Opinion by
Mokrison, J.,This is an action of trespass to recover damages for injuries to the plaintiff’s building and its contents resulting from an excavation made by the appellant on an adjoining lot. This is the second trial and appeal in the case by the defendant. The first judgment was for a sum in excess of the jurisdiction of this court and the appeal was to the Supreme Court where the judgment was reversed, on a single ground, in an opinion by Mr. Justice Elkin (Cooper v. Altoona C. C. & S. Co., 231 Pa. 557). Although in that appeal the appellant’s counsel presented thirty-five assignments of error, the Supreme Court refused to discuss them in detail and reversed the judgment for the following reasons: “The whole case turns upon the instruction given by the learned trial judge as to a promise alleged to have ' been made by an officer of the appellant company to the appellee, an abutting owner, concerning the protection of his wall while the excavating was being done. This ‘ promise was as follows: 'We are going to be very careful. *147We are going to take it out in sections and shore it up as we go along. We don’t want to have any accidenl and don’t want to kill anybody and will be very careful.’ In instructing the jury as to this question the learned trial judge said: 'If such a promise was made by Mr. Brandt that he would be particularly careful and guard his wall then the law would impose on him a duty of unusual caution and care; more than ordinary caution and care, unusual caution and care.’ This instruction was substantially repeated in several parts of the charge and taken in connection with the manner in which the whole case was tried and submitted to the jury, constitutes, in our opinion, reversible error.” We further quote from the opinion of Mr. Justice Elkin: “If, then, the excavator made a promise to the adjoining lot owner that he will excavate in a certain way, and this method is satisfactory to both parties, it is not placing any undue burden upon him to require it to be done in that way, or at least to give notice if the plan agreed upon be changed, so that the adjoining owner may have the opportunity of taking the necessary steps to protect his property. We agree, therefore, with the learned court below that the appellee so far as he had any duty to perform had a right to rely under the circumstances on the promise thus made. . . . All of these things are for the jury under proper instructions from the court. Appellant is not answerable in damages unless the excavating was done in a negligent and careless manner, or unless appellee was misled to his injury by the promise of appellant to do the work in a particular manner. In either event it" is for the jury to say whether under all the facts and circumstances the excavating was done in a negligent and careless manner, and if so, did the wall fall as a result of that negligence? The adjoining owner in every such case must take the necessary steps to protect his own buildings, or he must agree with the excavator on a method of doing the work which will answer the same purpose. If the parties agree as to the method of excavating, and this method is followed by the excavator, and the *148adjoining wall, notwithstanding the method agreed upon, falls, the excavator would be relieved from damages. If the excavator change the plan promised without giving ample notice to the adjoining owner, he takes the chances of having a jury say he was negligent under the circumstances.”
Now when we remember that the case Mr. Justice Elkin was considering was an action of trespass to recover damages for injuries to a building and its contents resulting from an excavation made by appellant on an adjoining lot, we have no difficulty in concluding that the opinion from which we have been quoting furnished a safe guide for the trial of the present case.
It must be conceded that an owner of land is by the law of nature entitled to lateral support for his soil, but not for buildings' erected thereon. We understand the law to be that an excavation made by an adjoining owner in such a manner as to remove the lateral support of the contiguous lot, causing it, unburdened by any buildings or structures of any character, to fall into the excavation, subjects the former to liability for the resulting injury, irrespective of the degree of care he may have exercised in making the excavation: Washburn on Easements & Servitudes, p. 582; Malone v. Pierce, 231 Pa. 534; Cooper v. Altoona C. C. & S. Co., 231 Pa. 557. “It is well settled that, where the owner of a lot builds upon his boundary line and the building is thrown down by reason of excavations made upon the adjoining lot (in the absence of improper motive and carelessness in the execution of the work), no recovery can be had for the injury done to the building:” McGettigan v. Potts, 149 Pa. 155. “As this right of lateral support is limited to the land itself in its natural condition, there can be no recovery for injuries to buildings or improvements resulting from the withdrawal of such support in the absence of proof of negligence or carelessness in excavating or mining on the adjoining land:” Matulys v. P. & R. Coal & Iron Co., 201 Pa. 70. See also the opinion of Mr. Justice Elkin in *149Malone v. Pierce, 231 Pa. 534, where it is distinctly stated that if the excavations are made in a careless and negligent manner and the buildings of the adjoining owner are thereby injured, the party so negligently making such excavation may under certain circumstances be held liable in damages to the extent of the injuries suffered: Hannicker v. Lepper, 6 L. R. A. (N. S.) 243; Larson v. Ry. Co., 16 L. R. A. 330. In the case last cited Mr. Justice Barclay, in delivering the opinion of the supreme court of Missouri, said: “If defendant notified plaintiff that a certain mode of proceeding was iJo be pursued and this led him to act upon that hypothesis and refrain from taking steps which would otherwise have been necessary and prudent to insure the safety of his property, the risk of injury to the plaintiff in the premises imposed on the defendant the duty towards him of conforming to the plan of work of which it had advised him or to reasonably notify him of a change in that plan in season tb admit of his adopting protective measures of his own.”
