In The
Court of Appeals
Ninth District of Texas at Beaumont
________________
NO. 09-21-00072-CV
________________
EDWARD VAN HUIS IV, Appellant
V.
MARINE VENTURES, LTD, Appellee
________________________________________________________________________
On Appeal from the 60th District Court
Jefferson County, Texas
Trial Cause No. B-207,016
________________________________________________________________________
MEMORANDUM OPINION
Edward Van Huis IV filed an interlocutory appeal of a temporary injunction
that favors the party that sought the injunction, Marine Ventures, Ltd. 1 See Tex. Civ.
Prac. & Rem. Code Ann. § 51.014(a)(4) (permitting interlocutory appeal of
temporary injunction). In three issues, Van Huis challenges the scope of the
1
“A temporary injunction’s purpose is to preserve the status quo of the
litigation’s subject matter pending a trial on the merits.” Butnaru v. Ford Motor Co.,
84 S.W.3d 198, 204 (Tex. 2002) (citations omitted).
1
injunction, which temporarily enjoined him from distributing the proceeds related to
the sale of other family-owned companies. He also argues the evidence is
insufficient to support the trial court’s order granting the temporary injunction.
Finally, Van Huis complains the bond the trial court set is inadequate to protect him
against the damages he argues the trial court's order has caused. For the reasons
explained below, we affirm.
I. Background
In January 2021, Marine Ventures filed an Original Petition and Application
for Temporary Restraining Order and Hearing on Temporary Injunction against
Tubal-Cain Marine Services, Inc., Tubal-Cain Holdings, LLC, Edward J. Van Huis
III, Deborah Van Huis, Edward Van Huis IV, Jonathan Van Huis, and Timothy Van
Huis in their individual capacities.2 In February 2007, Tubal-Cain Marine Services
entered into a ten-year commercial lease agreement with Marine Ventures to operate
a dry dock/shipyard to repair and construct seafaring vessels. However, Marine
Ventures alleged that contrary to the express terms of the lease excluding such
activities, Tubal-Cain Marine Services engaged in barge fleeting and barge cleaning
activities. Tubal-Cain Marine Services abandoned the property in late 2016, before
2
Defendants Tubal-Cain Marine Services, Inc., Tubal-Cain Holdings, LLC,
Edward J. Van Huis III, Deborah Van Huis, Jonathan Van Huis, and Timothy Van
Huis entered into an Agreed Order on Plaintiff’s Application for Temporary
Injunction and are not a part of this appeal.
2
the conclusion of its lease with Marine Ventures. According to Marine Ventures,
while conducting its operations and on the lease, Tubal-Cain Marine Services caused
environmental damages to the property that it had leased from Marine Ventures.
Marine Ventures further alleged that Tubal-Cain was responsible for failing to
properly clean and remove the hazardous materials in accord with the terms of its
lease and environmental laws and regulations, subjecting Marine Ventures to
damages and cleanup costs through a program administered through the Texas
Commission on Environmental Quality (TCEQ). And Marine Ventures claimed that
Tubal-Cain not only failed to remedy the environmental hazard related to its release
of waste materials on the property it leased from Marine Ventures, it also refused to
indemnify, defend, and hold Marine Venture harmless from the damages it caused
Marine Ventures to incur based on Tubal-Cain’s misuse of the Leased Property.
Marine Ventures asserted claims for breach of contract and for environmental
damages.
After its lease expired the TCEQ notified Tubal-Cain in July 2017 that Tubal-
Cain had to remove all waste from the waste management unit it created on the
Leased Property and demonstrate to the TCEQ that a release had not occurred from
the unit. TCEQ notified Tubal-Cain that the obligation Tubal-Cain had incurred was
one that continued to “ensure that municipal hazardous waste and industrial solid
waste are managed in a manner which does not cause the discharge or imminent
3
threat of discharge of waste into or adjacent to waters in the state[.]” In July 2018,
TCEQ informed Tubal-Cain that testing showed the soil and groundwater were
contaminated and additional action was necessary to remove the hazardous material
and remediate the property. TCEQ also notified Tubal-Cain that its failure to comply
would constitute a violation of the United States Environmental Protection Agency
Consent Agreement, an agreement issued after the EPA visited the Leased Property
in October 2014 and fined Tubal-Cain after conducting an investigation into the
waste management practices that relate to its use of the Leased Property.
In 2019, Tubal-Cain Marine Services, Inc. sold “all and/or virtually all” of
Tubal-Cain Marine Services’ assets to VLS Recovery Services, LLC through an
asset purchase agreement. All payments from VLS for the purchase of Tubal Cain-
Marine Services, Inc. were paid to the “the parent and sole shareholder” of Tubal-
Cain Marine Services, Inc., Tubal-Cain Holdings, LLC. Other than the payment of
certain disclosed debts, Tubal-Cain Marine Services, Inc. did not receive any funds
from the sale of “all and/or virtually all” of its assets to VLS Recovery Services,
LLC. Marine Ventures alleges that this resulted in a “asset-free shell corporation
from which [creditors were forced] to collect.” The purchase agreement placed a
certain amount of the purchase price into an escrow account and a portion of the
escrow money was distributed to Tubal-Cain Holdings in July 2020. Tubal-Cain
Holdings, LLC immediately distributed funds it received from the sale of the assets
4
of Tubal-Cain Marine Services to its five members. Van Huis owns more than 43%
interest in Tubal-Cain Holdings. According to Marine Ventures, the remaining
amount is “the only known money and/or asset available to Tubal-Cain Marine
Services, Inc. from the sale of its assets to VLS Recovery Services, LLC to satisfy
the claims of its creditors, including the Plaintiff.”
