Ryus v. Weeks-Betts Hardware Co.

ROBERTSON, P. J.

Upon the date therein designated, plaintiff and defendant entered into the following contract:

“Prosperity, Mo., May 10, 1906.
“W. H. Ryus sells to Weeks-Betts Hardware Company one 16 H. P. Gasoline all complete engine for $200. Payments are to be made as follows: Cash down twenty-five dollars and the balance in ten days provided the said Weeks-Betts Hardware Company accept the engine, if they do not accept the engine and pay for it in that time, said Weeks-Betts Hardware Company agree to deliver the engine to Webb City, Missouri, at the place that W. H. Ryus specifies. Then the twenty-five is to be forfeited to W. H. Ryus, in the case they do not accept the engine and pay for same. There is to be no expenses charged W. H. Ryus for drayage or repairs on said engine.
“In case that we do not take the engine we agree to deliver the engine in as good condition as it now is.
“Signed, .
Weeks-Betts Hardware Company,
By C. E. Weeks.
W. H. Ryus.”

*34Soon thereafter a representative of the defendant went to the place where said engine was stored and removed it to their place of business at Prosperity, near Webb City. A few days after removing the engine defendant’s representative went to plaintiffV home in Webb City and stated to plaintiff that the head of the engine was broken and wanted to know where he could get a head for it. Plaintiff says he advised him where he could get it; that the representative of defendant expressed doubt as to whether he could run the engine and plaintiff told him if he did not want the engine to deliver it to plaintiff on his lot in Webb City. Defendant’s representative testified that he and plaintiff agreed that plaintiff should order and pay for this new head, but the plaintiff strenuously denies this. About a year after this contract was entered into the plaintiff sent a man to defendant’s place of business to secure a burner for a gasoline engine and some packing and the defendant gave him. a burner and packing from this particular engine, for which the defendant thereafter rendered to plaintiff a bill, which he paid. The representative of defendant who transacted this business was a witness for defendant in the trial of the case and testified that the engine was complete at the time the defendant entered into this contract and received the engine. There is some testimony which has led counsel for defendant to insist that the burner was not with the engine at the time defendant received it, but, if that is material, we are of the opinion that the contention is. not sustained by the testimony. Also, the court, under a declaration of law given at defendant’s request, • found against it on that point. - Defendant’s .representative testified that “the only in: complete thing about the engine was the burner which Mr. Ryus came and got.” “Q. That was not on the engine when you got it? A. No, sir.” The plaintiff testified that this burner was not sent for until long after the defendant received the engine, and the defend*35ant’s bill for it, which was offered in evidence and undenied by defendant, is dated May 13, 1907; hence, we think the defendant is clearly in error on this contention and that the trial court properly so found.

It will be observed that the contract provides that, “There is to be no expenses charged W. H. Ryus for drayage or repairs on said engine.” Therefore, the only complaint under this contract which the defendant could urge against the transaction would be that the engine was incomplete. The testimony discloses beyond controversy that it was complete and, under the contract, which was written at the dictation of defendant’s representative, there was no duty devolving upon the plaintiff other than to deliver a complete engine. The contract anticipates the necessity for repairs.

The defendant made its fight in the trial court upon the theory that plaintiff had agreed to furnish a new head, that this constituted a modification of the original contract, and if thereafter the engine was sold to defendant and defendant notified plaintiff it would not accept the engine and plaintiff refused to designate the place in Webb City where defendant should' deliver the engine, that then the plaintiff could not recover.

Plaintiff charges in his petition the execution of the contract, which is copied therein, and then alleges “that the defendant retained said engine and did not return same to plaintiff at Webb City as it agreed to do in case it did not accept it.” And further that the defendant paid the twenty-five dollars-mentioned .in the contract and “that there is still due owing and unpaid to plaintiff under the terms of said contract above set forth the sum of $175.” And, further, “that under the terms of said agreement made and entered into as above stated between plaintiff and defendant and by reason of the failure of the defendant to pay the plain*36tiff the balance dne thereon, there is due owing and unpaid to plaintiff the sum of $1750’

The defendant answered by denying “each and every material allegation had and made in plaintiff’s petition, except such as- shall be hereinafter admitted.” Defendant then admits the execution of the contract, the payment of twenty-five dollars, and alleges that it took the engine to its place of business in Prosperity and attempted to operate the same when it found the engine was not complete in that the head was broken, and that the defendant at the special instance and request of the plaintiff ordered a new head at a cost of $15.75, but that the plaintiff had failed and refused to pay; that after trying the engine with the new head defendant w;as not able to operate the same and notified the plaintiff and offered to return it to him, but that the plaintiff refused to accept it or designate any place in Webb City for its delivery, and prayed judgment against plaintiff for $15.75.

To this answer the plaintiff filed a reply and the trial proceeded before the court without a jury and resulted in a judgment in favor of the plaintiff for the full amount sued for, from which judgment the defendant has appealed.

We think the petition would have been better had it alleged that the defendant accepted the engine within the ten days but we are of the opinion that there is sufficient alleged from which the inference may be drawn that the defendant did accept the engine within the ten days, because it is alleged that it retained the engine and did not return it to the plaintiff as it agreed to do in case it did not accept .it, which is equivalent to charging that there was an acceptance. The testimony abundantly discloses, and the court so found, that the defendant did accept the engine within the ten days and that it should be held liable therefor.

The main insistence on the part of the defendant now is that the plaintiff neither alleged nor proved the *37acceptance of the engine within the ten days and that until that fact was alleged and proven no liability was imposed upon the defendant; but, as we have stated, we are of the opinion that the petition is sufficient in that regard and the testimony of the plaintiff is ample to justify the judgment in this ease on that theory.

The defendant does not stand in a very consistent attitude before this court, insisting that there was no acceptance, when we consider the contract and the position assumed by the defendant in the trial of the case, where its sole contention was that there had been a substituted or modified contract wherein the plaintiff had agreed to supply the new head, which was resolved by the trial court upon the facts against it. The defendant also in the trial court claimed that the engine was not complete by reason of the absence of the gas burner and requested and obtained a declaration of law upon that assumed fact, which the court found against it. The defendant is now here contending that there was not testimony to disclose that it accepted the engine, but we must hold that if it did not as a matter of fact accept it, it did as a matter of law, and that the plaintiff has sufficiently alleged facts from which that inference must be drawn.

The judgment of the trial court is affirmed.

Farrington and Sturgis, J. J., concur.