USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 1 of 25
[PUBLISH]
In the
United States Court of Appeals
For the Eleventh Circuit
____________________
No. 20-14560
____________________
SOUTHERN COAL CORPORATION,
JAMES C. JUSTICE, II,
Plaintiff-Counter Defendants-Appellee-Cross Appellants,
versus
DRUMMOND COAL SALES, INC.,
Defendant-Counter Claimant-Appellant-Cross Appellee.
____________________
Appeals from the United States District Court
for the Northern District of Georgia
D.C. Docket No. 1:17-cv-01104-WMR
____________________
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 2 of 25
2 Opinion of the Court 20-14560
Before WILSON, LAGOA, and ED CARNES, Circuit Judges.
WILSON, Circuit Judge:
Drummond Coal Sales, Inc.’s (Drummond) motion to
amend this court’s judgment is GRANTED. We vacate our prior
opinion in this appeal, Southern Coal Corporation v. Drummond
Coal Sales, Inc., 25 F.4th 864 (11th Cir. 2022), and substitute for it
this one. Accordingly, Southern Coal Corporation’s (Southern
Coal) petition for rehearing en banc of the now-vacated opinion is
DENIED AS MOOT.
This appeal concerns a pricing dispute over a contract to
transfer and store coal between plaintiff Southern Coal and defend-
ant Drummond. The district court found Southern Coal breached
the contract and awarded a judgment in favor of Drummond in the
amount of $6,860,000 and $1,473,699.87 in prejudgment interest.
Drummond appeals this judgment on the ground that the district
court erred in finding a price escalation clause in the contract to be
unenforceable. If this price escalation were enforceable, then
Drummond would be entitled to even more damages under the
contract for Southern Coal’s breach. For its part, Southern Coal
cross-appeals the district court’s judgment, claiming that Drum-
mond’s actions excused Southern Coal’s obligation to pay Drum-
mond under the contract. Both parties challenge the district’s
court determination not to award attorneys’ fees to either party.
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 3 of 25
20-14560 Opinion of the Court 3
We affirm the district court’s judgment against Southern
Coal in the amount of $6,860,000 plus $1,473,699.87 in prejudg-
ment interest for a total of $8,333,699.87. The district correctly
found that Southern Coal was not excused from performing under
the contract. Further, the district court correctly found the price
escalation clause unenforceable. However, we reverse on the issue
of attorneys’ fees and remand to the district court to award a rea-
sonable sum to the prevailing party, Drummond.
I. BACKGROUND
The disputed contract in this case is called the Bulk Coal
Transfer and Storage Agreement (Agreement). Southern Coal en-
tered the four-year Agreement with Drummond in October 2013.
Under the Agreement, Drummond would sublease port capacity
located in Newport News, Virginia to Southern Coal. In exchange
for Drummond’s services under the Agreement, Southern Coal
agreed to transfer through Drummond’s port a minimum of 2 mil-
lion metric tons of coal per year and pay Drummond a “minimum
monthly Throughput Fee of $1,000,000.” Southern Coal’s then-
president, James C. Justice II, contemporaneously executed a guar-
antee of Southern Coal’s obligations under the Agreement.
Central to this dispute, § 6.14 of the Agreement provides
that the base amount for the Throughput Fee would be adjusted
upward based on increases in the “Peak Downs metallurgical
benchmark price.” “Peak Downs” refers to a mine in Australia
owned by Australian mining company BHP Billiton (BHP). BHP
is one of the leading coal exporters in Australia and produces high-
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 4 of 25
4 Opinion of the Court 20-14560
quality metallurgical coal. Metallurgical coal, often referred to as
coking coal, is a primary component of steel manufacturing. As
used here, “benchmark” refers to a negotiated price between min-
ing companies and Asian steelmakers. Beginning in the 1980s, BHP
would negotiate a yearly benchmark price for its high-quality met-
allurgical coal with Japanese steelmakers. This benchmark was
published in industry newsletters and the price would serve as the
market price of metallurgical coal for the year and other coal com-
panies would use the benchmark in negotiating their own con-
tracts.
For more than twenty years, BHP set the yearly benchmark
price for metallurgical coal. Around 2008, BHP announced that it
wanted to transition from a yearly negotiated benchmark price to-
ward a quarterly, monthly, and eventually, a daily negotiated price.
