No. 21-2150C
(Filed: March 11, 2022)
(Re-Filed: March 29, 2022) 1
**************************
PROGRESS FOR BAKERSFIELD
VETERANS LLC,
Plaintiff, Bid protest; post-award bid
protest; 28 U.S.C. §
v. 1491(b)(1); FAR 9.105-
2(a)(1) (2018); RCFC
THE UNITED STATES, 12(b)(1); RCFC 12(b)(6);
prejudice.
Defendant,
and
SASD DEVELOPMENT GROUP LLC,
Intervenor.
**************************
Elizabeth N. Jochum, Washington, DC, for plaintiff, with whom was
Michael J. Slattery, and Tjasse L. Fritz, of counsel.
John H. Roberson, Senior Trial Counsel, United States Department of
Justice, Civil Division, with whom were Brian M. Boynton, Acting Assistant
Attorney General, Patricia M. McCarthy, Director, and Douglas K. Mickle,
Assistant Director, for defendant. Kathryn M. Adams, Kristen S. Grotecloss,
General Attorneys, and Stephen M. Kelleher, Deputy Chief Counsel, United
States Department of Veterans Affairs, of counsel.
1
This opinion was originally filed under seal to afford the parties an
opportunity to propose redactions of protected information. The parties filed
a joint document with proposed redactions on March 25, 2022 (ECF No. 73).
We thus reissue this opinion with the proposed redactions.
Patrick T. Rothwell, Esq., Washington, DC, for intervenor. Jonathan
T. Williams, Katherine B. Burrows, and Lauren R. Brier, of counsel.
OPINION
BRUGGINK, Judge.
This is the second time we have had occasion to review a challenge
by plaintiff, Progress for Bakersfield Veterans, LLC (“PBV”), to actions by
the Department of Veterans Affairs (“VA”) arising out of this solicitation.
On December 9, 2019, the VA issued a solicitation for a 20-year lease of
30,100 square feet of space to be used for a Community Based Outpatient
Clinic providing primary, specialty, and mental health care to veterans in
Bakersfield, California. Plaintiff is the incumbent on the current lease, which
is being fulfilled at PBV’s facility located at 1801 Westwind Drive.
In its first protest, brought in August 2020, PBV filed a pre-award
protest challenging its exclusion from the competitive range. We rejected
the challenge and permitted the agency to proceed in negotiations with the
only remaining bidder, the intervenor, SASD Development Group, LLC
(“SASD”). Progress for Bakersfield Veterans, LLC, 151 Fed. Cl. 622 (2020)
(PBV I). Eventually the agency made an award to SASD, and, after an
unsuccessful protest at the General Accountability Office (“GAO”), plaintiff
commenced its second protest here.
PBV alleges that the VA violated the Federal Acquisition Regulation
(“FAR”) when it amended the solicitation without issuing a formal written
amendment, unlawfully awarded the lease to intervenor, and abused its
discretion by failing to cancel and reissue the solicitation in response to its
changed requirements. Plaintiff seeks a permanent injunction preventing the
VA from proceeding with the awarded lease. Defendant and intervenor filed
motions to dismiss for lack of standing, and alternatively, seek judgment on
the administrative record. Defendant also seeks dismissal of plaintiff’s
statutory arguments and plaintiff’s claim regarding the solicitation’s 24-
month provision. The motions are fully briefed, and oral argument was held
on March 3, 2022. For reasons explained below, we grant defendant’s
motion to dismiss plaintiff’s statutory arguments for lack of jurisdiction and
plaintiff’s claim regarding the solicitation’s 24-month provision on waiver
grounds. In addition, because we conclude that the VA did not waive
solicitation requirements by awarding the contract to SASD, we grant
defendant’s and intervenor’s motions for judgment on the administrative
record and deny plaintiff’s motion.
2
BACKGROUND
We assume familiarity with the facts set out in our decision in PBV I
and will not repeat the background to the prior protest.
A. PBV’s Pre-Award Protest in this Court
In PBV I, we denied PBV’s pre-award protest, finding that its ADA
and bias claims were barred by the doctrine of waiver. We rejected PBV’s
remaining substantive claims, holding that VA acted reasonably when it
evaluated the offers and removed PBV from the competitive range.
