Hibbard v. Talmage

Maxwell, J.

This action was brought by the plaintiff to foreclose a mechanic’s lien on a building and lot in the city of Kearney. The petition was filed- in February, 1889. In March following the defendant filed an answer, in which he pleads payment of the plaintiff’s claim, and sets out certain receipts and checks to sustain his plea. He also pleads that he sustained damages in a large amount by reason of the failure of the plaintiff to complete his contract at the time specified.

To this answer the plaintiff filed a reply, in which he al*148leges that $150 of the amount paid by the defendant to the plaintiff, as set forth in his answer, was for extra work on the building, performed by the plaintiff at the defendant’s request, and that there is still due plaintiff on said contract the sum claimed in the petition. He also alleges in substance that the delay in the completion of the building was caused by such extra work, etc.

The defendant filed a motion to strike out of the reply the claim for extra work as being redundant. This motion was overruled, to which exceptions were taken, and the ruling is now assigned for error.

The court properly overruled the motion to strike out the matter referred to. It devolved on the plaintiff, where the receipt of the money was admitted, to show how it was to be applied. If all the money paid by the defendant to the plaintiff was not for work and labor performed under the original contract, the plaintiff should state in the reply for.what purpose it was received. This is not a new cause of action. No lien is claimed for the extra work, and the plaintiff contends that it has been paid for. It was proper also in the reply to allege that the delay was caused by the extra work, in effect at the instance of the defendant, and that therefore the plaintiff was not liable for the delay.

Second — The testimony tends to show that the plaintiff entered into a contract to erect the building in question for the sum of $3,200; and a quantity of refuse building material then on the ground, of the value of $620, seems to have been included in the contract but not named therein. The extra work charged for consists in the taking down and rebuilding of a brick arch over one of the doorways of the building.

The court below found in favor of the plaintiff, and rendered judgment in his favor for the sum of $240, and decreed a foreclosure of the lien. This judgment is supported by a preponderance of the evidence, and we see no error in the record. It would subserve no good purpose *149to review the testimony at length. The judgment is right and is

Affirmed.

The other judges concur.