The last annually negotiated benchmark price was settled in 2009
and by the second quarter of 2010, the industry began using a quar-
terly benchmark price. When the parties entered the Agreement
in 2013, the industry was still using a quarterly benchmark, rou-
tinely negotiated and set by BHP. However, by the fourth quarter
of 2016, BHP moved away entirely from quarterly pricing, which
resulted in the published quarterly benchmark price being set by
other Australian coal producers.
Starting in the fourth quarter of 2013, Drummond began in-
voicing Southern Coal for the monthly Throughput Fee of $1 mil-
lion. Initially, Southern Coal paid these invoices without issue.
During this time, the price of metallurgical coal was relatively low
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 5 of 25
20-14560 Opinion of the Court 5
and the price escalation clause of the Agreement had consequently
not been triggered. In the fourth quarter of 2016, however, the
quarterly benchmark price of metallurgical coal, set by a company
other than BHP, rose to $200 per metric ton. Drummond consid-
ered this price increase to trigger § 6.14 of the Agreement. Accord-
ingly, Drummond sent Southern Coal an invoice on October 25,
2016 for $1,380,000, a figure which reflected a $380,000 increase in
the minimum monthly Throughput Fee. Drummond invoiced
Southern Coal for the same amount for November and December
2016.
In the first quarter of 2017, the quarterly benchmark price
for metallurgical coal—as reported in industry publications—rose
again to $285 per metric ton. Accordingly, Drummond sent South-
ern Coal an invoice on January 3, 2017, for $1,965,000, which in-
cluded a $965,000 increase in the minimum monthly Throughput
Fee. Southern Coal paid $1,000,000 of the invoice on February 6,
2017, but it refused to pay the remaining $965,000. After that pay-
ment, Southern Coal refused to pay any further invoices.
Southern Coal contested these invoices because it claimed
that the “Peak Downs” benchmark to which § 6.14 of the Agree-
ment referred ceased to exist as BHP was no longer setting the
quarterly benchmark price. Therefore, there was no longer a
mechanism for price adjustments under § 6.14 of the Agreement.
Southern Coal sent a letter to Drummond on March 9, 2017, de-
manding adequate assurances that Drummond would not charge
any increase to the Throughput Fee and would only charge the
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 6 of 25
6 Opinion of the Court 20-14560
minimum $1 million. Drummond sent a reply letter to Southern
Coal asserting its right to increase the Throughput Fee because §
6.14 still applied regardless of which company set the quarterly
benchmark, and that Southern Coal had no right to withhold pay-
ments.
Southern Coal sued Drummond and asserted claims for a
declaratory judgment and breach of contract. Drummond asserted
counterclaims against Southern Coal and Justice for declaratory
judgment, breach of contract, and breach of a corresponding guar-
antee. Both parties moved for summary judgment. The district
court found that § 6.14 of the Agreement was ambiguous and sent
the issue of the meaning of the term “Peak Downs metallurgical
benchmark price” to trial. However, the district court concluded
that Southern Coal was still liable for the minimum monthly
Throughput Fee of $1 million.
At a bench trial, the district court heard testimony from both
parties on the meaning of the ambiguous term. Ultimately, the
district court found that the term “Peak Downs metallurgical
benchmark price” was intended by the parties to be, specifically,
the quarterly price set by BHP for its coal that was mined from its
Peak Downs mine and sold to Japanese steelmakers. The district
court found the testimony of Dennis Steul, Drummond’s vice pres-
ident of sales and the primary negotiator of the terms of the Agree-
ment, to be the more credible and persuasive evidence of the par-
ties’ intent. Accordingly, the district concluded that § 6.14 became
unenforceable when BHP ceased setting the quarterly benchmark
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 7 of 25
20-14560 Opinion of the Court 7
price for metallurgical coal. However, because the Agreement
contained a savings clause, the district court determined that the
price escalation clause could be severed and the remainder of the
Agreement was valid. As a result, the district court granted judg-
ment in favor of Drummond in the amount of $6,860,000 against
Southern Coal and Justice.