In the underlying lawsuit, Marine Ventures further pleaded violations of the
Texas Uniform Fraudulent Transfer Act (TUFTA) and Texas Business
Organizations Code under sections 21.301 and civil conspiracy. Marine Ventures
asked the trial court to issue a temporary injunction enjoining the defendants from
“transferring, dissipating, or otherwise disposing of any proceeds received from the
sale of Tubal-Cain [Marine Services] until Plaintiff receives payment for the
damages it incurred as a result of…breaches of the Commercial Lease Contract with
Plaintiff.” In response, Van Huis filed an answer and special exceptions to Marine
Venture’s application. A hearing on Marine Ventures’ application for temporary
injunction was held in March 2021.
A. Testimony of Edward Van Huis IV
Van Huis testified that he was the president of Tubal-Cain Marine Services,
Inc. Beginning in February 2007, Tubal-Cain Marine Services leased a 9-acre lot on
the Sabine-Neches Canal in Jefferson County for a “a shipyard and/or dry dock
facility to repair and construct seafaring vessels.” Van Huis explained that in his
5
position as president of Tubal-Cain Marine Services, he was the “top person” in
charge, but that he had managers in place to cover different areas of the business and
ultimately, he had authority over his managers. Tubal-Cain Marine Services
abandoned the property in late 2016, which was before its lease with Marine
Ventures expired.
Van Huis also testified that he was the president of Tubal-Cain Holdings,
LLC, which was formed in 2012 or 2013. In July 2019, VLS bought Tubal-Cain
Marine Services, Inc. and “Five QSubs” for 48 million dollars. As part of the asset
purchase agreement, VLS agreed to place 10% of the purchase price into an escrow
account. The escrow account was created to hold money and charge off expenses
that were incurred by Tubal-Cain. According to Van Huis, the liabilities included
any potential liabilities that he disclosed to VLS before Tubal- Cain Marine, in 2019,
sold virtually all its assets to VLS in the asset purchase agreement. The amount
escrowed resulted in approximately $4.5 million, which was distributed in two
escrowed accounts. In July 2020, $3.8 million of the amount in escrow was released
to Tubal-Cain Holdings. The remaining balance, still in escrow, was scheduled to be
released in July 2021. Van Huis explained that before any money from VLS was
paid to Tubal-Cain Holdings, debts of $30 million had to be paid. After VLS paid
the $30 million of debt, there was approximately $18 million remaining from the
sale of the assets. Van Huis confirmed VLS purchased all the assets of Tubal-Cain
6
Marine Services, Inc., but Tubal-Cain Marine Services did not receive any money
from the sale. Instead, the funds VLS used to purchase all the Tubal-Cain family-
owned businesses were paid directly to various creditors and to Tubal-Cain
Holdings.3 Van Huis received 43.57% of the 18 million dollars, as “my ownership
percentage.”4 This percentage was “[a]pproximately $8 million.” Van Huis
confirmed that after “expenditures and taxes,” at the time of the temporary injunction
hearing, he still had about $4 million from the sale proceeds. According to Van Huis,
when Tubal-Cain Marine Services was sold to VLS, he acted in his “corporate
company capacity[.]” He testified that he acted in good faith in this capacity and
disclosed everything he knew during the sale of the corporate assets.
Van Huis explained that in the negotiations that resulted in purchase of Tubal-
Cain assets by VLS, he disclosed “several” liabilities of Tubal-Cain to VLS, but he
did not include Marine Ventures in that disclosure because “it was not an issue at
that time.” For that reason, issues involving Tubal-Cain Marine Services
environmental liabilities were not disclosed. According to Van Huis, details
regarding inquiries from the TCEQ about Tubal-Cain were not disclosed because he
3
In his Reply Brief, Van Huis represented that he testified that money from
the sale of the multiple companies’ assets, including but not limited to the assets of
Tubal-Cain Marine Services, Inc., paid off the debt at the family property known as
Old Yacht Club Properties.
4
Testimony demonstrated that the five people, including Van Huis, who
received interests in the proceeds from the purchase of Tubal-Cain Marine Services,
Inc., were the five people who were members of Tubal-Cain Holdings, LLC.
7
“did not receive any.” Van Huis testified that he has environmental managers who
take care of TCEQ inquiries, noting that the two employees who were responsible
for fielding inquiries from the TCEQ both now work for VLS. Van Huis explained
that currently, his father is assigned the responsibility on behalf of Tubal-Cain
Holdings to handle any claims for damages to the property leased from Marine
Ventures and pollution allegations with the TCEQ. Van Huis testified that when
Tubal-Cain Marine Services vacated Marine Venture’s property in 2016, he was not
aware of any pollution issues. He further explained that he was not aware of Marine
Venture’s allegation regarding pollution until he was served with a lawsuit in 2021.
B. Testimony of Bryan Clevenger
Bryan Clevenger testified that he is employed by EnSafe and is an
environmental scientist and project manager for corrective-action-project sites.
Photos of the Leased Premises were presented, one taken in 2006, which was before
Tubal-Cain Marine Services leased the property, and one taken after Tubal-Cain
Marine Services leased the property in 2012. Clevenger explained that the first photo
shows “a large acreage of grass-covered and vegetated property.” The second photo,
taken in 2012, demonstrates “large areas of dark staining, which is waste blast media
or spent blast media[.]” Clevenger stated that this dark staining appeared by Tubal-
Cain Marine Services’ “Waste Management Unit No. 1.” He explained the
significance of the waste management units created by Tubal-Cain Marine Services.
