to
terminate R&G’s eligibility to sell loans to, and service loans
for, Freddie Mac. Freddie Mac also instructed Doral’s Vice
President of Mortgage Servicing to prepare for the transfer of
certain physical mortgage files from R&G and to have personnel,
information technology support, and transportation support ready
by Monday morning. Over the weekend (July 12-13), Freddie Mac’s
representatives in Puerto Rico worked together with Doral staff
at Doral’s headquarters to set in place the necessary elements
of servicing. Freddie Mac provided Doral with electronic files
containing information about the loans in the Interim Portfolio,
including detailed personal and financial information about the
mortgage borrowers. Furthermore, Freddie Mac’s representative
told Doral on Saturday, July 12, that Freddie Mac anticipated
obtaining the R&G files in three calendar days.
On the morning of July 14, representatives of the two
companies met at Doral’s offices in San Juan to discuss, as
Freddie Mac characterized it, the “anticipated initiation of the
transfer of R&G’s files (including data) to Doral.” J.A. 143. In
43
addition, Freddie Mac provided Doral with an electronic copy of
the “trial balance data,” the loan data for the 46,132 Freddie
Mac mortgage loans then constituting the Interim Portfolio. J.A.
208, 1848-59. According to Doral, upon receiving this data,
together with the loan data received over the weekend, Doral had
all the information it needed to begin servicing the portfolio
by sending welcome letters to borrowers, accepting loan
payments, performing reconciliations, and making remittances to
Freddie Mac. Furthermore, Freddie Mac’s internal documents,
created prior to the evening of July 15, indicate that Freddie
Mac had “already assigned the servicing” to Doral and refer to
Doral as “the Interim Servicer.” J.A. 275-78, 534-36.
Based on this evidence, a reasonable jury could conclude
that Freddie Mac had “determine[d]” to transfer the servicing
rights to Doral, and had effectively “communicated” that
determination to Doral. Only after the temporary restraining
order enjoined Freddie Mac from transferring the portfolio to
Doral did Freddie Mac show any intention other than that Doral
imminently would become the interim servicer, and should make
every effort to prepare to begin servicing the portfolio.
III.
For these reasons, I would vacate the grant of summary
judgment to Freddie Mac and remand this action for trial.
44