Drummond raises three purported errors of the district
court on appeal: (1) evidence of industry usage establishes that §
6.14 is unambiguous and therefore extrinsic evidence of the parties’
intent should not have been admitted in interpreting the Agree-
ment; (2) instead of finding § 6.14 unenforceable, the Agreement
should have been equitably reformed to reflect the parties’ inten-
tions; and (3) attorneys’ fees should be awarded to Drummond as
provided for in the Agreement. On the other hand, Southern Coal
contends that the district court erred in not finding that Drum-
mond’s actions constituted anticipatory repudiation and material
breach of the Agreement. It also argues that the guarantee should
not be enforced against Justice.
II. DRUMMOND’S ISSUES ON APPEAL
A. Ambiguity of the Agreement
Drummond argues that the district court erroneously relied
on extrinsic evidence of the parties’ intent to interpret the Agree-
ment because evidence of industry usage establishes that the
Agreement is unambiguous. According to Drummond, the Agree-
ment is unambiguous based on evidence of industry usage that
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 8 of 25
8 Opinion of the Court 20-14560
demonstrates there is only one quarterly benchmark for the price
of metallurgical coal at any given time. To everyone in the indus-
try, the argument goes, the reference to the “Peak Downs metal-
lurgical benchmark price” refers unequivocally to the one and only
benchmark price.
The interpretation of a contract, including whether it is am-
biguous, is a question of law that we review de novo. Reynolds v.
Roberts, 202 F.3d 1303, 1313 (11th Cir. 2000). “Questions of fact
arise only when an ambiguous contract term forces the court to
turn to extrinsic evidence of the parties’ intent, such as precontract
negotiations, to interpret the disputed term.” Laws. Title Ins.
Corp. v. JDC (America) Corp., 52 F.3d 1575, 1580 (11th Cir. 1995).
If a contract is ambiguous “and the trial court must look to extrinsic
evidence to determine the parties’ intent, we review its findings of
fact . . . as to the parties’ intent for clear error.” Reynolds, 202 F.3d
at 1313.
The parties agree that New York law applies to this dispute.
Under New York law, “[i]n determining the obligations of parties
to a contract, courts will first look to the express contract language
used to give effect to the intention of the parties, and where the
language of a contract is clear and unambiguous, the court will con-
strue and discern that intent from the document itself as a matter
of law.” Williams v. Vill. of Endicott, 936 N.Y.S.2d 759, 761 (N.Y.
App. Div. 2012). “Evidence outside the four corners of the docu-
ment as to what was really intended but unstated or misstated is
generally inadmissible to add to or vary the writing.” W.W.W.
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 9 of 25
20-14560 Opinion of the Court 9
Assocs., Inc. v. Giancontieri, 566 N.E.2d 639, 642 (N.Y. 1990). Ex-
trinsic evidence may be considered to determine the parties’ intent
if the contract is ambiguous. Fattorusso v. RJR Mechanical, Inc.,
16 N.Y.S.3d 844, 846 (N.Y. App. Div. 2015). But extrinsic evidence
may not be used to create ambiguity in a contract that is “complete
and clear and unambiguous upon its face.” W.W.W. Assocs., 566
N.E.2d at 642.
In the context of a specialized trade or business contract,
“[c]ontract terms are considered ambiguous if they are capable of
more than one meaning when viewed objectively by a reasonably
intelligent person who has examined the context of the entire inte-
grated agreement and who is cognizant of the customs, practices,
usages and terminology as generally understood in the particular
trade or business.” Lightfoot v. Union Carbide Corp., 110 F.3d 898,
906 (2d. Cir. 1997) (internal quotation marks omitted) (applying
New York law). Conversely, “contract language is not ambiguous
if it has a definite and precise meaning, unattended by danger of
misconception in the purport of the contract itself, and concerning
which there is no reasonable basis for a difference of opinion.”
Hugo Boss Fashions, Inc. v. Fed. Ins. Co., 252 F.3d 608, 617 (2d Cir.
2001) (alterations adopted) (applying New York law). However, it
is possible that “even where a contract does not define a particu-
lar—and potentially ambiguous—term, a body of state law or an
established custom fills in the gaps left by the drafters.” Hugo Boss,
252 F.3d at 617. “Custom” may also refer to industry usage of a
term. In fact, “[w]hen interpreting a state law contract . . . an
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 10 of 25
10 Opinion of the Court 20-14560
established definition provided by . . .industry usage will serve as
a default rule, and that definition will control unless the parties ex-
plicitly indicate, on the face of their agreement, that the term is to
have some other meaning.” Id. at 617–18. Accordingly, by looking
to evidence of industry usage, “a possible ambiguity may ulti-
mately be proven to be illusory.” Id. at 618.
