Spangler v. Green

Mr. Justice Campbell

delivered the opinion of the court.

The objection interposed by the appellees to the jurisdiction of this court to entertain the appeal must first be disposed of before considering the assignments of error. Section 1, page 118 of the Session Laws of 1891, provides that no appeal to the supreme court shall lie to review the final judgment of any inferior court unless the judgment exceeds $2,500, exclusive of costs ; provided this limitation shall not apply where the matter in controversy relates to a franchise or freehold, or where a construction of the state or federal constitution is necessary to a determination of the case.

The proceeding to enforce a mechanic’s lien does not involve a freehold. McCandless v. Green, 20 Colo. 519. To warrant the assumption of jurisdiction, the amount of the judgment in a ease like the one at bar must be determined *508by the amount of the judgment in favor of each lien claimant, and not the aggregate amount of the several judgments; and. as neither of the several judgments here amounts to 12,500, jurisdiction on this ground does not attach. Keystone M. Co. v. Gallagher, 5 Colo. 23; Piper v. Jacobson, 98 Ill. 389; Farwell et al. v. Becker et al., 129 Ill. 261; Aultman & Taylor Co. et al. v. Weir et al., 134 Ill. 137; Bank v. Stout, 113 U. S. 684.

Evidently, therefore, the only ground, if any, which invokes the jurisdiction of this court to review this judgment and decree must be one of the constitutional questions referred to. The appellant claims that the court below must necessarily have based its judgment upon the construction given by it to section 11 of article 2 of our state constitution, prohibiting all laws impairing the obligation of contracts, and laws retrospective in their operation, and section 10 of article 1 of the federal constitution, relating to the same matters ; or rather that its judgment can be upheld onty by giving to the amendments of 1889 to the mechanic’s lien act of 1883 a retrospective operation, which necessarily violates the constitutional provisions mentioned.

After a careful examination of the record, we are satisfied that the judgment of the district court is wrong, and for its only support must rest upon the ruling made to the effect that the rights of the parties to this controversy are to be measured by the amendments of 1889.

The rights of the appellees in this case accrued under contracts made before the passage of these amendments, and if their contract rights were materially changed to their injury by the later law, the former, and not the later, law must govern. We are not unmindful of the doctrine that in mere remedies there can be no vested right; but where, under the guise of giving a new or different remedy, substantial rights themselves are infringed, these constitutional provisions are violated.

There can be no pretense that The Chicago Lumber Co. in filing its lien statement, or in the procedure to enforce its *509lien, has complied with the law of 1888 ; and while Ackroyd & Co. evidently supposed that their rights were to be measured by the amendmeuts of 1889, still they substantially complied with the old law of 1883 in the proceedings necessary to enforce their claim. It needs no argument to show that the amendments of 1889 materially affected both the rights of, and remedies against, the owner of a building, as they existed under the prior act of 1883. A mere reading of these different provisions will manifest the truth of this statement. The later provisions added to the burden of the owner; took from him certain rights of payment to the contractor, which, under the prior law, he might make with safety to himself, before a subcontractor claiming a lien had filed his notice of his intention to assert the same; and attached thereto certain penalties from which he was theretofore exempt, by preserving to the subcontractor his lien, although he neglect to file notice within the time fixed by statute, excepting from said lien the property of the owner only to the extent of such payments, if any, as the owner has made to the contractor after the expiration of the time fixed for the subcontractor to file his lien statement or notice.

This ruling of the district court, and the entire theory upon which it proceeded, were fundamentally wrong, and were in direct contravention of the provisions of the constitution which forbid retrospective legislation and the passage of laws impairing the obligation of contracts. Necessarily, therefore, to determine this case requires us to construe these provisions of the constitution. Having jurisdiction upon this ground, the same attaches as to all other matters necessary to a complete determination of the cause. Trimble v. The People, 19 Colo. 187.

The assignments of error, in the main common to the two suits, relied upon in argument, are:

First. That the plaintiffs fail to aver in their complaint that at the. time of filing their notice of intention to claim a lien there was something due from the owner to the principal contractor, which averment is said to be necessary in such an action.

*510Conceding this contention to be good, we think the absence from the complaint of an averment to this effect was not prejudicial to the appellant for the reason that the error, if any, was cured by her answering to the complaint after the demurrer was overruled and by the admission therein, as well as in open court, that at such time there was something due from her to the principal contractors on the building contract. This sufficiently disposes of the objection urged to the insufficiency of the complaint in this respect.

Second. The principal objection raised by the appellant is as to the ruling by the trial court that the law of 1889, and not that of 1883, was applicable to this controversy. In so doing, it must be apparent that the constitutional right of appellant to have her contract enforced under the law in existence at the time the contract was made, and not the law in effect when suit was brought, was infringed. The ruling directly was that the law, as to the conditions giving the right to the lien, in force when the suit to establish the lien was filed, — and not the law in effect when the contracts, from which all rights and remedies spring, were made,— governs the case. This decision must, in the nature of things, be founded upon the constitutional right of the legislature, under the provisions of the constitution involved, to pass such retrospective acts. This point, which is decisive of the controversy, was made below throughout the trial, was decided against the appellant, has been assigned by her as error, and is argued by her counsel; and it is necessary to determine it in this case.

An objection interposed by the appellees, which, if resolved in their favor, will, it is contended, require an affirmance of the judgment, notwithstanding we have determined that this court has jurisdiction to review the case, is that, conceding, for the sake of argument, that the court erred in refusing to permit the appellant, when the offer was first made by her, to introduce evidence that under her contract with Woodbury & Co. she had paid them all that was due and owing by her except about 11,200 before the filing of *511the lien statements by the appellees, — in which payment, under the law of 1883, she would be protected as against any claim of appellees, — yet as she claims that all the evidence was not returned in the bill of exceptions, the presumption in favor of the findings and decree is that at some other time during the trial such error was cured by the admission of proper evidence tending to negative such payments, upon which the findings and decision of the court were made; or that the appellant’s offer was subsequently renewed by her, and permission given by the court to prove her case, with the result that her proof thus introduced was held insufficient by the court to maintain her claim of payment:

It is true that the bill of exceptions does not contain an express statement that all the evidence introduced at the trial has been certified up, but at the close of the evidence offered in behalf of The Chicago Lumber Co. the statement is that “ thereupon said Chicago Lumber Co. rested its testimony,” and at the close of Ackroyd & Co.’s case it is “ Ackroyd & Co. here rested their testimony,” and at the close of appellant’s case the statement is “ defendant Jane Spangler here closed her testimony.” These' expressions are equivalent to that usually found in a bill of exceptions to the effect that all of the testimony taken was preserved. Ironwood Store Co. v. Harrison, 75 Mich. 197; Hitchcock v. Burgett, 38 Mich. 501.

It is sufficiently apparent, therefore, that the decree of the court, in so far as it relates to the question, and to the time, of payment by the appellant to the principal contractor, rests upon an entire' absence of the offered testimony of appellant to the effect that she had in the matter of payments complied with the law of 1883, except, as she herself admitted, as to the sum of about f1,200; and from this it follows that this ruling of the court deprived the appellant of her constitutional right to have the terms of her contract enforced and the obligations thereof determined by the law as it was when the contract was made.

*512The decree of the court below, resting upon an erroneous theory, is reversed, and the cause remanded with instructions for further proceedings in accordance with this opinion.

Reversed.