When this case was before the Supreme Court, Mr. Justice Elkin, speaking for that court, said: “The excavator on the adjoining lot was only bound to use due care so as not to negligently or carelessly inflict an injury upon the property of his neighbor.” Many of the cases decide and all of them which we have examined either decide or clearly imply that if the lateral support is carelessly or negligently removed and the buildings of the adjoining owner and their contents are destroyed or damaged, the person who negligently or carelessly removed such support may be liable for all of the damages sustained. And the cases are equally clear in support of the doctrine that if the person who is about to remove the lateral support agrees with the adjoining owner upon a method of such removal and then changes to some other method, without notice to the other party, and damages result to the adjoining buildings and property, proof of such agreement and its violation furnishes evidence of negligence and may render the excavator liable for all of the damages *150resulting. The true doctrine in this class of cases is recognized by this court in Fyfe v. Turtle Creek Borough, 22 Pa. Superior Ct. 292, where the opinion was written by Portee,, J., and that case by clear implication is authority for the doctrine that where an excavation is negligently made the excavator may be liable for damages to the adjoining lands and to the buildings.
In the present case we think there was ample evidence to convict the defendant of not only careless and negligent acts in removing the lateral support but also of violating its promise made to the plaintiff as to the manner of the removal and the support of the plaintiff’s wall, and also of the fact that in making the excavation the defendant excavated over and upon plaintiff’s land seven and one-half inches and to the depth of five or six feet below the bottom of the plaintiff’s foundation wall. We conclude that the jury probably did find against the defendant on all of the above-mentioned points. If it be true that the defendant excavated upon the plaintiff’s land a strip seven and one-half inches wide and even extending under his foundation wall, it is idle to argue that there is no evidence of negligence on the part of the defendant. And so it may be said, if it was a fact that the defendant did not make the excavations in sections and lay up the wall in sections and shore the plaintiff’s wall and building as it promised to do, then it would be idle on this ground to contend that there is no evidence of negligence.
We do not consider it necessary to discuss the question of the liability of the defendant for the damage to the contents of the plaintiff’s building if it was thrown down by the negligence and carelessness of the defendant. Surely if the building was destroyed by the defendant’s negligence and a direct result of the destruction was loss and damage to the plaintiff’s goods he would be entitled to compensation therefor. The plaintiff claimed damages to his building, for the loss and injury to the goods therein, the rental value of the building during the time necessary to reconstruct it and a small sum for expenses in making *151temporary repairs to save his goods from further injury. In our opinion all of these items were, under the evidence, for the consideration of the jury. These claims were not speculative, and if the jury found that plaintiff’s losses were the direct result of the- negligence of the defendant, we think the evidence shows that such losses were chargeable to the alleged negligence. It may be noted that the jury did not allow much more than one-half of the alleged damages to the building, and it would be mere speculation to attempt to account for the size of the verdict. If the defendant was properly held hable for the cohapse of the building, then the verdict is much less than it might have been under the evidence, and the defendant has no just cause of complaint as to the amount of the judgment.
One of the strong contentions of the appellant’s learned counsel is based upon their fifth point which raised the question that if the plaintiff erected his building upon an insufficient foundation and that this faulty foundation contributed to the collapse of the building in any degree, then there can be no recovery and the verdict must be for the defendant. This point was refused by the court. We think the appellant’s counsel failed to note the important distinction that the jury was.instructed that the plaintiff could not recover unless the injury he suffered was caused by the negligence and carelessness of the defendant in making the excavation. It is very clear that if the plaintiff’s foundation was not as good as it ought to have been and his building was destroyed by the negligent conduct of the defendant, still the plaintiff might recover in proportion to the loss actually suffered where the jury finds that the injury to the building and contents was the consequence of the defendant’s negligence. This doctrine was held in Dodd v. Holme, 1 Ad. & El. 493. In Shafer v. Wilson, 44 Md. 268, the court said-: “Although the plaintiff’s house be in a bad condition, the defendant has no right to hasten its fall by making improvements on his own lot in a careless and negligent manner.” But on this point we think the learned trial judge very carefully *152guarded the defendant’s rights in the charge to the jury as follows: “If this building collapsed owing not to the defendant’s negligence, but to the insecure foundation or the building construction, as contended by this defendant, and there was no agreement, as testified to by the defendant, and even if there was such an agreement, and the defendant complied therewith, then there can be no recovery, except, possibly for nominal damages, which we will explain hereafter.” Evidently the nominal damages to which the court referred related to the removal of the soil of plaintiff’s lot. It would therefore seem that the learned trial judge in instructing the jury upon this question went to the limit and told the jury in plain terms that if the building collapsed on account of faulty construction and not because of the negligence of the defendant, then there could be no recovery for the building and its contents.