In that opinion, we described the shortcomings the Technical
Evaluation Board (“TEB”) and Source Selection Authority (“SSA”) found in
PBV’s three offers, which were found to be technically inadequate. PBV’s
Westwind 1 offer was rated overall as “marginal” with “several significant
weaknesses which were not readily correctible, including what [the TEB]
viewed as the space plan’s significant departure from VA’s concept plan, the
building structure’s functional, programmatic, and spatial relationship issues,
and the current design’s operational problems for managing clinic resources,
which would require a major re-design effort.” AR 12374. PBV’s Westwind
2 offer received an overall “poor” technical rating because it contained
“numerous weaknesses, including a building interior that appeared to be
sterile and not patient-centric and because the floor plan failed to implement
the model required by the solicitation.” AR 12387-88. PBV’s [ ]
proposal received an overall “marginal” technical rating because the proposal
“contained several significant weaknesses which were not readily
correctable, including parking discrepancies, failure to present detail
regarding its plan for successful contract completion, and failure to explain
a strategy for sequencing the work as the solicitation required.” AR 12378.
We found no error in the agency’s determination, not only that
“SASD’s proposal was the most highly rated, but that the three remaining
proposals were qualitatively so much poorer that there was no point including
any of them in the competitive range.” 151
Fed. Cl. at 637-38. We determined that the VA’s decision to leave only the
most highly rated proposal, that of SASD, in the competitive range was
supported by the record and was not arbitrary or capricious.
B. Amendment Four and Award
After our 2020 decision, the VA entered into negotiations with SASD
regarding the award of a lease. On January 15, 2021, the VA issued
3
Amendment four and called for a revised offer from SASD due, in part, to
added costs for cleaning due to COVID-19 specifications and because the
lengthy delay due to protest proceedings coincided with increases in Labor
Department wage rate increases.
The amendment made several changes to the solicitation. It removed
an alternative for the space to be delivered within 20-months, leaving only
the 24-month delivery time frame. The amendment also included the
updated Department of Labor wage determinations and added cleaning
requirements due to the COVID-19 epidemic. This change also included a
reservation of the right to “unilaterally cancel this routine cleaning and
disinfecting at any time during the Lease term and, in such a case, the rental
rate will be reduced by the amount specified . . . .” AR 17088.
SASD’s second revised offer was considerably higher in price than its
first revised offer. This prompted a negotiation call between the VA and
SASD on February 10, 2021. During that call, “[s]ingle line items were
discussed, with many costs increasing based on the procurement delay and
COVID protocols inserted by VA and how COVID is influencing
construction pricing for both materials and labor (the later having the biggest
impact.)” AR 17233. The negotiations resulted in the VA requesting a third
revised offer from SASD, “which offered a rent reduction of [ ] on a
full-service basis on a net usable square foot basis.” Id. The agency’s final
price evaluation further states that “[o]f that rent savings, [ ] was
captured with a reduction in operating expenses.” Id.
The VA then completed a scoring analysis of SASD’s third revised
offer. Pursuant to the solicitation, offers had to score as an operating lease
under the OMB Circular A-11, Appendix B to be eligible for award. To score
as an operating lease “the present value of the minimum contractually
required payments over the life of the lease cannot exceed 90 percent of the
fair market value (“FMV”) of the asset at the beginning of the lease term.”
AR 33219. The VA calculated the price of SASD’s lease to be [ ]
percent of FMV, below the 90 percent threshold.
On March 15, 2021, the Contracting Officer issued an award decision
memorandum finding that SASD
offered the VA a 30,100 NUSF building which offered the best
value to the Government. It is, therefore, the CO’s
determination that the proposal submitted by SASD for a 20-
year firm term lease is fair and reasonable and represents the
4
best value to the Government. I hereby recommend the
acceptance of the SASD offer.
AR 17502-03. The agency summarized the awardee’s offer as follows:
annual unserviced rent for years one through twenty at [ ], along with
a lump sum payment of [ ]. The VA and SASD executed the lease on
April 26, 2021. The following day, VA provided PBV a post-award
debriefing.