8
When you register as a generator of industrial and hazardous waste in
the State of Texas, you are required to register them in various waste
management units, which is the area in which that waste is handled.
Tubal-Cain Marine Services registered four waste management units
during the time in which they were operating. Waste Management Unit
No. 1 specifically was where they managed their waste blast media
from sandblasting barges and marine vessels.
…
Waste Management Unit No. 2 was a drum storage area. It was near the
northeast corner of where this metal building was. Waste Management
Unit No. 3 was a building that they stored paint-related waste in. Waste
Management Unit No. 4 was on a portion of the property over here
(indicating). That was a berm drum storage area. All of these waste
management units were within the larger footprint of Waste
Management Unit No. 1.
In 2016, Clevenger was hired to do a site walk while Tubal-Cain Marine
Services was still on the property. He stated that during this walkthrough, he
observed Tubal-Cain Marine Services operations, which included areas where they
were sandblasting barges, areas in which they had drums, paint, paint-related waste,
and a general overview of their property and operations. He stated that in April 2017,
Tubal-Cain Marine Services sent the TCEQ a “waste management unit closer
report[.]” He explained that this letter told the TCEQ that Tubal-Cain Marine
Services had removed waste at the site and was requesting closure for that waste
management unit. The TCEQ responded with a letter in July 2017, asking Tubal-
Cain Marine Services to “remove all waste from the waste management unit and
demonstrate that a release from the waste management unit to the environment had
9
not occurred.” Tubal-Cain Marine Services replied and reiterated that all their waste
had been removed and, based on their additional testing, waste and contaminant
levels were not an issue. Clevenger explained that although Tubal-Cain Marine
Services indicated that it had removed all waste blast media from Waste
Management Unit No. 1, the TCEQ responded that it appeared there were two large
piles that could be interpreted as spent blast media located near the unit. The TCEQ
stated that Tubal-Cain Marine Services did not provide sufficient information to
support closing the unit. The letters and subsequent responses from Tubal-Cain
Marine Services were admitted at the hearing. According to Clevenger, in response
to correspondence from TCEQ, Tubal-Cain Marine Services conducted soil and
groundwater sampling and the results showed levels impacted with metals above
“Tier 1 residential protective concentration levels.” Clevenger summarized the
TCEQ’s response as follows,
So, this letter, what that’s saying is that this site, based on the data that
was provided to the State and based on the analytical data, is impacted
with contamination above the TCEQ’s protective concentration levels,
which are the regulatory levels that require action. This -- in addition to
their 2017 letter saying that there was still waste from their waste
management units, this said -- this has confirmed that there was an
environmental release to the property from their waste management
units.
Clevenger testified further about subsequent letters TCEQ sent to Tubal-Cain
Marine Services stating Tubal-Cain Marine was noncompliant with requirements,
imposed by statute, that related to closing its waste management units. Clevenger
10
pointed to a report prepared by the EPA, which was admitted without objection. In
2014, the EPA visited Tubal-Cain Marine Services and inspected the Leased
Property. During the visit, the EPA met with Randy Cooper and Tubal-Cain Marine
Services facilities consultant, Ron Reeves. Clevenger explained that as early 2014,
the EPA noted that Tubal-Cain Marine Services was using “Black Beauty sandblast
materials used as blast media” and subsequently “disposing” of this blast media as
“‘fill’ when it is spent.” Clevenger explained the significance of this procedure
utilized by Tubal-Cain Marine Services.
[T]his EPA site investigation was done in 2014. My understanding is
that in 2017 the EPA issued fines in a document called the “Consent
Agreement and Final Order” to Tubal-Cain Marine Services for
compliance violations. The purpose of that EPA inspection was not
necessarily to tell them at the time to clean up any of their waste or do
anything like that, but it is very important to document in here that as
early as 2014 an EPA inspector notes that they were disposing it by
disposing of spent blast -- Black Beauty sandblast materials used as
blast media by placing it on the property as “fill” when it is spent.
…
It means that you’re filling either low-lying areas or you’re putting it
on the property and using it to level out areas. It’s fill material. They’re
using an industrial waste, a solid waste, as a fill. And you can call it
“burying” it as well.
Clevenger then explained that aerial photographs taken in March 2016, after
the EPA visit, showed barges being pulled onto land, sandblasted, and sandblast
materials disposed of in a fill on the land. He stated the photograph demonstrated
more dark areas on the property consisting of disposed blast media. Another
11
photograph showed “bulldozer scars” on the property “as though it had been grated
out or covered.” Clevenger then provided pictures from 2019, two years after Tubal-
Cain Marine Services vacated the property. He testified that the photos showed the
presence of waste blast media left by Tubal-Cain Marine Services. He stated that
Marine Ventures investigated this property as required by the TCEQ at their own
cost. Marine Ventures did this because Tubal-Cain Marine Services did not complete
the necessary “Affected Property Assessment.” Clevenger stated the following
about the removal he believed needed to be performed on the property:
So, this cost estimate is based on volumes of waste that were
determined and documented by this site investigation that was
completed. Our estimate is that there are 52,856 tons of waste blast
media and contaminated soil at this property. Based on the extent and
footprint of the impacts from Waste Management Unit No. 1 and Waste
Management Unit No. 2, 52,856 tons. Now, it’s important to note that
every single inch of this property has not been investigated, and the
EPA has pointed out that this -- that some of this material was disposed
as fill and maybe buried or -- excuse me. Some of this material may be
buried; it may be distributed across the property. Our site investigations
found -- were consistent with that. When we would sample soil and
install soil boring, we could see blast media extending down in some
cases between 2 and a half and 7 and a half feet to below the ground
surface.