As noted above, the threshold determination of whether a
contract is ambiguous is a question of law that we review de novo.
Reynolds, 202 F.3d at 1313. We conclude that the district court
made no legal error when it determined the Agreement to be am-
biguous. Contrary to Drummond’s argument, the district court
did consider evidence of industry usage of the term in ruling on
summary judgment. In its order, the court specifically noted that
although “coal industry publications referred to the agreed upon
quarterly price using various terms such as the ‘Peak Downs bench-
mark,’ the ‘Australian coking coal benchmark,’ or simply ‘the
benchmark,’ there is some evidence to show that it was understood
in the coal industry that the various terms denoted the same thing.”
Ordinarily, courts are bound to the four corners of the contract in
interpreting it, but there is an exception for evidence of industry
usage or custom, and this evidence may be considered in determin-
ing whether a contract is ambiguous. See Hugo Boss, 252 F.3d at
617–18. Here, the district court properly considered extrinsic evi-
dence of industry usage before deciding on ambiguity. However,
the district found that the Agreement, when read as a whole to de-
termine its purpose and intent, was ambiguous because both
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 11 of 25
20-14560 Opinion of the Court 11
parties had offered reasonable interpretations of the term. As a
contract is ambiguous if “capable of more than one meaning when
viewed objectively by a reasonably intelligent person,” we con-
clude that the district court made the proper legal determination
that the Agreement was ambiguous. Lightfoot, 110 F.3d at 906.
Once the district court determined that the Agreement was
ambiguous, it could properly hear extrinsic evidence as to the par-
ties’ intent at trial. Fattorusso, 16 N.Y.S.3d at 846. The district
court heard trial testimony from Dennis Steul, Drummond’s pri-
mary negotiator on the Agreement, and Steve Doyle, an industry
expert called by Drummond. Doyle’s testimony demonstrated
that there has always been only one benchmark in the metallurgi-
cal coal industry and that there were a variety of terms used to de-
scribe this benchmark. As factfinder, the district court simply
found the testimony of Steul to be more credible and persuasive.
Steul’s testimony corroborated the finding that the term in the
price escalation clause was intended by the parties to be, specifi-
cally, the quarterly price set by BHP for the coal from its Peak
Downs mine that was sold to Japanese steelmakers. Steul testified
that he always considered Peak Downs to be a reference to the
mine owned by BHP. The district court was entitled to credit that
testimony.
Even more convincing was Steul’s testimony that in a con-
tract with another customer, Drummond priced the contract based
on the price of coal from another specific mine besides the Peak
Downs mine. Furthermore, that contract contained language
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 12 of 25
12 Opinion of the Court 20-14560
stating that, if the price for that mine was unavailable, the parties
would mutually agree to an alternative quarterly price basis. In the
Agreement here, there was no language that gave the parties the
right to use a different quarterly price for coal. The Agreement
instead tied increases in price to the Peak Downs price, which Steul
conceded was a reference to the mine owned by BHP. When BHP
stopped setting a quarterly benchmark price, the district court con-
cluded that the price escalation clause in the Agreement then be-
came unenforceable.
When the district court considers extrinsic evidence of the
parties’ intent in interpreting an ambiguous contract, this presents
a question of fact that we review for clear error. Reynolds, 202 F.3d
at 1313. Here, the district court did not clearly err in crediting
Southern Coal’s position in interpreting the contract because the
parties’ testimony at trial and the facts of this case supported this
interpretation. When the parties entered the Agreement, BHP was
routinely setting a quarterly benchmark price—thus, the price es-
calation clause was tied to the Peak Downs benchmark. However,
during the course of the Agreement, BHP stopped this practice.
