The principal issue in this case is the effect of a conservation commission’s failure to issue its decision denying a requested order of conditions within the statutorily prescribed time period.2 The plaintiff Oyster Creek Preservation, Inc. (OCP),
We granted the commission’s application for further appellate review. We conclude that the commission’s denial, issued after the expiration of the twenty-one day period mandated by the act as well as the town bylaw, is without effect, and for this reason, the DEP’s superseding order of conditions controls. We affirm the judgment of the Superior Court in part.
1. Background. The pertinent facts are these. In response to OCP’s July 5,2003, notice of intent for the Oyster Creek dredging project, the commission held a public hearing, as it was required to do under the act and the town bylaw. See G. L. c. 131, § 40. The public hearing commenced at the commission’s meeting on July 15, 2003, and was continued to August 5, with the consent of OCP. On August 5 and then on August 19, the commission
Thereafter, on September 29, 2003, the commission received a letter from an attorney representing Henry E. and Mary Davidson, and Lawrence and Mary McKevitt, abutting property owners on the south side of Oyster Creek: the letter expressed concerns about the proposed project’s impact on the abutters’ land. At its next meeting held on September 30, the commission voted unanimously to reopen the public hearing on the Oyster Creek dredging project to accept the abutters’ letter in evidence. This vote was followed directly by another vote to close the hearing to further evidence, and the commission then voted unanimously to deny the dredging project and order of conditions.
OCR appealed to the DEP pursuant to the act for a superseding order of conditions on October 8, 2003, twenty-two days after the commission had first closed the public hearing. On October 9 or 10, 2003, the commission issued its written decision denying the requested order of conditions.3 In that decision, the commission divided its statement of reasons for denial into two parts. The first part considered the proposed project in relation to the act and set out specific findings that referenced and were based on particular regulations that the DEP promulgated under the act. In the second part, the commission purported to review the project under the town bylaw and its implementing regulations.4
Following the issuance of the commission’s denial, OCR and
2. Discussion. The act sets out a comprehensive scheme to govern activities, work, or projects that entail the removal, filling, dredging, or altering of wetlands and lands bordering waters. G. L. c. 131, § 40. The act requires any person who seeks to undertake such a project to file a notice of intent with the appropriate conservation commission or other official, with a copy
The commission contends that its decision complied with the statutory and town bylaw time requirements because the public hearing on the OCP dredging project did not close until September 30, 2003. The argument fails. The record shows that the commission voted to close the public hearing on September 16, 2003. While the town bylaw allows for the continuance of a public hearing in certain defined circumstances, none of those circumstances obtained in this case.8 Furthermore, there is no
The commission’s alternate argument is that even if September 16 is the operative beginning date, the commission issued its denial within the requisite twenty-one days because the date of issuance was October 7, exactly twenty-one days after September 16. The record is to the contrary. The commission’s decision expressly states in four separate places that the date of issuance is October 9, 2003, which is twenty-three days after September 16.9 Moreover, the applicable DEP wetlands protection regulations define the date that an order is issued as “the date an [o]rder is mailed, as evidenced by a postmark.” 310 Code Mass. Regs. § 10.04 (1997). The record here is clear that the commission’s decision carried a postmark dated October 10, 2003, twenty-four days after September 16.10
Given that the commission’s decision was not timely, what is the remedy? Here and in the Superior Court, the plaintiffs’ position — which the Superior Court judge incorporated into the judgment — is that the failure of the commission to meet the twenty-one day time requirement results in the constructive grant of OCP’s notice of intent. We disagree. The act contains no provision deeming a notice of intent granted if a decision on that notice of intent is not issued within twenty-one days.11
“if a [local conservation] commission, after holding such a hearing has failed within twenty-one days therefrom to issue an order . . . any person aggrieved by said commission’s . . . failure to act . . . may, . . . within ten days from said commission’s . . . failure to act, request the [DEP] to determine whether the area on which the proposed work is to be done is significant [to interests protected by the act] .... Upon receipt of such request the [DEP] shall make the determination requested and shall by written order . . . impose such conditions as will contribute to the protection of the interests described herein .... Such order shall supersede the prior order of the conservation commission . . . and all work shall be done in accordance therewith . . . .”
Id. The import of this provision is that where a conservation commission does not issue its decision within the required twenty-one day period and the applicant appeals to the DEP, it is the DEP’s superseding order that controls; any late-issued decision of the commission is without effect.
The failure of a conservation commission to issue a timely decision presents a different case than one in which the commission is timely with its decision but rests its determination on provisions of a local bylaw that are more protective than the act. In the latter case, a superseding order of conditions issued by the DEP cannot preempt the conservation commission’s bylaw-based determination. See, e.g., Rodgers v. Conservation Comm’n of
3. Conclusion. We affirm the judgment of the Superior Court to the extent it declares that the proposed dredging project is effectively governed by the DEP’s superseding order of conditions. The other two aspects of the Superior Court judgment
So ordered.
2.
We acknowledge receipt of the amicus brief of Henry E. and Mary Ann
3.
There is disagreement among the parties about the exact date the commission “issued” its decision. This question is discussed infra.
4.
