By Court,
This action was commenced on May 30, 1873, by the defendant in error (plaintiff in the district court) against the plaintiff in error (defendant in the district court) to recover the sum of four hundred and twenty dollars, three- months rent claimed to be due on the first day of May, 1873, on a certain lease attached to and made a part of the petition. The answer of the plaintiff in error was a plea in bar, in which it was alleged that the defendant in error had theretofore sued the plaintiff in error in said district court, in “an action for the same debt as in the declaration alleged, and such proceedings were had thereupon in that action that the defendant in error afterward by the judgment of the court recovered against the plaintiffs in error two hundred and seventy-five dollars for said debt, * * * and the said judgment still remains in force.” On the trial of the case at bar, verdict was given the defendant in error for the sum of-, and judgment rendered on the verdict by the court.
The evidence on this trial, in the district court, showed that the case at bar, and the action and judgment plead in estoppel were founded on the same lease; the lease in each instance being made a part of the petition. That the following provisions among others were contained in the lease, viz: This lease commences to run on to-day, the seventeenth day of June, A. D. 1872, and expires on the first day of May, A. d. 1873, with the proviso, etc. The said Bath & Brother (of the plaintiffs in error) agree to pay as rent for all the property herein described, the sum of one hundred
The evidence also showed, that the action in which the judgment plead in estoppel was recovered, was commenced on the thirty-first day of January, 1873, or three months before the time stipulated in the lease for the same to expire, that the said action was brought to recover for the whole time that the lease by its terms was to run, namely, from June 17, 1872, to May 1, 1873, ten and one half months, and that the judge before whom the case was tried, being called upon to construe the lease, instructed the jury: “That it was the intention of the parties thereto that the rent mentioned therein should be due and payable monthly in advance, and that under the terms of said lease the rent became due on the seventeenth day of each month. That the jury could only find for the rent that had become due at the time of the commencement of the suit.”
The judge, in the case at bar, instructed the jury that “there is no evidence submitted in the trial of this cause to show that the claim upon which the plaintiff sues has ever been adjudicated. The jury will,' therefore, find for the plaintiff and assess his damage at such amount as the jury find him entitled to under the evidence.” * * And the judge, on motion of the plaintiffs in error, refused to give the following instructions, to wit: “That the debt sued upon by the plaintiff had been adjudicated as alleged in the plaintiff’s answer and shown by the proof on the trial, and that the plaintiff was for that reason not entitled to recover in this action.
The giving of said instructions and refusal to give the instructions requested by the plaintiff in error, are assigned as error. "We cannot see how the previous action and recovery can be considered a bar in this action. The construction put upon the lease by the district court in each instance we consider proper, and correct. It is true that
Judgment of the district court affirmed.