So, based on the data that we have now, we have 52,856 tons that we’re
estimating of waste that would require remediation. There may be areas
that we have not identified and that would be identified during said
remediation. So, these costs -- this blue outline here (indicating) is for
the soil. It says: Removal of 52,856 tons. It includes mobilization,
excavation, stockpiling, loading, transport, disposal, and backfill of
those areas. It also includes oversight costs, project management costs,
work plans to complete the work. It includes laboratory analysis to
characterize the waste for disposal of the landfill. It includes the
12
confirmation sampling necessary to demonstrate to the TCEQ that the
waste has been removed. And that cost, based on the data that we have
now, would be $8,670,466. This item here allows a 15 percent
contingency for additional areas. Again, we have not examined every
square inch of this property; and we’ve identified areas where waste is
buried. It’s reasonable and it’s expected that we’re going to identify
more areas. So, there’s a contingency of 15 percent, which brings us to
$9,971,036. That is for the soil alone. And the soil has been more
extensively studied than anything else on this property, just given the
nature of the release, with it being the blast media that’s distributed
about across the -- that was disposed across the soil in direct contact
with the ground surface.
The green down below, if you’ll recall the photograph that showed
waste blast media in direct contact with the waterway -- part of our
investigation involved collecting samples from the waterway about 10
foot off the shoreline, and what we pulled back was waste blast media
that had run off from Tubal-Cain’s operations or had been directly
disposed from Tubal-Cain’s operations. It’s unclear whether it was
runoff or direct discharge. Regardless, the source of these impacts was
from Waste Management Unit No. 1. That blast media was consistent
analytically with what was found on-site as well. We’re estimating a
certain area out into this waterway.
It’s important to note here that the extent of the impacts in the waterway
from Tubal-Cain Marine Services is not defined. If you go back to the
TCEQ’s letter, their Screening-Level Ecological Risk Assessment has
not been completed. Their APAR was not approved; their Affected
Property Assessment Report was not approved by TCEQ. There has
been no ecological reporting by Tubal-Cain Marine Services, and
there's no definition on how far out their waste media has extended into
the waterway. So, we’re defining costs here for this item based on the
data that we know alone -- it may extend further than the data that we
know, if that – if that all makes sense to everyone. So, we’ve added a
contingency here.
Based on the data that we have now -- again, this is not -- this is not a
hypothetical; this is based on our findings so far -- it is 563,291. If this
-- if the locations we sample, if we continue to find that media out for
an area that’s twice as large or more, that cost would go up. We’ve
13
added a contingency here with a note that we -- effectively would cover
two times the area with contingency on those costs or for impacts to the
waterway. The total between those two, based on the data that we have,
the site investigation that’s been done, is $9,233,757. The total with that
contingency built in for what we would -- what we may expect to find
once we begin remediation or once Tubal-Cain completes their required
assessment, is $11,097,618.
Clevenger continued that Tubal-Cain Marine Services failed to submit
ecological studies to TCEQ, explaining that they were required to screen and provide
a Screening-Level Ecological Risk Assessment report. If TCEQ requests additional
investigation in the waterway by the property, “[i]t can drive regulatory cleanup
levels… warrant a lower, more conservative cleanup level[, and] … increase costs.”
During cross-examination, Clevenger agreed that waste blast contamination could
last for decades but clarified that although the property had been used as a shipyard
in the decade before Tubal-Cain Marine Services leased the property, “[t]here was
no blasting and painting operations -- blasting and painting were not conducted on
the land, based on the information that I’ve seen. Blasting and painting were
conducted on the offshore barge.”5 And Clevenger testified no one had registered
with the TCEQ to conduct blasting or painting operations on the property before
Tubal-Cain Marine Services. To be fair, Clevenger admitted that no one showed him
a “baseline evaluation” of the pollution studies for the property that showed its
environmental status before Tubal-Cain Marine Services’ lease began.
5
Clevenger later clarified this “offshore barge” was a docked barge.
14
C. Testimony of Christopher Bean
Christopher Bean testified that he is the vice-president and acting manager of
Marine Ventures. He testified that Marine Ventures leased the acreage to Tubal-Cain
Marine Services on February 1, 2007. The lease was admitted into evidence and
Edward Van Huis III’s signature is on the lease. According to Bean, he did not have
personal contact with Van Huis after 2008. He stated that Tubal-Cain Marine
Services breached the lease by, among other things, creating a nuisance with its
waste, performing barge cleaning operations that violated the acceptable standards
that applied to those operations, violating environmental laws and the Texas Water
Code by dredging and dumping spoil from its operations without having the
appropriate and required permits, disposing of spent and blast materials on the
premises as fill, and by failing to remove the contaminated material and remediate
the site or pay the damages caused by its operations on the lease.
