This case has been considered previously by this court. Wentworth v. Manhattan Market Co. 216 Mass. 374. After the rescript of this court and in accordance therewith, the case was recommitted to the master, who assessed the damages to be awarded to the plaintiff. At the request of both parties the case was reserved by a judge of the Superior Court upon the master’s report upon the assessment of damages and the exceptions of both *95parties thereto, together with the record of the previous appeal; such decree to be entered as law and justice may require.
The defendant contends that it is liable only for nominal damages for failure to erect the building upon the premises because of the language contained in the previous opinion (216 Mass. 380): “The plaintiff has refused to allow the defendant to erect one [a building] such as the contract provided for.” The record shows that the plaintiff and the defendant were not in accord as to the size or character of the building that was to be erected. In other words, they differed as to the correct interpretation of the lease and contract which they had entered into. This court has decided that the defendant was correct in its interpretation of the agreement so far as it related to the dimensions and character of the proposed building. This does not, however, release or excuse the defendant from a failure to perform its contract, or, in the event of such failure, from respofiding in damages to the plaintiff. The language quoted from the opinion, that “the plaintiff has refused to allow the defendant to erect one such as the contract provided for, ” cannot be construed as meaning anything more than that the plaintiff refused to agree to the defendant’s interpretation of the contract. The defendant has been in full possession and control of the premises ever since June 1, 1910, and there is nothing to show that it might not have proceeded with the construction of such a building as was called for by the agreement, and have fully completed it on or before June 1, 1912. It would be inequitable for the defendant to be relieved from liability for failure to perform the contract which it admits it entered into. Especially is this true in view of the following finding of the master: “That the defendant, after it secured a renewal of its lease of the quarters now occupied by it, which was during the two year period, at no time considered the erection of any new structure upon the premises leased by the plaintiff until after a demand from the plaintiff in the spring of 1912 for the erection of the building called for in the lease and agreement. The defendant then took up the question of the new construction, but went only so far as to determine what was the simplest building that could be constructed to satisfy its obligation under its covenant, and except for that there was no plan at any time to erect any building upon the plaintiff’s land.”
We are of opinion that the plaintiff is entitled to damages (1) by *96reason of the failure of the defendant to erect the building, and (2) for failure to pay the rent stipulated in the lease. The plaintiff undoubtedly has a remedy at law for the recovery of whatever sums may be due him as rent under the lease, but as the bill is brought among other things to compel the specific performance of the contract, and as the court in the exercise of its discretion has determined that specific performance pught not to be ordered, but has determined that the proper relief to be awarded the plaintiff is that of damages, we see no reason why the rule in chancery practice in this Commonwealth should not be followed in this case and jurisdiction retained for the assessment of damages although the relief of specific performance has been refused. Newburyport Institution for Savings v. Puffer, 201 Mass. 41, 47. Nickerson v. Bridges, 216 Mass. 416, 421.
We are of opinion that the rulings and findings of the master under the paragraphs of his report numbered one and two are correct. The written agreement for the construction and finish of different parts of the building recites that the same is to be done “in a manner satisfactory to said Wentworth” and “in a manner to the reasonable satisfaction of the saidWentworth.” These different forms of expression are to be construed as having the same meaning. They are to be considered as agreements to do the work in such a way as reasonably ought to satisfy the plaintiff. Handy v. Bliss, 204 Mass. 513, 519, 520. It seems plain that the defendant was not required to put a roof on the brick building upon which was to have been placed the three story wooden building. Nor can we say that the findings of the master that the building should have a wooden floor, that the walls were not to be plastered, and the other findings, including the finding that such a building would cost $4,020.05, were plainly wrong. The finding as to the reasonable cost of the building is based upon the cost of such building before June 1, 1912, when, by the terms of the agreement, it was to have been completed, but as the defendant was entitled to the use and occupancy of the building, had it been erected, until June 1, 1920, the date when the lease, unless renewed, would expire, the plaintiff is entitled to recover as damages only a sum equal to the present worth of the building. That is to say, the fair cost of the building should be reduced to such a sum as with interest at six per cent per annum will produce the amount at the end of the term.
*97We are of opinion that in the absence of any evidence to the contrary, six per cent per annum, which is the legal rate of interest fixed by statute where there is no agreement for a different rate, would be reasonable interest in this case. R. L. c. 73, § 3.
It is to be observed that there is no evidence before the court as to the extent, if any, that the building would have depreciated in value at the time of the termination of the lease. No rent has been paid since June 1, 1912, and the question arises as to what sum should be paid from and after that date. The lease and agreement provided that the building to be erected upon the premises should be completed within two years from June 1,1910, and that from and after June 1, 1912, the increased rental at the rate of $2,500 should be in force. The evidence shows however that owing to differences between the parties as to the size, location and character of the building, no building has been erected, and the controversy between the parties as to the proper interpretation of the lease and agreement recently has been decided by the rescript filed in this case on January 9, 1914. The report of the master shows that the defendant seasonably before June 1, 1912, tendered performance by offering to erect such a building as the contract called for, but that the plaintiff refused to accept such a building.
Under these circumstatices, we are of opinion that the rent reserved at the rate of $700 a year from June 1,1910, until the date of the rescript, is due and payable, together with interest at six per .cent on each monthly instalment as it became due under the lease, and that from and (after the date of the rescript for the remainder of the term of the lease the plaintiff is entitled to receive the yearly rental of $2,500, payable in equal monthly payments in accordance with the lease, with interest at six per cent on each monthly instalment as it became due. It follows that the plaintiff’s exceptions to the master’s report must be overruled.
The defendant’s exceptions have been largely disposed of by what has been said. The master was justified in ruling that there had been a breach of the contract on the part of the defendant. This follows from the previous opinion in this case. The defendant’s first exception therefore must be overruled. As the plaintiff is entitled to recover substantial damages, the second exception is overruled. The third, fourth and tenth exceptions, for the *98reasons already stated, must be sustained. The eleventh and twelfth have become immaterial. The master’s finding that the defendant should lay a wooden floor and that there should be suitable finish about the doors and windows cannot be found to have been clearly wrong. Accordingly the fifth exception must be overruled. The eighth exception is overruled, as it does not appear what method the master adopted in making his finding as to the cost of the building, nor is the evidence before us upon which this finding was based. The letter of January 26, 1914, from the defendant’s counsel to the plaintiff’s counsel, would seem to have been immaterial upon the question of damages, which was the only issue before the master, but we fail to see how the defendant could have been harmed even if the letter was admitted wrongly; Accordingly this exception must be overruled.
The defendant’s sixth and seventh exceptions relate to the exclusion of the defendant’s offer to show that in the spring of 1912 it had a bona fide bid in writing from a responsible person to erect the building required for $3,007. The master found that the bid which the defendant offered in evidence was based upon a certain plan and specifications prepared by the defendant’s architect and contained certain errors and omissions.
We are of opinion that this evidence was incompetent. An unaccepted bid had no tendency to show the reasonable cost of the building in 1912. Accordingly the defendant’s sixth and seventh exceptions must be overruled. Peirson v. Boston Elevated Railway, 191 Mass. 223, 233. Doherty v. Hill, 144 Mass. 465, 469. Wood v. Firemen’s Fire Ins. Co. 126 Mass. 316, 319. Dickenson v. Fitchburg, 13 Gray, 546, 554.
A final decree in favor of the plaintiff in accordance with the foregoing, with costs, is to be entered; its form t'a be settled in the Superior Court.
Ordered accordingly.