C. PBV’s Post-Award GAO Protests
On May 6, 2021, PBV filed a new protest at GAO, raising three
allegations. PBV argued that, when VA issued amendment four, it should
either have provided the amendment to PBV or re-solicited the lease; that the
agency improperly treated SASD’s proposed lease as an operating lease, as
opposed to a capital lease; 2 and that VA unreasonably failed to reopen the
solicitation in light of SASD’s increased price. PBV also argued in a
supplemental protest that VA should have cancelled or amended the
solicitation because, in its view, SASD’s clinic site would not be able to meet
environmental assessment requirements and, as a result, SASD would not be
able to meet the lease’s 24-month completion deadline.
On August 11, 2021, GAO denied PBV’s protest. It held that the
amendment did not change the terms and conditions of the solicitation in any
material way; that the VA was not required to provide the solicitation
amendment to PBV because its offer was not in the competitive range and
the subject of the amendment was not directly related to the reasons that VA
excluded PBV from the competitive range; and that PBV’s arguments
concerning the operating lease calculation and environmental requirements
were untimely. Progress for Bakersfield Veterans, LLC, B-418703.7 et al.,
2021 CPD ¶ 303 (Comp. Gen. Aug. 11, 2021). In addition, the GAO held
that PBV’s argument that SASD would not be able to complete the
construction of the clinic in 24 months was not supported by the record. Id.
On November 8, 2011, PBV filed its complaint here.
2
For purposes of calculating whether a lease can be considered an operating
lease, the solicitation instructs that the amount for items that the agency will
pay as a lump sum upfront are excluded from the amount of rent payments if
those items are associated with special features or enhancements to meet the
government’s needs or agency specific customization.
5
DISCUSSION
PBV makes several arguments, but during oral argument it focused on
five: (1) That the VA violated various statutory limitations on the
appropriations available for the lease; (2) that the VA’s award to SASD
amounted to a waiver of the solicitation’s 24-month delivery provision; (3)
argues that the VA waived the solicitation’s requirement that the offeror
show control over the property over which it intended to build a facility; (4)
that the VA unlawfully amended the solicitation by awarding a lease to
SASD even though SASD’s proposal did not score as an operating lease; (5)
and that the VA reduced the importance of price by awarding SASD’s
proposal at a [ ] price premium in comparison to PBV’s lowest-priced
offer.
Our review is deferential in accordance with the standard set forth in
the Administrative Procedures Act, 5 U.S.C. § 706, which is to say that we
review agency action in a procurement for illegality and a lack of rationality.
Impressa Construzioni Geom. Domenico Garufi v. United States, 238 F.3d
1324, 1332-33 (Fed. Cir. 2001). So long as the agency’s decision was not
irrational or otherwise illegal, we will leave it undisturbed.
I. Motions to Dismiss
Defendant moves to dismiss several claims on jurisdictional and
waiver grounds and more broadly asserts that the complaint should be
dismissed for lack of standing. Intervenor makes the latter point as well in
its own motion to dismiss.
A. Jurisdiction
The government moves to dismiss plaintiff’s statutory claims for
lack of jurisdiction. PBV argues that the award to SASD ran afoul of three
legislative prohibitions concerning lease funding. It cites the ADA, Public
Law 113-146, § 602, and 38 U.S.C. § 8104. Plaintiff’s statutory arguments
are premised on the notion that the lease could not exceed the $3.4 million
authorized by Congress in 2009 in PL 111-82. Assuming that figure is
correct, the twenty-year lease would have violated the Anti-Deficiency Act,
31 U.S.C. § 1341, in its first year, according to plaintiff. In addition,
Section 8104 requires the VA to notify Congress of the terms of the lease,
which plaintiff contends was not done. See 38 U.S.C. § 8104(b) (2018).
Finally, plaintiff asserts that the VA violated § 602 by not having up-front
budget authority in an “amount equal to total payments under the full term
6
of the lease or [an] amount sufficient to cover first year lease payments plus
cancellation costs.” Public Law 113-146, § 602(a)(3).
Defendant disagrees with the factual predicates to these contentions
but principally argues that this court lacks jurisdiction to entertain any of
these allegations because they concern appropriation provisions and not
procurement statutes. It points out that our jurisdiction under 28 U.S.C. §
1491(b), extends only to “challenges to statutes or regulations ‘in connection
with a procurement or proposed procurement.’” Cleveland Assets, LLC v.