According to Bean, Marine Ventures was required to hire EnSafe to assess the
nature and extent of the damages and contamination on the Leased Property. Bean
testified that Tubal-Cain Marine Services abandoned the property without notifying
Marine Ventures that it had been notified by the government that an environmental
or regulatory action would be instituted or had been threatened, failed to notify
Marine Ventures that it had created an environmental hazard by its operations, and
failed to notify Marine Ventures that it had violated the requirements that applied to
15
its operations under its lease. According to Bean, Marine Ventures has lost rental
income of “over a million dollars” since the termination of the lease due to the
contamination of the Leased Property, damages that do not include the damages to
fixtures, buildings, and environmental damage. Bean explained his assessment of
the damages includes three acres not originally included in the Leased Property’s
acreage but is property Tubal-Cain Marine Services used while it occupied the
Leased Property. Bean calculated that Tubal-Cain Marine Services owes “just under
$500,000[]” for the property they utilized that lies adjacent to the Leased Property,
property they were using but on which they were not paying rent. Bean stated that
in the decade before Marine Ventures leased the property to Tubal-Cain Marine
Services, the property was used in various ways, including fleeting of barges, and
some dry dock activity that included “[r]epair to marine equipment.” But any type
of blasting or painting was performed on an adjacent property owned by another
company.
When the hearing ended, the trial court granted Marine Ventures’ application
for a temporary injunction, finding that
Plaintiff has shown a probable injury because the harm is imminent; if
the temporary injunction does not issue, the funds payable to
Defendants from VLS Recovery will be released and distributed to
Defendants or others, and the injury would be irreparable; and the
applicant has no other adequate legal remedy.
Therefore, this temporary injunction is granted because Defendant,
Edward Van Huis, IV, has committed acts or is committing acts that
16
will deplete his assets and/or money available to satisfy an adverse
judgment and render that judgment in the litigation ineffectual and
leave Plaintiff with an irreparable injury and without an adequate legal
remedy. It is further
ORDERED that this temporary injunction be effective immediately and
the bond paid by Plaintiff in the amount of $500 payable to Defendant,
Tubal Cain Holdings, LLC, will extend to this temporary injunction.
As part of the Temporary Injunction, the trial court ordered
Defendant, Eddie Van Huis, IV, is ordered not to directly or indirectly
use, convey, assign, encumber, or disburse money or other rights, titles,
interests, assets or other proceeds that (1) are or were held in any escrow
account or part of any escrow agreement, whether or not previously
released, and paid directly or indirectly by VLS Recovery, Aurora
Capital Partners, and/or their respective affiliates to (or for the benefit
of) Defendant, Edward Van Huis, IV, or any of Defendant in
connection with VLS Recovery, Aurora Capital Partners, and/or their
respective affiliates’ acquisition, asset purchase, and/or merger with
Tubal-Cain Marine Services, Inc., Tubal-Cain Holdings, LLC and/or its
affiliates (the “Asset Purchase”) or (2) Defendant Edward Van Huis, IV
received in connection with the Asset Purchase. This order expressly
covers any funds that are or were part of an escrow account or part of
any escrow agreement arising out of the Asset Purchase that are
currently held or were held at Third Coast Bank in the name of or for
the benefit of Tubal-Cain Marine Services, Inc., Tubal-Cain Holdings,
LLC, or their affiliates, and any funds that are still held or retained by
VLS Recovery, Aurora Capital Partners and/or their respective
affiliates that have not been paid or released to Tubal-Cain Marine
Services, Inc. or Tubal-Cain Holdings, LLC or their affiliates.
Van Huis filed this interlocutory appeal.
II. Standard of Review
We review a trial court’s decision to grant a temporary injunction for an abuse
of discretion. Butnaru v. Ford Motor Co., 84 S.W.3d 198, 204 (Tex. 2002). We must
17
not substitute our judgment for the trial court’s judgment unless the trial court’s
judgment was so arbitrary that it exceeded the bounds of reasonable discretion. See
id. We review the evidence in the light most favorable to the trial court’s judgment
and draw all legitimate inferences from the evidence in a manner most favorable to
the trial court’s judgment. See Cameron Int’l Corp. v. Guillory, 445 S.W.3d 840,
845 (Tex. App.—Houston [1st Dist.] 2014, no pet.). We will not find an abuse of
discretion if the trial court heard conflicting evidence and evidence appears in the
record that reasonably supports the trial court’s decision. Dall. Anesthesiology
Assocs., P.A. v. Tex. Anesthesia Grp., P.A., 190 S.W.3d 891, 896 (Tex. App.—Dallas
2006, no pet.). The trial court abuses its discretion when it misapplies the law to the
“established facts, or when the evidence does not reasonably support the conclusion
that the applicant has a probable right of recovery.” State v. Sw. Bell Tel. Co., 526
S.W.2d 526, 528 (Tex. 1975) (citations omitted). Our review is limited to the validity
of the trial court’s temporary injunction order, and we will not consider the merits
of the underlying case. See Cameron, 445 S.W.3d at 845.
III. Analysis
A. Issue One
In his first issue, Van Huis argues that the trial court abused its discretion by
issuing a temporary injunction that is overly broad because it temporarily enjoins the
dissipation of proceeds and assets that he received from the sale of “multiple family
18
companies.” Specifically, he contends the injunction is overbroad because it attaches
to assets that he received from the “sale of corporate interests other than Tubal-Cain
Marine.”
