Action by certain property owners to cancel special taxbills issued to defendant Plummer as contractor in payment for the construction of a district sewer in the city of Springfield. The defendants in their answer alleged compliance with the law and ordinances of the city and asked for a foreclosure of the lien of the taxbills issued against the property of the plaintiffs. The trial court found for the defendants except that he reduced the amount of each bill
The questions upon which plaintiffs rely for a reversal of the judgment are:
First: That the contract for putting in the sewer was let at a price in excess of the preliminary estimate of the city engineer.
Second: That material changes were made in the construction of the sewer after the contract was let., by the addition of laterals not called for in the contract and by omitting other parts that were called for in the contract.
Third: That there was a change of grade after the contract was made.
Fourth: That there was a double charge for excavating by charging for both dirt and rock in the same part of the ditch.
Fifth: That the court erred in excluding certain testimony offered by the plaintiffs.
As to the first point, we do not think the contention is sustained by the testimony. The estimate of the engineer itemized the work and the cost. He estimated that it would require 1705 lineal feet of eight inch pipe including Ys, branches and joints, two lamp holes, two flush tanks, four manholes, etc. The excavation was classified and a separate estimate put upon all excavations including back filling; six feet and under eight feet being in one class; eight feet and under ten feet in another; ten feet and under twelve feet in another; twelve feet and under fourteen feet in another; fourteen feet and under sixteen feet in another; sixteen feet and under eighteen feet in another; and on each of these a separate estimate was made. There was an estimate of 2800 lineal feet for a rock trench and 3400 lineal feet of flint excavation. These with some other items all of which were specified made a total of $3189.15. The contract also specified same items and was at a less price for each item than the estimate of the engi
The basis for the contention that the contract price exceeded the estimate of the engineer is not based upon the fact that the contract was let at a higher price on any item of the contract but is based upon the fact that after the work was completed and the work actually done was computed that by the addition of laterals, the length of the ditch was increased and also that the amount of flint excavation was increased over the estimate; and that being true, the total cost, instead of being as estimated $3189.15, amounted to $4247.35.
In the very nature of things it was impossible for the, engineer to ascertain before the ditch was actually dug how much flint and how much rock would be encountered in excavating the ditch, and for that réason, the parties could not understand that his estimate as to thé total cost should control over the estimate as’ per the items making up the total expenditure and as the contract was let at a price below the estimate on each item and, all the items going to make up the total having been specified, it would certainly be unreasonable to hold that because the engineer underestimated the amount of rock and flint to be found under the ground that the contractor could not recover for the work actually done. We are cited by appellants’ counsel to the case of G-ratz v. City of Kirkwood,. 165 Mo. App. 196, 145 S. W. 874, decided by the St. Louis Court of Appeals as authority for the- position that the contract or the total: amount of the taxbills could not exceed themstimate of the engineer as to the .total cost of the construction óf the: sewer, but a careful examination of that, case will show‘that instead, of; being an authority for that position, it is authority for. the position that the
The second contention is that material changes were made after the contract was let, by shortening one of the ditches called for in the contract and by adding laterals at other places not called for in the contract. The evidence shows that this was done and that by doing so, the total length of the ditches dug and pipes laid was greater than that stated in the engineer’s preliminary estimate. But we do not think under the evidence in this case that these changes were fatal to the validity of the taxbills. It is the duty of the city in constructing any district sewer to place it in such a way that it will accommodate the property owners of the district. In this case,, an abstract of title was procured for the purpose of determining who the owners were and size of the lots and their location in order that the sewer might be so placed as to meet the demand for service from all the lots. It developed that some mistakes had been made in the abstracts and that when they went to do the work it became necessary to add some laterals in order to reach some parts of the district and it also was found unnecessary to dig one of the. ditches the full length estimated by the engineer. The addition of the laterals was necessary in order to furnish proper, drainage for the entire district and one ditch was shortened because it was found to be unnecessary to dig it as long as estimated and since the basis of this contract was the items of work, we think it was entirely right and proper for these changes to have been made and was in fact the duty of the city to make them so that the district could be properly accommodated and without unnecessary cost.
•It is next contended that plaintiffs offered to show that one lot about 50 by 100 feet lying within the district had been omitted in computing the area of the district and that bv reason thereof, the cost to these plaintiffs had been increased to that extent. When this offer was made the court excluded it upon objection of defendant. Afterward, however,'the same testimony was admitted without objection and it was further shown that certain other territory not lying in the district was included in computing the area so that the area as computed was not less than the actual area and the charge against the plaintiffs’ property was not thereby increased. The testimony was competent and should have been admitted but since it is shown that the area of the district as computed by the engineer was not less than the actual area, plaintiffs were not injured by this omission and cannot now complain.
Plaintiffs also offered to prove that since the trial had begun, parties had made excavations of the ditch at certain points and that at the points at which these excavations were made, the side walls of the ditch showed that there was at these points but a small proportion of flint excavation. This testimony was excluded. We think the exclusion of this testimony was error. It ought to have been admitted and have gone to the jury or the court sitting as a jury for what it was worth. But if this testimony had been admitted, the trier of the facts might- still have found that there was no mistake in the totals returned as flint excavation for
As to the contention that there was a double charge for both dirt and rock on that portion of the ditch in which rock was found a very close question is presented which rests largely upon a construction of the contract itself. The items for excavating as stated in the contract run in the following form: “The price per lineal foot for all excavation and back filling: six feet or over and under eight feet, $.30; . . . eight feet or over and under ten feet, $.25; . . . ten feet or over and under twelve feet, $.40; . . . twelve feet or over and under fourteen feet, $.45; . . . sixteen feet or over and under eighteen feet, $.60; price per lineal foot for rock trench per foot in depth, $.25. ’ ’ The testimony showed that in sewer contracts similar to this it had been the uniform practice for years in counting the cost of excavation to count it at the price mentioned the entire depth of the ditch and then if there was rock in the ditch to add that to it and that was done in this case and one of the items making up the total charges in this case is 1000 lineal feet of rock trench at $.25 per lineal foot, $250. The evidence also showed that rock was found at the bottom of the ditch but at what sections, or how deep the excavations were at places where the rock was found, does not appear, but in any event the most shallow excavation anywhere was in the class of six feet or over and under eight feet, and for that class $.30 per lineal foot was charged so that if in that section the dirt was five feet thick and then one foot of rock was to be excavated below the dirt and we should compute the five feet of dirt at the dirt price, we would
■ • . In view of this situation we are of the opinion that it was competent to show by oral, testimony .the practice in vogue in the city of Springfield to allow the $.25 per lineal foot for rock excavation in addition to the amount which would have been charged had the dirt extended to the bottom and as the evidence clearly shows that to have been the practice for years prior to the execution of this contract and the city engineer having recognized it and reported it in that way in his computation of the cost of the sewer, the trial court ,was entirely right in making the computation upon that basis. In making a contract of this character, both the city and the' contractor ought to be careful to see that the contract should express in language too plear to be misunderstood exactly what the parties intend, but after the contract has been executed, the work honestly performed and the question arises in the court as to what compensation the contractor may recover, we must apply a reasonable and common sense rule, to the construction .of the contract with the end in view of trying to ascertain in a fair-and jiist manner what the parties really meant when-., the ¡ contract was executed. , ’ ■
Some contention is made here also that even if the taxbills are held to be valid, the amount of.recovery
Judgment affirmed.