It is contended that the judgment ought to be reversed on account of the manner of the taking of the verdict of the jury. In the general charge the jury was instructed that, if they concluded that the plaintiff had sustained damages and that the defendant was liable therefor, they might take into consideration the fact that some time had elapsed since the damages were sustained and add a reasonable sum to the amount of damages which they believed the plaintiff had sustained, but such an amount should not be more than legal interest upon the said damages. The jury returned a verdict awarding the plaintiff $1,000, with interest from March 30, 1907. The trial judge refused to receive this as the verdict of the jury because the interest was not computed and a total sum named. He did, however, submit to the jury whether the sum of $1,289.30 was satisfactory to them and if that was their verdict. The jury answered in the affirmative and the verdict was taken and recorded by the court. “The only verdict is that which the jury announces orally and which alone is received and recorded as the jury’s finding:” Henning v. Keiper, 37 Pa. Superior Ct. *153488. To the same effect is Rottmund v. Penna. R. R. Co., 225 Pa. 410. We therefore conclude that the written memorandum brought in by the jury cuts no figure, in the case, but we have to deal with the verdict as it was taken and recorded with the oral consent of the jury. Now it appears from the charge that the judge instructed the jury before they retired that they might add a reasonable sum to the amount of the damages but such sum should not be more than interest upon the damages. It is not reasonable to suppose that the jury understood this as a binding instruction to add legal interest. We think the language used by the judge would be understood by the jury that they could add less than legal interest, and when the jury assented in open court to have the sum allowed for the detention of the damages computed at six per cent they clearly indicated their desire to add six per cent. It is not and cannot be contended that the jury did not have the power to allow six per cent for the detention of the damages which they had found the plaintiff suffered by reason of the negligence of the defendant. We do not think any of the cases require a reversal of the judgment for the reasons just referred to.
We think the charge of the court contains clear and accurate instructions to the jury upon all of the questions necessary for a proper consideration of the case and we have given the twenty-six assignments of error careful consideration and in our opinion they do not raise reversible error.
The refusal of the plaintiff’s counsel to deliver to the opposing counsel copies of the written points presented to the trial judge and the refusal of the latter to require the points to be presented and discussed in the presence of the jury gives ground for the thirteenth and fourteenth assignments of error. We consider it entirely within the discretion of the trial judge whether or not the jury shall be present while the points are being discussed and considered. Written points are for the consideration of the *154trial judge-, and if lie reads such points as he affirms to the jury and files those that he refuses with his rulings and exceptions which may be taken, then nothing more can be required of him. Some judges read to the jury all of the points with the answers thereto, while others only read to the jury such as they affirm. We here remark that when counsel present to the trial judge written points for instructions, ordinary courtesy would seem to suggest that copies of the same should be handed to the opposing counsel, and if that had been done it is probable that considerable contention in the present case would have been obviated. 1
Appellant’s counsel contend that the trial judge erred in using the word “agreement” instead of “promise” in referring in the charge to the promise of the defendant made through its officer, Mr. Brandt, as to the method defendant would adopt in making the excavation. The evidence was that the defendant “promised,” and it is very evident that the use of agreement by the trial judge was- an inadvertent mistake and we cannot believe that calling it an agreement instead of a promise did the defendant any harm. But be that as it may, if counsel thought this mistake might injure their client they should have called the attention of the judge to his evident slip and we cannot doubt, if that had been done, he would at once have corrected his error.
“A party may not sit silent and take his chances of a verdict, and then if it is adverse, complain of a matter which, if an error, would have been immediately rectified and made harmless:” Com. v. Razmus, 210 Pa. 609; Penna. R. R. Co. v. Donora S. R. R. Co., 219 Pa. 361; Slavin v. North Cambria St. Ry. Co., 47 Pa. Superior Ct. 454.
The assignments of error are all dismissed and the judgment is affirmed.
Porter, J., dissents.