“A temporary injunction is an extraordinary remedy and does not issue as a
matter of right.” Butnaru, 84 S.W.3d at 204 (citation omitted). To be entitled to a
temporary injunction, the applicant must plead and prove a cause of action against
the defendant, a probable right to the relief sought, and a probable, imminent, and
irreparable injury in the interim. Id. It is the applicant’s burden to produce some
evidence that establishes a probable right of recovery. Cameron, 445 S.W.3d at 845;
see also In re Tex. Nat. Res. Conservation Comm’n, 85 S.W.3d 201, 204 (Tex. 2002)
(quoting Camp v. Shannon, 348 S.W.2d 517, 519 (Tex. 1961)). However, the
applicant is not required to prove that it will ultimately prevail at trial, only that it is
entitled to preservation of the status quo pending trial on the merits. Cameron, 445
S.W.3d at 845.
In this interlocutory appeal of the temporary injunction, Van Huis sets out
three very narrow issues for the court to address. Van Huis does not dispute that the
trial court was within its discretion to grant temporary injunction based on the first
element, that the applicant must plead and prove a cause of action against the
defendant, regarding the specific causes of action pleaded by Marine Ventures for
breach of contract, fraudulent transfer of assets, civil conspiracy, violation of Texas
19
Business Organizations Code and environmental statutes. See generally Rocklon,
LLC v. Paris, No. 09-16-00070-CV, 2016 WL 6110911 (Tex. App.—Beaumont Oct.
20, 2016, no pet.) (mem. op.) (examining a temporary injunction, TUFTA cause of
actions, and alter ego); see also Butnaru, 84 S.W.3d at 204. Van Huis only asserts
that the temporary injunction is “overbroad to the extent that it freezes proceeds
derived from the sale of corporate entities and assets other than Tubal-Cain.” Van
Huis does not contend that there was no evidence that the Tubal-Cain Marine
Services sale was made with the intent of depriving Marine Ventures of the ability
to recover its losses or satisfy its judgment. See Rocklon, 2016 WL 6110911, at *3
(“The purpose of TUFTA is to prevent debtors from prejudicing creditors by
improperly moving assets beyond the creditors’ reach.”). Instead, Van Huis argues
that Marine Ventures offered no evidence segregating the proceeds of the sale of
Tubal-Cain Marine Services, Inc.’s assets from the proceeds of the sale of other
entities. Therefore, we assume without deciding that the trial court did not abuse its
discretion in determining that Marine Ventures’ causes of action are applicable, and
Marine Ventures provided sufficient evidence of its causes of action to support the
temporary injunction. See Butnaru, 84 S.W.3d at 204.
“Although a temporary injunction should be broad enough to safeguard a
party’s protectable interests pending a trial on the merits, it should not be so broad
that it prohibits the restrained party from engaging in lawful activities that are a
20
proper exercise of its rights.” Cooper Valves, LLC v. ValvTechonologies, Inc, 531
S.W.3d 254, 266 (Tex. App.—Houston [14th Dist.] 2017, no pet.) (citations
omitted). “[A] trial court was well within its discretion to weigh the evidence and
determine that [the plaintiff] satisfied the requirements for a temporary injunction[,]”
including determining that a plaintiff has a claim against the defendant, and
“[w]ithout the injunction, [the defendant] would spend the money.” Morrison v.
Colbert, No. 12-18-00206-CV, 2019 WL 968512, at *4 (Tex. App.—Tyler Feb. 28,
2019, no pet.) (mem. op.) (citations omitted). In this case, Marine Ventures pleaded
a cause of action under TUFTA against the Tubal-Cain Holdings, LLC, its subsidiary
companies and its members, alleging that the assets of Tubal-Cain Marine Services,
Inc. were wrongfully disposed of leaving the corporate entity without assets to
respond to any judgment that may be obtained in this lawsuit. See Tex. Bus. & Com.
Code Ann. §§ 24.001, 24.002, 24.003–24.013. The purpose of TUFTA is to prevent
debtors from prejudicing creditors by improperly moving assets beyond the
creditors’ reach. Tel. Equip. Network, Inc. v. TA/Westchase Place, Ltd., 80 S.W.3d
601, 607 (Tex. App.—Houston [1st Dist.] 2002, no pet.). TUFTA defines a “claim”
as “a right to payment or property, whether or not the right is reduced to judgment,
liquidated, unliquidated, fixed, contingent, matured, unmatured, disputed,
undisputed, legal, equitable, secured, or unsecured.” Tex. Bus. & Com. Code Ann.
§ 24.002(3). Subject to applicable principles of equity and in accordance with the
21
Texas Rules of Civil Procedure, section 24.008 of TUFTA specifically provides that
in an action for relief under the Act, a creditor may obtain “an injunction against
further disposition by the debtor or a transferee, or both, of the asset transferred or
of other property[.]” Id. § 24.008(a)(3)(A).
Here, testimony established that VLS purchased all assets of Tubal-Cain
Marine Services, Inc. and “five QSubs” 6 for 48 million dollars. This money was not
paid to Tubal-Cain Marine Services, Inc. but paid directly to its parent company,
Tubal-Cain Holdings, LLC and then distributed to the family owners, the Van Huis
family, the sole members of the holding company. The trial court heard testimony
that sale of the assets left Tubal-Cain Marine Services, Inc. insolvent.
