Welch v. Mischke

NIXON, P. J.

This was a suit on a promissory note for the principal sum of $549.32, executed by defendant (Mischke) to plaintiff (Welch) for the purchase price of a stave saw and appurtenances, the plaintiff retaining a vendor’s lien on said machinery in the language usually employed in the creation of such liens. Plaintiff prayed for judgment on the note in the sum of $724.40 (principal and interest), for the enforcement of the lien and for the sale of the property to satisfy said judgment and costs.

Defendant, for answer, admitted the execution of the note, but set up as an affirmative defense that according to the terms of a new contract between plaintiff and defendant, made after the execution of the note, defendant was relieved from the payment of the note by the manufacture and sale to plaintiff of 500,000 white oak staves, including those already made by defendant for plaintiff after the execution of the note but before the making of the second contract, and by the return of the machinery to the plaintiff. Defendant pleaded an offer to surrender the machinery, and a demand for the note, alleging his compliance with the terms of said second contract. Defendant also pleaded a counterclaim in the sum of $343 as a balance due him on account of staves sold plaintiff, alleging that he had sold plaintiff 514,500 staves and had been paid for but 490,000.

Plaintiff’s reply was a general denial and a plea of lack of consideration to support the alleged second contract.

The lien feature was eliminated from the case and the cause was tried as a suit on a promissory note, with defendant urging his affirmative defense. The jury found for the defendant on the note and for plaintiff on the counterclaim. Plaintiff has appealed.

The evidence shows that on April 15, 1902, the defendant executed his promissory note for $549.32 as the purchase price of a stave saw and appurtenances, the. *732plaintiff retaining a vendor’s lien on said machinery. Before the execution of this- note, however, plaintiff wrote a letter to defendant stating that plaintiff would sell the machinery to defendant and that he (plaintiff) would “contract to take 500,000 No. 1 white oak staves, to be 13-16 of an inch thick when green so they will measure 3-4 of an inch when dry, 34 inches long, and to average 4 1-2 inches wide after all defects are measured out so they will run this width after being smooth jointed at the finishing plant, and pay you $12.50 per 1000 on cars at Sligo or any station near there on the Prisco line. If staves do not run this wide you are to put in enough extra to make it up; if they run wider we to allow for them. In other words, you are to furnish us 4500 inches of clear timber for every 1000 staves, no staves to' be put in less than three 'inches wide. . . . Will agree to let you pay for machinery in staves, you leaving back $1 on every 1000 made, you to agree to make not less than 30,000 per month on an average after getting started. Will advance you on each month’s cut $7 per 1000. ... On each car loaded out will advance you $3 more per 1000, and balance as soon as car is unloaded and counted out.” After plaintiff’s signature, defendant wrote, “I accept the above proposition.”

By letter of October 3, 1903, from plaintiff to defendant, it appears that plaintiff had allowed defendant $13 per 1000 instead of $12.50 for all staves shipped up to that time, and in this letter plaintiff agreed to increase it to $14 per 1000.

By letter dated September 12, 1904, from plaintiff to defendant, it appears that defendant had been to St. Louis to see plaintiff and that a new contract had there been made. The reference to such contract' in this letter is as follows: “In regard to making staves,, when you were here I told you if you would make 500,-000, I would deliver the note back to you and take the machinery off your hands, which I consider very fair *733and which I stand ready to do when you cut this many staves, and in case you quit cutting the staves, I shall expect you to pay the note with interest and keep the machinery. If you do this you are at liberty to cut staves for anyone you want to. It’s up to you what is best to do.”

Defendant testified: “Q. Mr. Mischke, when you were in St. Louis you say that you had an agreement with Mr. Welch that if you would make 500,000 staves the note would he surrendered to you. Now I will ask you if that agreement was to include the staves already made? A. That is what I understood.”

By letter dated August 27, 1901, from plaintiff to defendant, the following appears.: “When you were here in St. Louis I agreed to take the machinery back, provided you could cut 500,000 No, 1 staves, and since you were here you have made very little effort to get out the staves, and I will say to you that unless you cut the 500,000 staves, I shall expect you to pay for the machinery. If you do not cut staves faster, I shall have to send the notes over for collection. You say you are after 320 acres of timber, and if you get it it ought to make the 500,000 staves. In regard to sending you more money, T want to hear from you as to what you expect to do, and if you want to do the right thing, I will do everything that I agreed to, to help you out.”

T. H. Wiseman for the plaintiff testified that he and plaintiff manufacture staves together and that it is his business to go around and look after the factories and inspect the stock.. That he was present in St. Louis in 1901 when defendant was there to see plaintiff; that defendant “wanted to have his note returned — the note he had given for the machinery — and Mr. Welch told defendant he would not return it, but he said, ‘If you will get me 500,000 No. 1, 31 inch staves, and deliver them to me on the yard at Dillard, I will pay you the price I am now paying you for them and surrender your note.’ We were to take back the machinery.”