United States, 883 F.3d 1378, 1381-82 (Fed. Cir. 2018). The government
argues that none of the cited statutes are properly characterized as
procurement statutes. We agree.
First, Public Law 113-146, § 602(b) details the mechanism through
which the VA is to record lease obligations relative to, and “[s]ubject to the
availability of appropriations provided in advance.” Section 602(b)(1). This
statute “says nothing of how [the agency] must run its procurement once the
appropriation is made.” Cleveland Assets, 883 F.3d at 1382. Similarly, 38
U.S.C. § 8104 does not describe “procurement procedures for any . . .
construction, alteration, or lease.” Id. Instead, 38 U.S.C. § 8104 identifies
“‘what material must be included in the ‘prospectus of a proposed project,’”
and when “the maximum cost may be increased.” 38 U.S.C. § 8104(b)(1)
(detailing the material that must be included in a prospectus provided to
Congress with respect to a medical facility lease). Likewise, Public Law
111-82, does not direct how a procurement is to be made, but only provides
an initial authorization for the lease amount. We conclude that Congress has
not given the court a role, in the context of a procurement dispute, with
enforcing these provisions. They “say[] nothing of how [the Agency] must
run its procurement once the appropriation is made.” Cleveland Assets, 883
F.3d at 1382.
In sum, plaintiff’s arguments concerning these statutes are too
tangential to the lease procurement. As the Federal Circuit instructs, “[i]f
plaintiffs could allege any statutory or regulatory violation tangentially
related to a government procurement, § 1491(b)(1) jurisdiction risks
expanding far beyond the procurement context.” Id. at 1381. If these statutes
were to be interpreted as “procurement statute[s], every appropriations bill
and rider would become a potential source of challenge for any interested
party under 28 U.S.C. § 1491(b)(1).” Id. at 1382. Accordingly, we grant the
government’s motion to dismiss plaintiff’s statutory claims for lack of
jurisdiction.
7
B. Motion to dismiss on waiver grounds
PBV alleges that SASD would be incapable, as required by the
solicitation, to complete the construction of the facility within 24 months,
and that the VA knew this before executing the lease. By nonetheless
awarding the contract to SASD, PBV alleges that the agency must have
amended the solicitation to allow SASD to complete the clinic in more than
24 months. Defendant also moves to dismiss this claim on waiver grounds
pursuant to the Rule 12(b)(6) of the Rules of the United States Court of
Federal Claims (“RCFC”).
We agree with defendant. In support of its claim, PBV admits that,
prior to submitting its offer, it knew, not only that it could not complete the
project within 24 months, but also “that no one could deliver a newly
constructed clinic within 24 months.” Pl. Mot. at 17. PBV states that its
principals were “active investors and operators in Bakersfield over 15 years,”
and that PBV had a “long, deep and highly relevant construction experience
in Bakersfield.” Id. at 16-17. The government disagrees that SASD’s
proposal reflected an inability to complete on time, but it argues that PBV
has in any event waived its objection to the solicitation’s 24-month delivery
provision. If PBV was aware of the problem, it should have raised it before
submitting its own offers to complete the clinic within 24 months.
We agree. Plaintiff cannot reserve an issue with a solicitation
requirement until after its offers have been rejected. It had a duty to protest
the asserted flaw in the solicitation before submitting its own offers. In short,
PBV has waived its argument concerning SASD’s asserted inability to
complete the project within the 24-month period. See Blue & Gold Fleet,
L.P. v. United States, 492 F.3d 1308, 1313 (Fed. Cir. 2007). We grant the
government’s motion to dismiss plaintiff’s claim regarding the 24-month
alternative on waiver grounds.
C. Motion to dismiss for lack of standing
Defendant and intervenor also move to dismiss all of plaintiff’s
complaint pursuant RCFC 12(b)(1) for lack of standing. They argue that
plaintiff lacks standing because it cannot show that the VA would likely
award the lease to PBV given that the court has accepted the agency’s
conclusion that PBV’s offers were outside the competitive range. Because
plaintiff’s ratings were too poor or marginal, and in ways that were not
readily correctable, defendant argues that plaintiff fails to show that removal
of the errors would have presented plaintiff with a substantial chance for
8
award or inclusion within the competitive range.