The trial court also heard evidence that Marine Ventures could potentially
suffer several million dollars in damages as a result of Tubal-Cain Marine Services
environmental damage to the leased premises and surrounding area. The trial court
ordered enjoined-
…money or other rights, titles, interests, assets or other proceeds
that (1) are or were held in any escrow account or part of any escrow
agreement, whether or not previously released, and paid directly or
indirectly by VLS Recovery, Aurora Capital Partners, and/or their
respective affiliates to (or for the benefit of) Defendant, Edward Van
Huis, IV, or any of Defendant in connection with VLS Recovery,
Aurora Capital Partners, and/or their respective affiliates’ acquisition,
asset purchase, and/or merger with Tubal-Cain Marine Services, Inc.,
Tubal-Cain Holdings, LLC and/or its affiliates (the “Asset Purchase”)
Qualified Subchapter Subsidiary-A corporation as described in the Internal
6
Revenue Code, sec. 1361(b)(3)(B). I.R.C. § 1361(b)(3)(B).
22
or (2) Defendant Edward Van Huis, IV received in connection with the
Asset Purchase. This order expressly covers any funds that are or were
part of an escrow account or part of any escrow agreement arising out
of the Asset Purchase that are currently held or were held at Third Coast
Bank in the name of or for the benefit of Tubal-Cain Marine Services,
Inc., Tubal-Cain Holdings, LLC, or their affiliates, and any funds that
are still held or retained by VLS Recovery, Aurora Capital Partners
and/or their respective affiliates that have not been paid or released to
Tubal-Cain Marine Services, Inc. or Tubal-Cain Holdings, LLC or their
affiliates.
While Van Huis complains that the scope of the injunction enjoins proceeds
from the sale of other corporate assets not associated with Tubal-Cain Marine
Services, Inc., Van Huis offered no evidence to support his contention. The trial
court was only offered evidence that the sales proceeds were commingled as one
lump sum and were being transferred and disbursed, allegedly in violation of
TUFTA and other statutes. Van Huis presented no evidence of any breakdown of
assets of any other entity he contends was a part of the sale to VLS that are allegedly
wrongfully enjoined by the scope of the temporary injunction. See Hartwell v. Lone
Star, PCA, 528 S.W.3d 750, 759 (Tex. App.—Texarkana 2017, pet. dism’d) (In an
evidentiary challenge to a temporary injunction, “we view the evidence in the light
most favorable to the trial court’s order and indulge every reasonable inference in its
favor[,]” noting there must be some evidence that reasonably supports the trial
court’s decision). Having found evidence in the record to reasonably support the trial
court’s order, we overrule Van Huis’s first issue.
23
B. Issue Two
In his second issue, Van Huis argues that “[t]he injunction impermissibly
extends to sales proceeds in excess of the value of the lease premises.” Van Huis
argues that the Texas Supreme Court stated in Gilbert Wheeler, real property is
classified as either temporary or permanent, and that the difference effects the
measure of damages. See Gilbert Wheeler, Inc. v. Enbridge Pipelines (East Texas),
L.P., 449 S.W.3d 474, 478–79 (Tex. 2014). Van Huis contends under Gilbert
Wheeler “[i]f the injury is permanent, then the measure of damages is ‘the difference
between the value of the land immediately before the injury and its value
immediately after[,]’ [and] [i]f temporary, then the measure of damages is the cost
of repair.” Van Huis states that this standard applies to both breach of contract cases
and tort cases.
The trial court’s injunction contained the following language,
Marine Ventures, Ltd.’s Application for a Temporary Injunction,
presented to the Court today. The Court examined the pleadings of the
Plaintiff, the evidence presented, and the argument of counsel, and after
due consideration finds that:
1) a cause of action against the Defendant, Edward Van Huis, IV, exists;
2) Plaintiff has a probable right to the relief sought; and
3) Plaintiff will suffer a probable, imminent, and irreparable injury in
the interim.
Therefore, Plaintiff is entitled to a temporary injunction.
It is therefore ORDERED that the clerk of this Court issue an Order of
24
Temporary Injunction restraining Defendant, Edward Van Huis, IV,
and any other person(s) with knowledge of this Order, from engaging
in any conduct which delays, hinders or prevents payment from
Defendant, Edward Van Huis, IV, to (or collection by) Plaintiff, Marine
Ventures, Ltd., for alleged breaches of the Commercial Lease Contract
with Marine Ventures, Ltd., and/or for Defendant, Edward Van Huis,
IV's, alleged violation of the Texas Uniform Fraudulent Transfer Act
and/or the Texas Business Organizations Code.
Van Huis attacks the trial court’s injunction arguing that Marine Ventures did
not carry its burden demonstrating the value of the land and presented the Court with
an improper standard for an injunction amount as applicable under Gilbert Wheeler.
In Gilbert Wheeler, the Texas Supreme Court stated that the following regarding
temporary and permanent injury to real property.
We hold that application of the temporary-versus-permanent distinction
in cases involving injury to real property is not limited to causes of
action that sound in tort rather than contract. Of course, contracting
parties are free to specify in an agreement how damages will be
calculated in the event of a breach, but when they do not, both courts
and parties benefit from the application of general principles with
respect to calculating damages for such injury. In this case, we find
persuasive our prior holding that, with respect to right-of-way
agreements like the one at issue here, “the measure of damages for
breach of an easement that restricted a right to cut trees would be the
same as the measure for negligently cutting trees.” This stands to reason
because the injury in question under either cause of action is the same.
We see no reason to compensate a party differently because the
wrongful conduct that caused the identical injury stems from breaching
a contract rather than committing a tort. Further, the exceptions to the
general rules in this area, discussed below, operate to ensure
landowners are adequately compensated. Accordingly, we hold that the
temporary-versus-permanent distinction underlies the determination of
the proper measure of damages for both the trespass and breach-of-
contract claims at issue.