This portion of the decision read as follows:
“DENIAL — Harwich Wetland Protection Regulations
“1.12 Procedures
“Section 2(a)(l)(3) — The applicant did not prove to the satisfaction of the Commission that the proposed work is not significant to the protection of the interests identified in 1.01 Purpose — Land Containing Shellfish. In addition, the applicant failed to show that the proposedPage 862project would not have an adverse impact of either an immediate or a cumulative nature upon the interests of the By-Law.
“1.16 Appendix (6)
“The plans do not meet the minimum requirements of the Conservation Commission.”
5.
In their respective decisions, the Superior Court judge and the Appeals Court only considered the count of the plaintiffs’ complaint that sought review in the nature of certiorari (count HI). The Superior Court judgment, however, also granted the plaintiffs a judgment declaring that the commission had constructively granted the plaintiffs’ notice of intent, and further adjudged the commission in violation of the open meeting law. Like the other two courts, we focus on the plaintiffs’ count brought pursuant to G. L. c. 249, § 4, but address briefly the other two counts of the complaint at the end of this opinion.
6.
Before these motions were heard, the DEP issued a superseding order of conditions on January 7, 2005, approving OCP’s proposed dredging project subject to certain conditions. On motion of the plaintiffs in the Superior Court, the DEP’s superseding order of conditions was added to the administrative record. The DEP’s order points out that the dredging project being approved would involve a substantial reduction in the volume of dredging to be done as compared to the proposal OCP originally had presented to the commission, and that OCP had eliminated entirely the proposed marsh construction and vinyl sheet toe waH. These last two aspects of the original project proposal were the primary points of concern expressed by the abutters in their letter sent to the commission on September 29, 2003.
7.
Section 5.4 of the town bylaw provides: “The [c]ommission shall issue its Determination or permit in writing within 21 days of the close of the public hearing or receipt of the File Number issued by the [DEP], whichever is later, unless an extension is authorized in writing by the applicant.” There is no contention made in this case that receipt of the DEP file number occurred after September 16, 2003.
8.
Section 5.6 of the town bylaw provides:
“Public hearings may be continued as follows:
“1. without the consent of the applicant to a date, announced at the hearing, which continued date shall be within 21 days of receipt of the Notice of Intent.
“2. with the consent of the applicant, to an agreed-upon date, which shall be announced at the hearing; or
“3. with the consent of the applicant for a period not to exceed 21 days after the submission of a specified piece of information or the occurrence of a specified action. The date, time and place of said continued hearing shall be publicized in accordance with [G. L. c. 131, § 40], and notice shall be sent to any person at the hearing who so requests in writing.”
There is no evidence that OCP, as the applicant, consented to a continuance of the public hearing beyond September 16, either generally or to accommodate the submission of some identified piece of information or the occurrence of an identified action. Indeed, the commission contends that the hear
9.
The significance of October 7 is that it appears to be the date the commission’s chairman signed the decision and had his signature notarized.
10.
The commission argues that while the town bylaw requires the issuance of a written decision within twenty-one days after a public hearing has closed, the bylaw does not require that the applicant be notified of the decision or that it be mailed within twenty-one days. The point is debatable, since the town bylaw may be read as having incorporated the definition of “date of issuance” set out in the DEP regulation, 310 Code Mass. Regs. § 10.04 (1997). However, it is not necessary to determine whether the commission is bound by the definition of “date of issuance” in the DEP regulation, because the record is clear that the commission itself has identified the date it issued its decision as October 9, 2003, which is more than twenty-one days after September 16.
11.
Contrast, e.g., G. L. c. 40A, § 9 (failure of special permit granting author
12.
Given this conclusion, it is not necessary for us to reach the question, discussed at some length in the decisions of the Superior Court judge and the Appeals Court, whether the town bylaw is more stringent or protective than the act. We express no opinion on this point. However, we do agree with the Appeals Court’s concern about the commission’s vague and general reference to the town bylaw, and that court’s observation that “if a town conservation commission simply refers to a by-law without providing any indication that it actually relied on it or how it did so, any comparison of the statute and the by-law to determine which is more protective is rendered difficult or impossible. A town’s by-law may contain some exceptionally protective provisions, and a commission’s general reference to the by-law in its decision, without elaboration, would allow it to insulate the decision from scrutiny.” Cf. Massachusetts Inst. of Tech. v. Department of Pub. Utils., 425 Mass. 856, 867-874 (1997) (failure of Department of Public Utilities to make necessary findings and explain reasons for decision makes judicial review of rate decision impossible); Planning Bd. of Springfield v. Board of Appeals of Springfield, 355 Mass. 460, 462 (1969) (decision of board of appeals granting variance cannot stand unless board makes specific findings that each statutory requirement is met).
13.
The judgment of the Superior Court also included a declaration that the plaintiffs’ notice of intent “has been constructively granted,” as well as an order that the commission violated the requirements of G. L. c. 30A, § 11A lh (the State open meeting law), and was required to comply with that statute at future meetings. For reasons discussed supra, the declaration of rights is in error. The order concerning the open meeting law is also erroneous, since G. L. c. 30A, § 11A 1h, does not apply to local governmental bodies such as the commission.