We therefore ask, if BHP is no longer setting a quarterly bench-
mark for its Peak Downs mine, then how can the price escalation
clause remain enforceable? Drummond argues that this is made
possible by changing the term “Peak Downs metallurgical bench-
mark price” to “the quarterly benchmark price as agreed by mining
companies and Asian steel producers and as published in industry
newsletters.” However, if that is what the parties intended, why
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 13 of 25
20-14560 Opinion of the Court 13
did the parties, who are sophisticated and familiar with the indus-
try, not write the Agreement to so read? Regardless, the correct
approach here was clear. When BHP stopped setting the quarterly
benchmark price, the Agreement became unenforceable. See In re
Licata, 908 N.Y.S.2d 441, 442 (N.Y. App. Div. 2010) (“[W]here a
contract’s material terms are not reasonably definite, the contract
is unenforceable.”). Accordingly, we conclude that the district
court made no legal error in finding the Agreement ambiguous and
further, its decision to find the price escalation clause unenforcea-
ble was not clearly erroneous.
B. Equitable Reformation of the Agreement
Next, Drummond argues that even if the contract is ambig-
uous, the Agreement should be reformed to reflect the parties’ in-
tentions. We disagree.
Under the equitable reformation doctrine, “courts of equity
will reform a written contract where, owing to mutual mistake, the
language used therein did not fully or accurately express the agree-
ment and intention of the parties.” Philippine Sugar Ests. Dev. Co.
v. Gov’t of Philippine Islands, 247 U.S. 385, 389 (1918) (emphasis
added).
Drummond argues that the mutual mistake here was that
the parties thought that BHP always set the quarterly benchmark
price, when in fact, prior to entering the Agreement, companies
other than BHP had set the quarterly benchmark price. However,
this does not appear to be an issue of a mutual mistake, but rather
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 14 of 25
14 Opinion of the Court 20-14560
a lack of due diligence by these sophisticated parties before enter-
ing the Agreement. See Thompson v. McQueeney, 868 N.Y.S.2d
443, 447 (N.Y. App. Div. 2008) (“[W]ith a minimum degree of due
diligence, defendants’ mistake . . . would have been readily appar-
ent.”). Furthermore, the district court determined that the intent
of the parties was that the price escalation clause was a specific ref-
erence to the Peak Downs mine. Therefore, we cannot say the
Agreement does not “fully or accurately express the agreement and
intention of the parties.” Phillipine Sugar Ests. Dev. Co., 247 U.S.
at 389. At best, this was a unilateral mistake on the part of Drum-
mond. The only apparent mutual mistake here was a poorly
drafted contract. Therefore, Drummond’s claim for equitable
reformation fails.
C. Attorneys’ Fees
Lastly, Drummond argues that the district court erred in
denying its request for attorneys’ fees. We agree.
We review the district court’s denial of attorneys’ fees for an
abuse of discretion. In re Trinity Indus., Inc., 876 F.2d 1485, 1496
(11th Cir. 1989). Under New York law, a prevailing party in a
breach of contract case may not collect attorneys’ fees and costs
from the non-prevailing party unless such an award is authorized
by the contract, statute, or court rule. TAG 380, LLC v. ComMet
380, Inc., 890 N.E.2d 195, 201 (N.Y. 2008). In determining the pre-
vailing party for purposes of awarding attorneys’ fees, the court
must consider “the true scope of the dispute litigated, followed by
a comparison of what was achieved within that scope.” Duane
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 15 of 25
20-14560 Opinion of the Court 15
Reade v. 405 Lexington, L.L.C. 798 N.Y.S.2d 393, 394 (N.Y. App.
Div. 2005). New York courts have also said that a prevailing party
“must simply prevail on the central claims advanced, and receive
substantial relief in consequence thereof.” Sykes v. RFD Third
Ave. I Assocs., LLC, 833 N.Y.S.2d 76, 77–78 (N.Y. App. Div. 2007).
The district court determined that since neither party was
the “prevailing party” an award of attorneys’ fees was inappropri-
ate. While Drummond succeeded on its claim regarding the mini-
mum Throughput Fees under the Agreement, Southern Coal suc-
ceeded on its claim regarding the escalated fees. Although Drum-
mond’s victory was not total because it did not obtain judgment
for the escalated fees, its “central claim” was that Southern Coal
breached the Agreement by failure to pay the monthly Through-
put Fee. The district court entered judgment in favor of Drum-
mond for $6.86 million based on Southern Coal’s breach in this re-
gard. This qualifies as “prevail[ing] on the central claims ad-
vanced.” See Sykes, 833 N.Y.S.2d at 77–78. A litigant’s success does
not have to be total to be considered the prevailing party. See
Duane Reade, 798 N.Y.S.2d at 394 (“That the landlord’s success at
trial was only partial does not negate the fact that it prevailed.”).