In its response, plaintiff asserts that it was prejudiced by being
evaluated under different requirements than those applied to SASD. There
is a substantial chance, it argues, that the VA would have made the award to
plaintiff if it could have competed on the same terms as SASD; that if the
agency’s actual requirements had been reflected in the solicitation, PBV
would have made material changes to its proposal and would have had a
substantial chance of being selected for award. If plaintiff is correct that
there were material changes to the solicitation after it was excluded, without
which SASD would have been excluded or the agency would have been
forced to resolicit, it is true that plaintiff might have standing. On those
assumptions, the agency would not be in a position to award to SASD and
there were no other offers ahead of PBV for the award. This possibility
means that we cannot reject the balance of plaintiff’s claims for lack of
standing. We therefore must decide the merits of the remaining claims and
thus deny the motions to dismiss on standing grounds.
II. The Remaining Merits
PBV has remaining three primary challenges to the VA’s award to
SASD: (1) that the VA waived the solicitation’s requirement that the offeror
show control over the property on which it intended to build a facility; (2)
that the VA unlawfully amended the solicitation by awarding a lease to
SASD even though SASD’s proposal did not score as an operating lease; and
(3) that the VA reduced the importance of price by awarding SASD’s
proposal at a [ ] price premium in comparison to PBV’s lowest-priced
offer. We find that all three of plaintiff’s challenges lack merit.
A. The VA did not waive requirements related to the control of the
property
PBV argues that the VA waived the solicitation’s requirement that the
offeror show control over the property over which it intended to build a
facility by awarding a lease to SASD even though SASD’s proposal did not
provide the required evidence of site control. 3 PBV alleges that SASD only
3
The solicitation defined evidence of site control as including “the following
fully executed documents: an option to purchase, a purchase and sale
contract, a fee simple deed, an option to lease property for longer than the
duration of the lease term including all renewable options and the post-award
design and construction phase.” AR 162.
9
submitted evidence of a contingent right to purchase the property for a period
that expired on July 1, 2020, prior to lease award. 4 Plaintiff argues that,
although the provided information 5 may indicate that at some point SASD
and the owners of the two parcels comprising its proposed site had an
agreement to sell the property to SASD, that is insufficient under the
solicitation to demonstrate ownership or control of the site.
PBV also complains that SASD failed to provide evidence to the VA
regarding the right to subdivide of one of the parcels of land upon which part
of SASD’s facility was to be constructed. If SASD planned to subdivide one
of the parcels, plaintiff alleges, doing so would violate California law, 6 and
would have required a lot line adjustment from the City of Bakersfield, 7
which would delay the facility’s construction. Finally, plaintiff argues that
the VA waived a notary requirement because the documents SASD
submitted as evidence of site control are not notarized.
Plaintiff argues that these deficiencies prejudiced it because, if the VA
had properly enforced the requirements of solicitation § 1.11, it would have
been forced to reject SASD’s proposal, which would have increased the
likelihood of PBV’s being considered for and obtaining award. See
Crassociates, Inc. v. United States, 95 Fed. Cl. 357, 390 (2010) (holding “that
the combined impact of the [Agency procurement] errors encountered . . .
clearly prejudiced plaintiff, since “[t]he correction of these errors
4
“Closing of Escrow shall occur Sixty (60) days after Bakersfield VA Clinic
award referenced as solicitation No. VA No. 38C10F19R0067 is awarded,
but in no event later than January 15, 2021.” AR 11850. Accordingly, the
face of the documents provided indicate that the property would have fallen
out of escrow prior to the time of award on April 23, 2021.
5
SASD further provided a preliminary report in response to an application
for a title insurance policy showing that “title to said estate or interest at the
date hereof is vested in” owners other than SASD. AR 11854.
6
California’s Subdivision Map Act generally prohibits the sale of any parcel
of real property for which a map is required, unless a map compliant with its
provisions has been filed. California Government Code Sec. 66499.30.
7
SASD’s proposal indicates that it intended to request a lot line adjustment.
But plaintiff asserts that a lot line adjustment requires approval from the City
of Bakersfield.
10
undoubtedly could lead to significant fluctuations in both technical ratings
and price, paving the way for plaintiff to receive an award of the contract”).