25
…
As noted above, the general rule in cases involving injury to real
property is that the proper measure of damages is the cost to restore or
replace, plus loss of use for temporary injury, and loss in fair market
value for permanent injury. However, we apply this rule with some
flexibility, considering the circumstances of each case to ensure that an
award of damages neither over– nor under-compensates a landowner
for damage to his property. We maintain that the purpose of the law “in
every case, is to compensate the owner for the injury received, and the
measure of damages which will accomplish this in a given case ought
to be adopted.” For that reason, Texas courts have appealed to a number
of exceptions to the general rule when it would compensate a landowner
unjustly. Two of those exceptions are at issue in this case.
Id. at 478–482 (citations omitted). The Gilbert Wheeler court limited its holding to
cases involving breach of contract and tort. See id. Marine Ventures has pleaded
causes of actions against Van Huis for breach of contract, but also for TUFTA
violations, and environmental damages under Texas Health and Safety Code Section
361.344. Van Huis does not contest the sufficiency of the evidence to support the
temporary injunction on any other cause of action other than breach of contract. As
such,
[i]f an independent ground fully supports the complained-of ruling or
judgment, but the appellant assigns no error to that independent ground,
we must accept the validity of that unchallenged independent ground,
and thus any error in the grounds challenged on appeal is harmless
because the unchallenged independent ground fully supports the
complained-of ruling or judgment.
Oliphant Fin. LLC v. Angiano, 295 S.W.3d 422, 424 (Tex. App.—Dallas 2009, no
pet.) (discussing unchallenged grounds in the context of dismissal). If an applicant
26
pleads and proves the essential elements to grant the temporary injunction for an
independent cause of action, any trial court error pertaining to other independent
causes of action is harmless given the pleaded and proven ground fully supports the
temporary injunction. Washington v. Associated Builders & Contrs. of S. Tex. Inc.,
621 S.W.3d 305, 311–12 (Tex. App.—San Antonio 2021, no pet.). Therefore,
because Van Huis does not challenge the Marine Ventures TUFTA or environmental
claims, and the trial court did not specify which ground upon which it granted the
temporary injunction, we must accept the validity of the unchallenged ground and
any error of the challenged ground on appeal is harmless. See Hartwell, 528 S.W.3d
at 763 (citing Oliphant, 295 S.W.3d at 424); see also Ahtna Support & Training
Servs., LLC v. Asset Protection & Security Servs., LP, No. 13-19-00196-CV, 2020
WL 1856470, at *4 n.8 (Tex. App.—Corpus Christi–Edinburg April 9, 2020, no pet.)
(mem. op.); In re Estate of Minton, No. 13-11-00062-CV, 2011 WL 2475394, at *4
(Tex. App.—Corpus Christi–Edinburg June 23, 2011, no pet.) (mem. op.). We
overrule Van Huis’s second issue.
C. Issue Three
In his final issue, Van Huis challenges the trial court’s decision to set the bond
amount for the temporary injunction at $500. Van Huis argues that the $500 is not
appropriate to freeze four million dollars in funds, the funds represent the bulk of his
personal assets, and should be set in a “far greater amount.”
27
“A trial court has considerable discretion in setting the amount of bond for a
temporary injunction.” Biodynamics, Inc. v. Guest, 817 S.W.2d 128, 131 (Tex.
App.—Houston [14th Dist.] 1991, writ dism’d by agr.) (citation omitted). “The
purpose of the bond is to protect the enjoined party from damages it may incur
resulting from an improperly granted injunction.” Hartwell, 528 S.W.3d at 770
(citations omitted). “The determination of the adequacy of the bond set by the trial
court is to be made on a case-by-case basis based upon the record before the
reviewing court.” IAC, Ltd. v. Bell Helicopter Textron, Inc., 160 S.W.3d 191, 203
(Tex. App.—Fort Worth 2005, no pet.) (citations omitted). The amount of bond is
soundly within the discretion of the trial court and we will not disturb the trial court’s
determination of a bond on appeal absent an abuse of discretion. Id.
While Van Huis testified that the injunction would basically tie up all his
money and affect his ability to support his family in the manner they were
accustomed, Van Huis offered the trial court no evidence at the hearing on the
temporary injunction of any potential damages he may suffer should it be determined
that these assets were wrongfully enjoined. See id. at 203 (explaining that evidence
regarding harm of bond amount must be “ascertained with a reasonable degree of
certainty and exactness[,]” and general testimony that the income about lost profits
needed to support the appellant’s family, was insufficient to prove lost profits); see
also Tex. Instruments, Inc. v. Teletron Energy Mgmt., Inc., 877 S.W.2d 276, 279
28
(Tex.1994). Testimony cannot be too general or conclusory about lost profits or
damages to show the trial court abused its discretion when setting a bond amount.
Hsin-Chi-Su v. Vantage Drilling Co., 474 S.W.3d 284, 304 (Tex. App.—Houston
[14th Dist.] 2015, pet. denied) (holding the trial court did not abuse its discretion in
setting a bond amount when the appellant did not “explain how he calculated this
amount or the nature of such potential loss”). The record does not demonstrate that
the trial court abused its discretion by setting a $500 dollar bond amount. We
overrule Van Huis’s last issue.
IV. Conclusion
Having overruled all Van Huis’s issues on appeal, we affirm the judgment of
the trial court.
AFFIRMED.
________________________________
CHARLES KREGER
Justice
Submitted on September 9, 2021
Opinion Delivered March 31, 2022
Before Golemon, C.J., Kreger and Horton, JJ.
29