Therefore, we conclude that the district court abused its discretion
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 16 of 25
16 Opinion of the Court 20-14560
in not awarding attorneys’ fees to Drummond because Drummond
was the prevailing party. 1
New York law states that “when a contract provides that in
the event of litigation the losing party will pay the attorneys’ fees
of the prevailing party, the court will order the losing party to pay
whatever amounts have been expended by the prevailing party, so
long as those amounts are not unreasonable.” F.H. Krear & Co. v.
Nineteen Named Trustees, 810 F.2d 1250, 1263 (2d Cir. 1987) (ap-
plying New York law). Accordingly, we remand to the district
court for a determination of whether the attorneys’ fees Drum-
mond requests are reasonable.
III. SOUTHERN COAL’S ISSUES ON CROSS-APPEAL
A. Anticipatory Repudiation
On its appeal, Southern Coal argues that the district court
erred in determining that Drummond’s actions did not constitute
an anticipatory repudiation. “An anticipatory breach of contract
by a promisor is a repudiation of a contractual duty before the time
fixed in the contract for . . . performance has arrived.” Princes
Point LLC v. Muss Dev. LLC, 87 N.E.3d 121, 124 (N.Y. 2017) (al-
teration adopted). An anticipatory breach of contract—also known
as an anticipatory repudiation—can be shown through statements
by the obligor to the obligee or an affirmative act by the obligor.
1In its brief, Southern Coal argues that it is the prevailing party for purposes
of attorneys’ fees. Because we conclude that Drummond is the prevailing
party, Southern Coal’s argument in this regard fails.
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 17 of 25
20-14560 Opinion of the Court 17
Id. “For an anticipatory repudiation to be deemed to have oc-
curred, the expression of intent not to perform by the repudiator
must be ‘positive and unequivocal.’” Id. New York courts have
held that “a wrongful repudiation of the contract by one party be-
fore the time for performance entitles the nonrepudiating party to
immediately claim damages for a total breach.” Id. at 125.
Whether a party commits anticipatory repudiation of a contract is
a question of fact. O’ Connor v. Sleasman, 788 N.Y.S.2d 518, 520
(N.Y. App. Div. 2005).
When the price of coal increased to $285 per metric ton in
the first quarter of 2017, Southern Coal refused to pay its obliga-
tions under the Agreement because BHP was no longer setting a
quarterly benchmark price and the price escalation was therefore
invalid. Southern Coal sent a letter to this effect to Drummond in
March 2017 and demanded adequate assurances that Drummond
would not invoice more than the minimum $1 million per month.
Drummond responded that the price escalation clause remained
valid and it would continue to invoice Southern Coal based on the
quarterly benchmark price set by other companies. According to
Southern Coal, this response constituted anticipatory repudiation.
Notably, however, Drummond’s response stated, “Drummond’s
performance obligation is to provide Southern [Coal] with the
throughput services, and there is no question regarding Drum-
mond’s ability to provide these services.”
In its brief, Southern Coal cites to IBM Credit Fin. Corp. v.
Mazda Motor Mfg. (USA) Corp., where the New York court of
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 18 of 25
18 Opinion of the Court 20-14560
appeals held that a party’s “insistence on an untenable interpreta-
tion of a key contractual provision, and refusal to perform other-
wise, constituted an anticipatory breach of the contract.” 706
N.E.2d 1186, 1187 (N.Y. 1998). Thus, anticipatory repudiation re-
quires a refusal to perform under the contract. Here, Drummond’s
obligation under the Agreement was to provide throughput ser-
vices for its port to Southern Coal. At no point did Drummond
indicate that it would not perform that obligation. Therefore,
there can be no anticipatory repudiation. Accordingly, Southern
Coal’s argument that the district court should have excused South-
ern Coal from owing anything under the Agreement based on an-
ticipatory repudiation is without merit.