We agree, however, with defendant and intervenor that SASD
provided sufficient information to support the VA’s determination that
SASD had control of the site. Solicitation provision § 1.11 requires that
offerors show proof of ownership and chain of title through a current title
report. The solicitation did not require actual ownership, but rather “the right
to ownership or control of the site during the term of the lease.” AR 162.
The evidence of the right to control includes an option to purchase. Here,
SASD provided VA with documentary evidence showing that SASD had
entered into an option agreement to purchase the property upon which the
clinic is to be constructed. 8 Contrary to PBV’s assertions, the option to
purchase agreement did not expire but had been extended to July 15, 2021,
well past the April 26, 2021 lease execution date. That argument thus fails.
Regarding the issue of the application of city and state law to SASD’s
proposed use of the site, the solicitation did not require this level of detail in
setting forth and demonstrating site control. Plaintiff has not established that
the VA was under either a duty to enforce these requirements nor that it
promised to do so in the solicitation.
During oral argument, defendant conceded that the documents SASD
submitted as evidence of site control were not notarized, however, we agree
with the government that this error is de minimis and correctible and does not
justify overturning the lease award. See Grumman Data Sys. Corp. v. Dalton,
88 F.3d 990, 1000 (Fed. Cir. 1996) (de minimis errors in the procurement
process do not justify relief) (citing Andersen Consulting v. United States,
959 F.2d 929, 932-33, 935 (Fed. Cir. 1992)). Plaintiff has not presented a
basis for overturning the award.
B. The VA did not waive the solicitation’s requirement that the lease
score as an operating lease
The solicitation states that the agency will award a lease “only if the
Lease will score as an operating lease under Office of Management and
Budget Circular A11, Appendix B.” AR 163. As explained earlier, this
means that the present value of the lease payments cannot exceed 90% of the
8
The agreement contains the title-related documents connected with the
property. In addition, SASD provided a title report with its related documents
to VA.
11
fair market value of the facility. PBV contends that the VA unlawfully
amended the solicitation by making the award to SASD when it neglected to
properly take into account the upfront payment that SASD would receive in
year one. It points to the following language of the Circular:
If the terms of a lease contain an upfront, lump sum payment,
only the amounts associated with special features or
enhancements to meet the Government’s unique needs or
specifications and the amounts associated with agency specific
customizations can be removed from the agency scoring
calculation. Any payment in excess of that amount will be
factored into the net present value scoring calculation.
Pl.’s Compl. at 11 (quoting OMB Circular No. A–11 (2016), Appendix B at
7). Plaintiff argues that the VA failed to perform the required analysis of the
proposed upfront payment to ensure that it only contained items
contemplated by the OMB Circular. 9 If the agency had applied these costs
to the rental value, according to PBV, it is possible that SASD’s lease would
not score as an operating lease.
Plaintiff also asserts that the VA permitted SASD to use its lump sum
amount to mitigate the risks that it will not get the necessary approvals to
proceed with the project. To support this assertion, PBV points to an email
between SASD and the VA, in which the VA “agreed that the lump sum
amount for Sustainable Design is available to SASD in the event the project
does not move forward as a result of this challenge by the incumbent Lessor
in Bakersfield, PBV and or due to issues outside of SASD’s control.” AR
18276. Plaintiff argues that this email shows that the VA permitted SASD
to use part of the lump sum earmarked for “Sustainable Design” to mitigate
the risks that SASD will not get the necessary approvals to proceed with the
project. PBV argues that if SASD’s lease had been properly scored, the
award could not go forward and there is a substantial chance that the agency
would have reopened the competitive range or otherwise made an award to
PBV.
9
As support, plaintiff states that although the solicitation identified costs
associated with “Sustainable Design and Energy Efficiency” as a “specific
enhanced federal requirement cost” to be excluded from the rental rate, it
appears that the agency conflates sustainable design costs with all design
costs. AR 417. We have no basis, however, for overturning the agency’s
conclusion that the lump sum amount only included funds earmarked for
“Sustainable Design.”
12
In its response, the government asserts that the VA’s exchange with
SASD does not show that the agency improperly mitigated risks, rather it
acknowledges the unrelated and innocuous obligation to pay SASD for its
work if the lease were prematurely terminated due to a protest. For the first
11 months of the lease SASD was to design the facility so that it complied
with the sustainability and energy efficiency directives. The CO was
hypothesizing in her emails that if SASD were to be terminated as a
contracting partner during this time, SASD would be owed the cost of its
performance up to the point of that termination.
