School District v. Hayne

ObtoN, J.

The defendant, in his answer, sets up substantially, that by reason of the failure of the plaintiff to make the monthly payments stipulated in the contract, and the nonperformance of the contract by the plaintiff in this respect, he was unable to continue the work; and that accordingly he rescinded the contract and abandoned work under it, and thereafter the work that was done was so done without and regardless of the contract.

The jury found, as a question of fact, that the plaintiff did so fail to pay and perform, and that the defendant was thereby hindered and delayed in his work, and suffered damages in the sum of $519, which was deducted, in the rendition of the judgment, from the damages allowed the plaintiff.

"Whether the contract was in fact so rescinded, and the work abandoned, on account of such nonperformance by the plaintiff, as claimed by the defendant in his answer, were very material questions in the case, to be passed upon by the jury before they could properly answer the sixth interrogatory, as to whether the further prosecution of the work was within and under the contract or outside and irrespective of it. On this question of rescission and abandonment, the jury were instructed as follows: “ You will ascertain from the evidence *514in this case, whether the contract was rescinded or abandoned by the consent of both parties. That contract cannot be rescinded except by mutual consent of both parties. It cannot be rescinded by one. A refusal to go on by one, is simply a breach of the contract, for which he is liable in damages; but if both parties agree to lay the contract aside, to consider it ended, it is competent for them to do so; and unless such action is taken by both parties, the contract • continues in force.” The words here italicised show clearly the objectionable features of the instructions. This language is substantially repeated in other parts of the charge; and the fourth special finding of fact was, that there had not been an abandonment of the contract by the plaintiff and defendant. The natural meaning of the language of these instructions is, that to constitute a rescission or an abandonment of the contract, there must have been an express agreement of the parties, and an express consent of both parties at the time; and that one party alone could not take such action as would, in law, constitute a rescission of the contract, under any circumstances; and that the consent of a party to the rescission of a contract cannot be implied or inferred from facts and circumstances, but must be expressed.

The jury must have so understood the instructions, and made their fourth special finding accordingly.

These instructions were most clearly erroneous, and evidently misled the jury to the prejudice of the defendant.

It may be abstractly true, as a general rule, that, as a contract can be made only by the consent of all the contracting parties, it can be rescinded only by the consent of all; and yet such consent need not be expressed by an agreement to rescind in any case; and when a party for any sufficient cause rescinds or abandons the contract, the consent of the other party will be implied or presumed, as he might have well anticipated and expected such rescission and abandonment by reason of his own default. A party may rescind the contract *515when tbe other party has done anything, or omitted to do something, which renders him unable to perform it; and when one party fails or refuses to perform his part of the contract, or disables himself from performing it, the other party may'treat the contract as rescinded; and the purpose of rescinding need not be expressly declared by the one party, in order to give the other party the right of consenting and so rescinding. 2 Parsons on Con., 675, 678; 2 Chitty on Con., 1092, and references in note. The failure or refusal to make payments according to the terms of an executory contract, by one party, will give the other party a right to rescind the contract, or treat it as rescinded. Cort v. The Ambergate, Nottingham, etc., R. W. Co., 6 Eng. Law and Eq., 230. If the act of one party be such as necessarily to prevent the other from performing on his part according to the terms of his agreement, the contract may be considered as rescinded; and when a party was prevented from performance within the stipulated time, by the omission of the other, and subsequently performed the work agreed upon, he need not. bring his action upon the contract, but may resort to the guantum meruit to obtain his indemnity (Dubois v. Delaware & Hudson Canal Co., 4 Wend., 285); and such prevention need not be physical or forced. 6 Eng. Law and Eq., supra. “ If a party to a contract be delinquent in the advancement of funds, the other party may take advantage of the omission by declaring the contract at an end.” Shaw v. The Turnpike, 3 Penn., 445. A party may rescind the contract by reason of the nonperformance of its stipulations by the other party, as in the sale of personal property, where the property proves to be different from that contracted for (Woodle et al. v. Whitney, 23 Wis., 55); as in the sale of land, when the title is defective (Taft v. Kessel, 16 Wis., 273); or by reason of failure to perform by the vendee (Minert v. Emerick, 6 Wis., 355); or, when the obligations of the parties to an executory contract are mutual, either party may rescind for nonperform-*516anee by the other, without the consent o£ the other party. Bradley et al. v. Denton, 3 Wis., 557.

In the light of these authorities, and all others upon the question of both the right and the fact of the rescission of contracts, the instructions, in application to the facts of this case, were not only wrong as given, but failed to give the law applicable to such a case.

By the Court. — The judgment of the circuit court is reversed, and the cause remanded for a new trial.

RyaN, O. J., took no part.