B. Material Breach
Similar to its anticipatory repudiation argument, Southern
Coal argues that the district court should have found that Drum-
mond materially breached the Agreement and therefore Southern
Coal was discharged of its contractual obligations. A breach of con-
tract is material if it goes “to the root of the agreement between
the parties.” Frank Felix Assocs., Ltd. v. Austin Drugs, Inc., 111
F.3d 284, 289 (2d Cir. 1997) (applying New York law). Further, “[a]
party’s obligation to perform under a contract is only excused
where the other party’s breach of the contract is so substantial that
it defeats the object of the parties in making the contract” and the
court must consider “the special purpose of the contract” in mak-
ing this determination. Id.
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 19 of 25
20-14560 Opinion of the Court 19
The district court concluded that Southern Coal’s material
breach argument was “without merit.” Southern Coal contends
that the escalated invoices constitute material breach. The district
court specifically noted that “[t]he fact that Southern Coal may not
agree with the amount that Drummond invoiced does not mean
that Drummond breached its duty to invoice as required under
. . . the Agreement.” We agree with the district court’s determina-
tion that Drummond did not materially breach the Agreement.
The “root” of the Agreement was that Drummond would provide
throughput services to Southern Coal. At no point did Drummond
indicate that it would not perform this obligation.
Our conclusion is consistent with the Second Restatement
of Contracts’ approach to determining whether a breach is mate-
rial. The Restatement notes the following circumstances, among
others, are significant in making this determination: (1) “the extent
to which the party failing to perform or to offer to perform will
suffer forfeiture;” (2) “the likelihood that the party failing to per-
form or to offer to perform will cure his failure, taking account of
all the circumstances including any reasonable assurances;” and (3)
“the extent to which the behavior of the party failing to perform or
to offer to perform comports with the standards of good faith and
fair dealing.” Restatement (Second) of Contracts § 241 (1981) (em-
phasis added). Thus, central to the material breach analysis is the
party’s failure to perform. Because Drummond continued to per-
form its obligations under the Agreement and because Drum-
mond’s breach in this case went to pricing, and not to the
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 20 of 25
20 Opinion of the Court 20-14560
Agreement’s “special purpose” of providing throughput services,
we cannot say that Drummond’s breach in this regard was mate-
rial. Frank Felix Assocs., Ltd., 111 F.3d at 289. Accordingly, we
conclude that Drummond did not materially breach the Agree-
ment and Southern Coal was not thereby excused from performing
its obligations under the Agreement.
C. Justice’s Liability under the Guarantee
Lastly, Southern Coal argues that if the award against it is va-
cated, then the award against Justice must also be vacated. How-
ever, since we are affirming the district court’s judgment against
Southern Coal, we need not address this argument. Regarding the
award of attorney fees, the guarantee agreement, signed by Justice,
provides that he “agrees to pay all expenses, including, without lim-
itation, all reasonable fees and expenses of outside counsel which
may be paid or incurred by [Drummond] in enforcing or asserting
any of their respective rights under this Guarantee.” Therefore,
the guarantee provides that Justice may also be liable for attorneys’
fees incurred by Drummond. We conclude that the judgment
against Justice stands and he is also liable for the additional award
of attorneys’ fees if Southern Coal is unable to pay Drummond for
this obligation.
IV. CONCLUSION
In sum, we affirm the district court’s judgment against
Southern Coal and Justice in the amount of $6,860,000 plus
$1,473,699.87 in prejudgment interest for a total of $8,333,699.87.
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 21 of 25
20-14560 Opinion of the Court 21
We conclude that the district court correctly found as a matter of
law that the price escalation clause in the Agreement was ambigu-
ous. We further conclude that district court did not clearly err in
interpreting this provision at trial and finding it unenforceable. We
also reject Drummond’s claim of equitable reformation and South-
ern Coal’s claims of anticipatory repudiation and material breach.
Lastly, we conclude that the district court erred in not awarding a
reasonable sum of attorneys’ fees to Drummond. Therefore, we
reverse on the issue of attorneys’ fees and remand to the district
court to determine a reasonable sum.
AFFIRMED in part, and REVERSED and REMANDED in
part.
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 22 of 25
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 23 of 25
20-14560 ED CARNES, J., Concurring 1
ED CARNES, Circuit Judge, concurring in part and concurring in
the judgment:
I concur in the panel’s judgment and most of its opinion, in-
cluding the conclusion that Drummond is entitled to a reasonable
amount of attorney’s fees. But I disagree about why Drummond
is entitled to them.
