Delaware & Atlantic Telegraph & Telephone Company's License Fees

Opinion by

Head, J.,

The Act of April 17,1905, P. L. 183, provides that where any dispute shall arise between a municipality and any telegraph, telephone, light or power company as to the amount of a license fee named in any ordinance for the inspection and regulation, under the police power of such municipality, of the poles, wires, conduits or cables of such company, either party may apply by petition to the court of common pleas of the proper county, to determine the said dispute. After providing the process to bring the other party into court, and for pleadings to raise the issues of fact out of which the dispute has arisen, the act directs that it shall be heard and determined “in the way and manner provided by law for the hearing of *156cases in equity.” The act then provides in section 4, that “ either party shall have the right of appeal from the order of the court, to the Supreme or Superior Court, as in other cases.”

The present proceeding resulted in a decree, entered by the learned court below, that the annual license fees fixed in the ordinances of the borough of Sharon Hill, to wit: $1.00 per pole, $2.50 per mile of wire or cable, and $30.00 per mile of conduit were properly collectible under the evidence produced, and from that decree this appeal is taken.

Is such appeal but a substitute for the common-law writ of certiorari? If so, our functions are limited to an inspection of the record and a determination whether or not the court had jurisdiction and the proceedings were regular. If the legislature intended the appeal to be of this limited character it would not have been necessary that the right to take it should have been expressly granted. But as the right of appeal has been in terms granted and as the act, in a previous section, had declared'that the cause should be determined “in the way and manner provided by law for the hearing of cases in equity,” we are disposed to hold that this appeal, like one from the decree in an ordinary case in equity, brings before us the entire record m'ade up by the exceptions filed to the conclusions of law and fact adopted by the learned trial court.

In such a case it has been well settled that the findings of fact adopted by the trial judge, when the ascertainment of such facts involves the balancing of conflicting testimony, the credibility of witnesses, etc., will be regarded by the appellate court as if established by the verdict of a jury. Where, however, such findings are but conclusions or inferences drawn from testimony that is practically undisputed, it becomes our duty to examine the evidence and determine for ourselves whether or not the findings are warranted by it.

The learned court below was not called upon, in this proceeding, to exercise'the power possessed by the courts long before the passage of the act now under consideration, viz, to set aside an ordinance because it was unreasonable, oppressive and arbitrary, resulting from an abuse of the powers of the municipality.' The object of this proceeding was simply to de*157termine, from the evidence produced, “the amount of annual license fees which should be paid to the said municipal corporation in order to properly compensate it for the necessary cost of the services performed, or to be performed, by it, for the inspection and regulation of the poles, wires, conduits or cables, of the said telegraph” or other “company.”

The dispute in the present case arose out of the fact that the borough of Sharon Hill claimed the right to levy, from the petitioner and other corporations of its class operating in the borough, annual license fees based on these rates, viz.: $1.00 for each pole erected, $2.50 for each mile of wire strung thereon, and $30.00 per mile for each mile of conduit laid under its streets. Each of these companies, before beginning the work of construction, was obliged to apply for and obtain a permit, for which a charge of $5.00 was made, and to execute and deliver to the borough a bond with satisfactory security conditioned that any streets' or sidewalks affected by such construction should be restored to proper condition and maintained in good order thereafter.

The petitioner itself has constructed in the borough, two and one-fifth miles of conduit, 15.15 miles of wire and ten. poles, so that its annual license fee would amount to $113.88. As there was some common use, by the several companies there operating, of portions of property severally owned, the learned court found that all of the annual fees claimed would be, in addition to the petitioner’s............................. $113.88

Suburban Gas Co.......4.3 miles pipe........ 129.00

Springfield Water Co. .. .4.4 miles pipe.-....... 132.00

Citizens’ Light Co.......175 poles.....$175.00

10 miles wire.. 25.00 200.00

Western Union Tel. Co... 36 poles...... 36.00

27 miles wire.. 67.50 103.50

Chester Traction Co.....42 poles...... 42.00

5 miles wire.. 12.50 54.50

Total $732 88

*158It was shown that the borough had committed to its single policeman, the duty of inspecting the poles, wires and conduits of the several companies and for this service paid him a salary of $20.00 per month, or about one-third the amount of the annual license fees levied to compensate it for the services performed in the “inspection and regulation” contemplated by the act. It was not alleged or proven by the borough that the inspection thus given was not fully up to any municipal requirement, that it was not adequately compensated in the amount paid the policeman, or that a proper inspection sufficient to enable the borough to discharge every duty it owed to its citizens in the premises could not have been had even for less money.

On the contrary, the testimony offered by the petitioner, which was uncontradicted, tended to prove that when a conduit has been laid underground, when the frosts of the winter and the thaws of the spring have once come and gone, and the overlying surface has been then adjusted to the new conditions, all surface indications marking even the location of the buried conduit will have practically disappeared and inspection of the line thereafter could at best be but little more than perfunctory. It would seem, therefore, that an annual charge of $30.00 per mile would go far beyond the Compensation contemplated by the act.

' As to the pole and wire structure the evidence would fairly lead to the conclusion that for a period of years after new construction there is. but little to apprehend from the natural decay of the material. But such a structure is plainly subject to injury from external causes, high winds, heavy snows and the like and therefore might properly be inspected several times each year by a careful municipality. But both poles and wires may be inspected at the same time, and it is manifest from the testimony that no great amount of time need be spent in making an effective inspection of a pole line. The borough, too, has the benefit of the frequent inspections made by the companies themselves whose business cannot be transacted unless their lines are maintained in efficient working order. The borough is of course not required to accept these inspections as conclusive and may properly supplement them by its own. But the fact *159that.they are made by competent men and with the end of maintaining the lines in standard condition ought not to be lost sight of in a proceeding like the present.

We are not unmindful, on the one hand, that the object of inspection is the regulation that is to follow, and that reports must be made and so kept that their information is available for the use of councils; whilst, on the other hand, the courts have repeatedly declared that a municipality may not, under the guise of license fees, levy and collect revenue to be expended in the discharge of municipal obligations: Kittanning Boro. v. Telegraph Co., 26 Pa. Superior Ct. 346; Pottsville Boro. v. Pottsville Gas Co., 33 Pa. Superior Ct. 480.

Realizing the difficulty of arriving at the exact sum which a borough should properly undertake to collect, as license fees, from companies like the petitioner, the legislature has wisely provided that the question should be subject to a readjudication at the end of two years. Thus, accumulating experience will beget increased knowledge, serious disputes will more rarely arise and their adjustment will become more easy and accurate.

After endeavoring to give due weight to all of the evidence contained in the record and an attentive consideration to the aim and object of the statute, we have reached the conclusion that the decree, entered by the learned court below, should be so modified as to make the maximum sum which the borough shall be authorized to charge as license fees against the petitioner, $10.00 per mile for each mile of conduit; $1.50 per mile for each mile of wire, and fifty cents for each pole, and the record is remitted to the court below with direction to enter a decree in accordance with this order. The costs of this appeal to be paid by the respondent, the borough of Sharon Hill.