More basically, PBV does not identify any specific costs that should
not have been included in the lump sum. It has not, therefore, shown any
prejudice from this asserted agency action. It merely suggests that the VA
should have been more skeptical of the sorts of items included in the upfront
lump sum amount and speculates that “there is a substantial chance it would
have removed impermissible costs from the lump sum and included them in
SASD’s rent.” Pl. Mot. at 14. Agencies, however, “are entrusted with a good
deal of discretion in determining which bid is the most advantageous to the
Government.” Tidewater Management Servs., Inc. v. United States, 573 F.2d
65, 73 (Ct. Cl. 1978). In the absence of any clear basis for second-guessing
the agency’s acceptance of the elements of the lump sum payment, we have
no basis for sustaining this claim.
C. The VA did not reduce the importance of price in the evaluation and
award decision
PBV asserts that the agency ignored those terms of the solicitation
which provide that technical evaluation factors are considered equal to price
in determining which offeror poses the best value. 10 It points to the fact that,
between the time SASD submitted its initial offer and the time of award,
SASD increased its rental rate by more than [ ] and that the VA eventually
accepted a price from SASD’s which was [ ] price higher than PBV’s
lowest-priced offer. PBV argues that the agency therefore disregarded price
in its award decision, and that, if SASD’s proposal, as repriced, had been
compared to PBV’s offers, the agency should have made the award to
plaintiff. See Amazon Web Servs. v. United States, 147 Fed. Cl. 146, 154
(2020) (to establish prejudice, a protester is not required to show that but for
the alleged error, the protester would have been awarded the contract, but
AR ¶ 2.2 at 171 (“The technical evaluation factors other than cost or price,
10
when combined, are approximately equal to price”).
13
“plaintiff must, at a minimum, show that had the alleged errors been cured, .
. . its chances of securing the contract [would have] increased”).
Defendant and intervenor argue that record gives an unproblematic
explanation for SASD’s price increase. We agree. After PBV was removed
from the competitive range, the VA and SASD participated in price
negotiations in response to Amendment Four, which led to increases in
SASD’s price, a process common in competitive procurements. FAR
15.306(d) provides that “after the competitive range has been established, the
Government and offerors can undertake negotiations with the intent of
allowing the offeror to revise its proposal.” FAR 15.306(d). These
negotiations may include bargaining as to “price, schedule, technical
requirements, type of contract, or other terms of a proposed contract.” Id.
The price negotiations by themselves do not indicate that the agency
amended the evaluation criteria to discount the price factor.
More importantly, the [ ] increase in price is attributable to at
least two phenomena which would have impacted any bidder, namely, the
increase in costs due to COVID, and increased labor wage rates. This
procurement has been delayed almost five years. Plaintiff cannot rely on cost
increases triggered by delay which would have equally affected its costs. See
Golden Mfg., 107 Fed. Cl. at 276-277 (denying protest where the
modification affected all offerors equally and concluding that the change
would not change the relative competitiveness of the proposals evaluated);
Cardinal Maint. Serv., Inc. v. United States, 63 Fed. Cl. 98, 109 (2004)
(nature of the work changed substantially and nearly doubled the price of the
contract). 11
CONCLUSION
Plaintiff has not established that the VA waived solicitation
requirements by awarding the lease to SASD. Plaintiff’s argument regarding
the solicitation’s 24-month requirement came too late. With respect to
plaintiff’s statutory arguments, we find that we do not have jurisdiction to
hear arguments concerning appropriation statutes. The issues of price and
lease scoring are equally unavailing for the plaintiff. Not having shown
success on the merits, we need not consider the other injunctive factors. No
relief is warranted. Accordingly, plaintiff’s motion for judgment on the
11
We have considered PBV’s other arguments and find them unpersuasive.
14
administrative record is denied. Defendant’s motion to dismiss is granted in
part, as explained above. Defendant’s and intervenor’s motions for judgment
are granted. Accordingly, the Clerk of Court is directed to enter judgment
for defendant. No costs.
s/Eric G. Bruggink
ERIC G. BRUGGINK
Senior Judge
15