Crane Co. v. Rogers

Opinion by

Kepbart, J:,

In Crane Co. v. Rogers, et al., (No. 1), in an opinion this day filed, post, p. 305, among other questions discussed was whether the lien was fatally defective because of its failure to set forth the time when the materials were furnished. In that case there was no prior contract between the contractor and subcontractor wherein the materials , to be furnished and labor to be done specifically appeared. In the present case we" have a contract formed by a proposal and an acceptance in writing, embodying all the items to be furnished each specifically set forth. The itemized statement attached to the lien carefully avers the various articles of material furnished *302and their price. There is a specific averment in the lien that the first of these items was furnished on December 13, 1910, and the last was furnished October 28, 1911, and continuously from time to time between those dates. The question of the validity of the lien rests solely on the absence of the dates on which the material was furnished; the lien having been filed by a subcontractor who had a written contract, covering all of the items, with the original contractor. The reasons given for exacting particularity as between the subcontractor and the owner have been frequently stated. In Chapman v. Faith, 18 Pa. Superior Ct. 578, this court said: “The reasons given in the cases for requiring the claim to be itemized when the claimant is a subcontractor between whom and the owner no privity exists, are that the agreement between him and the contractor is not the measure of the owner’s responsibility; such a contract is not evidence of the sum which the owner ought to pay, nor of the amount of the claimant’s lien upon the building; of the nature and amount of his claim, the kind of work which he has done upon the building, the kind and amount of the materials which he has furnished, as well as the time when the credit arose, it is presumable the owner knows nothing, because they have not dealt with each other; notwithstanding the subcontract, the owner is as much interested as he would be, had it not been made, in knowing the kind of work and materials with the amount of each which the subcontractor had furnished ; for these reasons, it is of the highest importance that the owner should be informed by the claim filed as to the particulars of the demand, that he may be enabled to make the necessary inquiries to satisfy himself of its justice as a lien upon his property”: Shields v. Garrett, 5 W. N. C. 120; Lee v. Burk, 66 Pa. 336; Wharton v. Real Estate Investment Co., 180 Pa. 168; Burrows v. Carson, 53 Pa. Superior Ct. 488, affirmed, 244 Pa. 6.

We are asked to. distinguish this case from that of Burrows v. Carson, supra. The lien was there filed for *303work and labor done and materials furnished in finishing and erecting stairs. The subcontract was for nineteen houses. It was in writing, pursuant to a written bid and acceptance by the contractor. The lien filed averred specifically the kind of materials furnished, their price and the “exact date at which each item was furnished.” The claim contained an item for the labor which “went into and its results became a constituent part of the building.” It was stated as follows: “1911, April 4 to Nov. 20, — 137 hours labor at 60 cents per hour, $82.20.” This labor was a part of the “finishing and erecting stairs” as contracted for. It did not specifically appear whether that work was done at the shop of the subcontractor, or when the materials appeared upon the ground and were made into the stairs. This item for labor was not itemized with the dates when the work was done, “it did not mention any specific day upon which any.work was done.” Speaking of this question as to time, Mr. Justice Mestkezat, in affirming this court, in Burrows v. Carson, supra, says: “The only information as to the time when the labor was furnished is the statement that it was performed between the dates of April 4 and November 20, 1911, that is, some time during a period of over seven months. Such claims have never been held to be sufficient as to the kind of work or the time when it was done, either under the present or prior legislation on the subject. They fail to give the necessary information to the owner to enable him to determine the correctness of the claim for which the contractor is primarily liable. The claimant here is a subcontractor who dealt with the contractor and not with the owner, and the latter is liable for the debt which is that of the contractor only when the claimant complies with the provisions of the statute which gives him the lien. We have uniformly held under a similar statute that claims such as the one here, in controversy are defective on their face and will be stricken off. McFarland v. Schultz, 168 Pa. 634, is al*304most identical with the case in hand.” If it was essential to the validity of that lien filed under a written contract that the dates when the labor was done on a specific job, with the prices, should be set forth, for the same reason it is equally important to the validity of this lien that the dates when the materials are furnished be not omitted. The averment that the first item was furnished December 13,1910, and the last October 28,1911, will not be sufficient. Between these two dates more than one hundred items are listed. The lien states they were continuously furnished or furnished at different times. When were the items just before the last item furnished? We cannot say that all but the last item were furnished on the first date given. The lien expressly states otherwise but even if this be true, that certainly would not be such continuous furnishing under a written contract to swing the lien within the time required by the statute. Here again enters the character of the work to be done. What we said on this subject in Pierce v. Rodgers; Crane v. Rodgers No. 1, and Brant v. Hartrick in opinions this day handed down is applicable here. We are unable to distinguish Burrows v. Carson from this case in this respect. We cannot localize this feature of that opinion into a ruling that it applied to labor only. Hád it been a contract for labor, this argument might have some force. It was a contract for labor and materials going into and forming a finished stairs. ' The argument that the owner has no more information as to the justness of his claim even if the dates had been set forth when the material was supplied, does not meet the objection raised by Mr. Justice Mestrezat that the owner “is liable for the debt only when the claimant complies with the provisions of the statute which gives him the lien.”

' The Act of 1905 specifies “the time when the materials were furnished.” It may be these dates are of no importance in arriving at the justness of his claim, but these liens are of statutory origin for the benefit of a special class of creditors, and parties seeking to avail *305themselves of this remedy must strictly comply with the act. The additional argument that the subcontractor, in dealing with a building contract of this nature, does not usually keep the dates of furnishing when he works under such contract, but an account showing just what articles were furnished in accordance with the contract until he completes his undertaking, and that the requirement as to dates imposes an undue burden on the subcontractor, cannot be considered. Whatever merit there may be in this contention, the question was settled in Burrows v. Carson, supra. The importance of dates to an owner investigating the correctness of a bill is material. A great deal of this work is concealed and the truthfulness of the bill of particulars could be inquired into only by knowing the time they were furnished, that the owner might on investigation, through those who worked there at the time, determined in some degree their correctness. The dates of furnishing are also very important to show whether it has been continuous, although the written contract and character of work would to some extent control this question. ( .

The assignments of error are overruled and the judgment is affirmed at the cost of the appellant.