*734Was there sufficient evidence of a consideration for the second contract — that is, the contract made while defendant was in St. Louis in 1904, referred to in the letter of September 12, 1904 to authorize the .trial court to refuse plaintiff’s peremptory instruction and submit the case to the jury? In plaintiff’s letter to defendant, dated September 12, 1904, we find that plaintiff has agreed to surrender defendant’s note — not on payment of the principal sum with interest, in a lump sum, or at the rate of $1 withheld on every 1000 staves furnished —biit on condition that defendant furnish 500,000 staves; and that, under this agreement, when plaintiff surrendered the note, defendant should surrender the machinery. Here is a different situation.- Defendant on his part agrees to get out the staves the same as before, but also to surrender the machinery. This was a loss. Defendant testified that he contracted these staves at $12.50 per 1,000 “and they were paying at that time $24 to $26.” Defendant received $13 per 1000 for the first three carloads and $14 per 1000 for the remainder. Having to surrender the nxachinex’y after making 500,000 staves meaxxt that he was paying ten to twelve dollars per thoixsand staves for the use of the machinery. Plaintiff on his part agreed to surreixder the note, and take back the xnachixxery, somethixxg he was not required to do under the first contract. It is obvious that the secoxxd contract was supported by a sufficient consideration. Indeed, the very substitution of the new contract for the old was a sufficient consideration. As said in Peters & Reed Pottery Co. v. Folckemer, 131 Mo. App. l. c. 106, 110 S. W. 598, “There is no doubt of the right of the parties to make a xxewagreement. The fact of its taking the place of the old, was a sufficient consideration.” Again, in Scriba v. Neely, 130 Mo. App. l. c. 261, 109 S. W. 845: “In bilateral contracts the promise of each one of the parties is a sufficient consideration for the promise of another. . . . Consideration means not so much that one *735party is profited as that the other abandons some legal right in the present, or limits his legal freedom of action in the future as an inducement for the act of promise for the first. It does not matter whether the party accepting the consideration has any actual benefit thereby or not — it is enough that he accepts it and that the party giving it does thereby undertake some burden or lose something which in contemplation of law may be of value.” Further, “A valid contract made in substitution for one of a prior date, annuls the obligation of the former, and of itself furnishes a sufficient consideration for the release of the first agreement.” [Sanders’ Pressed Brick Co. v. Barr, 76 Mo. App. l. c. 386 and cases cited; Lancaster v. Elliot, 55 Mo. App. l. c. 255.] Moreover, where a modified contract is acted upon by the parties, the original contract is abandoned, which of itself will uphold the modification thereof, so far as consideration is concerned. [Cannon-Weiner Co. v. Boswell, 117 Mo. App. l. c. 476, 93 S. W. 355.]

Appellant contends that his peremptory instruction should have been given for the reason that the burden of proving t'he discharge of the indebtedness was upon the defendant- — the party alleging the discharge — and that there was no-«evidence showing that defendant furnished 500,000 No. 1 staves according to his contract.

During the early part of the trial nisi counsel agreed “that defendant shipped to plaintiff 447,560 No. 1 staves and 86,070 No. 2 staves and the same were accepted by plaintiff; this agreement means the above number by count and not by measurement.” Defendant testified that plaintiff while at defendants mill told defendant he would take two No. 2 staves for one No. 1. Taking defendant’s view of the second contract — that the 500,000 staves meant 500,000 including those already shipped up to that time — and adding- to 447,560. one-half of 86,070, we find only the equivalent of 490,-590 No. 1 staves. It will be remembered that in the first contract (of February 3, 1902) the agreement was that *736defendant was to furnish plaintiff 4500 inches of clear timber for every 1000 staves; that is, the staves were to average 4 1-2 inches in width, no staves to be less than three inches wide. Defendant testified that in 1902 and 1903 “and several times” plaintiff measured staves at defendant’s mill; that plaintiff would measure a large number and then figure the average width; that he told defendant at those times that “900 staves would scale out a thousand,” meaning that the average width of the staves was ten per cent more than 4 1-2 inches; that he agreed to plaintiff’s average and thought it was fair; that he never receivéd any money from plaintiff for this excess or any statement of the amount due him for excess and that he never sent plaintiff a statement for the same or kept any book account of the same; that he spoke to plaintiff about it several times, asking him to settle, but that plaintiff always said he would fix that up later and always put it off; that “he promised he would settle up after a while, after we got done, you know, then he would settle up and pay me.” “Mr. Welch always put it off, and that was the understanding, he was to pay me later on, when we got done.” And defendant stated that he figured ten per cent as the excess according to what he and plaintiff had agreed on, and that he always expected to receive pay for this excess.

