The plaintiff seeks to recover the balance due on a building contract, and in addition the sum of $163 for changes* in the composition of mortar used. The plaintiff and defendant made a written contract for the construction of a library building for the sum of $17,255. The plaintiff has completed the contract. The matter in dispute is the sum of $1,050, that being the price of the heating and pipe installation, which work was done by the defendant. The specifications were made a part of the contract. They provide, "The Heating and ventilation will be done under separate contract by the Town, but the General Contractor must assist the Sub contractor by
The trial judge found for the plaintiff in the sum of $171.15, made up of the item for the mortar furnished, with interest. He found that the defendant was entitled to an allowance of $1,050 for the heating system, and found for the defendant on this item. In the Appellate Division judgment was ordered for the plaintiff in the sum of $1,213 damages and interest. The defendant appealed.
It appeared from the findings of the judge that the building committee of the town obtained its knowledge of the detailed schedule about one month after the work had begun, at the time the first payment was due; that the question of deducting the sum of $1,050 first arose at the time the last payment was made.
The provision in the contract that the plaintiff will furnish the architect with a detailed schedule of prices, the schedule to be the basis for all payments, coupled with the fact that the schedule was duly furnished by the contractor, and "that it did not include the item of $1,050 is not in our opinion sufficient to show that the sum of $1,050 should not be deducted from the contract. Whatever may have been the reason for the insertion of the requirement that a schedule of prices should be furnished, the schedule to be the basis for payments, it is not enough to overcome the terms of the contract providing that the allowance is to be made. If the plaintiff made an error in calculating the cost, the defendant could still insist upon compliance with the contract and the allowance of $1,050.
As we interpret the record, although the schedule was duly furnished by the contractor, the building committee of the town had no knowledge of its existence until after the work had begun and the first payment was due and payable. The fact that the schedule was to be the basis
The defendant has paid the plaintiff all that was due with the exception of the amount due for the mortar. There was no error by the trial judge in refusing the plaintiff’s requests for rulings.
The order of the Appellate Division directing that judgment should be entered for the plaintiff in the sum of $1,213 and interest is reversed, and the finding of the trial judge that judgment should be entered for the plaintiff in the sum of $163 is affirmed and judgment is to be entered for that amount with interest from the date of the writ.
So ordered.