Unlike the majority opinion, I don’t think a prevailing party
analysis is the right attorney’s fees framework. The parties’ agree-
ment calls for a different framework, and under New York law that
choice should be honored. The agreement provides that the “De-
faulting Party shall indemnify the Non-Defaulting Party for any ex-
penses and costs, including attorney fees, arising out of or relating
to any default under this Agreement or any effort to collect pay-
ment.” And it defines a “Defaulting Party” as a party who, among
other things, “fails to make a payment as required under this Agree-
ment.”
Those contract terms matter because when considering
whether to award attorney’s fees in a contract dispute, New York
courts generally follow the terms of the contract. Admittedly, the
caselaw is not crystal clear, but the courts of that state don’t appear
to apply a prevailing party analysis where the contract provides
otherwise. Instead, they apply a “defaulting party” analysis when
the terms of the contract call for it and a “prevailing party” analysis
when the terms of the contract call for that.
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 24 of 25
2 ED CARNES, J., Concurring 20-14560
New York decisions have addressed contracts with “default-
ing party” language that is similar to the language used in the agree-
ment in this case. Those decisions have awarded attorney’s fees
based on whether a party “defaulted” instead of whether a party
“prevailed.” See Violet Realty, Inc. v. Amigone, Sanchez & Mat-
trey, LLP, 183 A.D.3d 1278, 1280–81 (N.Y. App. Div. 2020) (“The
lease provided that, in the case of a default, the default-
ing party is liable for the payment of, among other things, the
other party's reasonable attorneys’ fees. Defendant does not dis-
pute that it defaulted under the lease, and we conclude that the
court should have granted that part of plaintiff's motion seeking an
award of attorneys’ fees.”); LG Funding, LLC v. Johnson & Son
Locksmith, Inc., 170 A.D.3d 1153, 1154 (N.Y. App. Div. 2019); Sem-
pra Energy Trading Corp. v. P.G. & E. Tex. VGM, L.P., 284 A.D.2d
253, 254 (N.Y. App. Div. 2001) (“An award of attorneys’ fees was
proper since the parties expressly provided in their contract that, in
the event of a default, the defaulting party would be responsible for
costs and expenses, including attorneys' fees, incurred by the per-
forming party as a result of the default.”); Montgomery-Otsego-
Schoharie Solid Waste Mgmt. Auth. v. Cnty. of Otsego, 249 A.D.2d
702, 703–04 (N.Y. App. Div. 1998) (“Defendant's failure to pay the
GAT shortfall amount due under the contract constituted a default;
consequently, under the provision for counsel fees in the event of
a default, . . . MOSA's cause of action for counsel fees should not
have been dismissed.”).
USCA11 Case: 20-14560 Date Filed: 03/28/2022 Page: 25 of 25
20-14560 ED CARNES, J., Concurring 3
By contrast, where the contract provided that attorney’s fees
should be awarded to a “prevailing party,” or didn’t specify what
analysis should be used to award attorney’s fees, New York courts
have applied a prevailing party analysis. See, e.g., TAG 380, LLC
v. ComMet 380, Inc., 890 N.E.2d 195, 201 (N.Y. 2008); Sykes v. RFD
Third Ave. I Assocs., LLC, 39 A.D.3d 279, 279 (N.Y. App. Div.
2007); Duane Reade v. 405 Lexington, L.L.C., 19 A.D.3d 179, 180
(N.Y. App. 2005).
The difference between a defaulting party analysis and a pre-
vailing party analysis might matter in some circumstances, albeit
not in these. As mentioned, the agreement provides that the “Non-
Defaulting Party” gets attorney’s fees from the “Defaulting Party,”
which includes a party that “fails to make a payment as required
under th[e] Agreement.” Southern Coal failed to make a payment
as required under the agreement; it is the “Defaulting Party.” For
that reason, I reach the same conclusion under the defaulting party
contractual provision as the majority reaches under the prevailing
party analysis.
There’s not much more that needs to be said about the
proper route to follow to get to the same result. Because the result
is the same either way, and because our decision does not bind any
New York court anyway, I’ll leave it at that.