We think there was enough evidence on this issue to authorize the submission of the case to the jury. The case was submitted — as to this issue — on instructions substantially as follows: For the plaintiff the jury was told that if defendant delivered staves to plaintiff during the years 1902, 1903, 1904, 1905, 1906 and 1907, and plaintiff accepted them and paid defendant the contract price, and according to defendant’s own count, then it was the duty of the defendant, if he desired to make a claim against the plaintiff on account of the staves running wider than the average width (4 1-2 inches) provided in the contract, to notify plaintiff within a rea*737sonable time after tbe delivery of tbe staves that the staves so delivered ran wider than the width called for in the contract and to demand payment for such excess v ithin a reasonable time, and in the absence of such notice and demand the jury should find for the plaintiff on defendant’s counterclaim. The court of its own motion gave this instruction: ' “If you find from the evidence that the staves furnished by Mischke to plaintiff did not average more than 4 1-2 inches in width, then you will find for the plaintiff on defendant’s counterclaim.” For the defendant the jury was told that if they found that under the second agreement defendant did make and deliver to plaintiff 500,000 No. 1 staves of the average width of 4 1-2 inches, they would find for the defend: ant as to the surrender of the note. The following verdicts were returned:

“We, the jury, find the issues on the counterclaim for the plaintiff, that he does not owe the defendant anything on account of the staves averaging over 4 1-2 inches.”
“We, the jury, find the issues for the defendant on the note that plaintiff agreed to take the machinery in payment of same if defendant delivered to him 500,000 staves under the contract and that defendant complied with said contract and that the note is satisfied thereby.”

Appellant contends that these two verdicts are inconsistent one with the other. The trouble with appellant’s contention is that it stands upon the untrue hypothesis that the instructions given concerning the recovery of the excccs as set up in the counterclaim should apply generally to all the issues and limit the jury so that they could not add whatever excess they found there was on the 490,590 staves actually furnished in order to make out the 500,000 staves, the number defendant agreed to furnish before his note would be surrendered. These instructions referred only to the *738counterclaim and this is made clear in the instructions themselves. The instruction given by the court of its own motion simply told the jury that if the staves did not average more than 4 1-2 inches in width they should find for the plaintiff on defendant’s counterclaim. Of course this was correct. The plaintiff’s instruction goes entirely on the question of whether notice and demand were seasonably given and made, and not on the general question as to whether excess should be allowed in any event. Indeed, it assumes as its basis that excess was allowable and then requires a finding that reasonable notice was given and demand made before a recovery could be had therefor. The résult was that the jury found for the plaintiff on defendant’s counterclaim, and then, finding that defendant had furnished only the equivalent of 490,590 No. 1 staves, according to count, looked to the evidence which tended to show that the staves would scale 1000 for every 900 and that the average width was over 4 1-2 inches, and, to the original contract, which clearly defined the intention of the parties to be that defendant was to furnish 4500 inches of clear timber for every 1000 staves with the express provision that if they run wider plaintiff was to allow for the excess, and the jury, no doubt, took this provision as evidence of the intention of the parties. They found enough, according to measurement, to make up the necessary 500,000 No. 1 staves. Having done so, the verdict was found for the defendant on the note, and rightly so. The fact that the two verdicts may have been inconsistent as claimed by appellant is not necessarily conclusive that error was committed against the appellant. There was evidence tending to show that defendant was entitled to the excess' claimed in his counterclaim and any error the jury may have committed in that behalf is not for our consideration as the defendant took no appeal. Moreoever, it is not sufficient for the appellant to show that the findings of the jury are incon*739sistent, but he must go farther and show that material error was thereby committed.

Appellant complaiiis of the action of the trial court in admitting the evidence as to the terms of the agreement between plaintiff and defendant to the effect that two No. 2 staves would be taken as one No. 1 and paid for accordingly. This objection is based on the ground that there is nothing- in the pleadings to support it. It is alleged in the pleadings that defendant agreed to and did furnish a certain number of staves- under and by virtue of their contract, and that contract, as modified and acted upon by both parties, was tha,t two No. 2 staves would be accepted in place of one No. 1 and the evidence tended to show that they were so paid for. The jury has found that this was the contract. The meaning of this language is to be interpreted bv the understanding of the parties as shown by their actions and dealings. Where parties to a contract have given its terms a particular construction, such construction will generally be adopted by the court in giving effect to its provisions. .[9 Cyc. 588; The St. Joseph Union Depot Co. v. Railway, 131 Mo. 291, 31 S. W. 908; Meyer v. Christopher, 176 Mo. 580, 75 S. W. 750.] We therefore find that no error was committed in the admission of this evidence.

A thorough examination of this record convinces us that the result reached by the jury was entirely fair and just to both parties, that the judgment was for the right party, and should be affirmed. It is accordingly so ordered.

All concur.