Harris Patriot Healthcare Solutions, LLC v. United States

OPINION AND ORDER

GEORGE W. MILLER, Judge.

In this post-award bid protest, plaintiff Harris Patriot Healthcare Solutions, LLC (“Harris”) filed its complaint on October 18, 2010, protesting defendant’s failure to immediately comply with the automatic stay imposed by the Competition in Contracting Act (“CICA”), 31 U.S.C. § 3553(d) (2006). Plaintiff sought to enjoin the Department of the Interior (“DOI”) from permitting defendant-intervenor Stanley Associates, Inc. (“Stanley”) to continue work on an awarded task order. Compl. ¶ 1 (docket entry 1, Oct. 18, 2010). One day after this action was commenced, DOI implemented the CICA stay by issuing a stop-work order to Stanley. Defendant filed a motion to dismiss plaintiffs complaint on October 27, 2010 on mootness grounds. Defendant’s Motion to Dismiss and Opposition to Plaintiffs Application for a Temporary Restraining Order and Motion for a Preliminary Injunction (docket entry 30, Oct. 27, 2010) (“Def.’s Mot.”). After defendant filed its motion to dismiss, DOI decided to take corrective action in response to Harris’s protest filed October 4, 2010 at the Government Accountability Office (“GAO”). As a result, GAO dismissed Harris’s protest as academic on November 2, 2010.

At this time, the parties tentatively agreed that defendant’s actions had rendered plaintiffs action moot. During discussions on filing a stipulation of dismissal, defendant clarified that, during the pendency of the corrective action, DOI would not permit Stanley to perform work under the protested task order; however, DOI would not forfeit the ability to have Stanley or another company perform work covered by the task order using a different contractual vehicle in order “to meet its immediate and short term needs.” Transcript of November 12, 2010 Hearing at 8 (docket entry 49, filed Nov. 16, 2010) (“Nov. 12 Tr.”). Unsatisfied that DOI had reserved the right to have work covered by the task order performed in the future to meet “immediate and necessary needs,” id. at 14, Harris announced that it contended the case was not moot. See Transcript of October 29, 2010 Status Conference at 12-13 (docket entry 40, filed Nov. 4, 2010) (“Oct. 29 Tr.”); Plaintiffs Response to Defendant and Defendant-Intervenor’s Motions to Dismiss and Supplemental Memorandum in Support of Motion for Preliminary Injunction at 1 (docket entry 46, Nov. 10, 2010) (“PL’s Resp.”).

On November 3, 2010, defendant filed a renewed motion to dismiss, again contending that the action was moot. Defendant’s Renewed Motion to Dismiss (docket entry 34) (“Def.’s Renewed Mot.”). Stanley also filed a motion to dismiss on mootness and ripeness grounds. Stanley’s Motion to Dismiss (docket entries 35 & 36, Nov. 3, 2010) (“Stanley’s *588Mot.”). The parties participated in a hearing on these motions on November 12, 2010. For the reasons set forth below, defendant’s renewed motion to dismiss and defendant intervenor’s motion to dismiss are GRANTED.1

I. Background

A. The CONNECT System Follow-On Contract

Harris was awarded a contract in 2008 by the Acquisition Services Directorate (“AQD”), a part of the DOI, for the development and maintenance of the CONNECT software system.2 Compl. ¶ 6; PL’s Mem. at 3. The CONNECT software system is an inter-agency federal initiative linking the Government, healthcare providers, and hospitals in the development of “an open source software solution that supports health information exchange,” and creation of “standards and governance to make sure that health information exchanges are compatible with other exchanges being set up throughout the country.” CONNECT Community Portal, What is CONNECT?, http.V/www.connect opensource.org/about/whalHS-CONNECT (rev.2010).

Harris’s contract was set to expire in March 2010, but DOI issued a sole-source bridge contract extending Harris’s contract until September 24, 2010. Declaration of Tony Galluscio ¶ 8 (docket entry 10, Oct. 18, 2010) (“Galluscio Deck”). This bridge contract permitted Hams to continue work on the CONNECT system pending a competition for the CONNECT follow-on contract. Sole-Source Bridge Request for Quote (“RFQ”) at 1, attached as Ex. 1 to PL’s Mem.; Galluscio Decl. ¶ 9; Def.’s Mot. at 2.3 DOI issued a request for quotation on August 11, 2010, “to continue the ongoing development of CONNECT.” Follow-On RFQ Statement of Work (“SOW”) at 1, attached as Ex. 4 to PL’s Mem.4 The task order award was to be made on a best value basis to an awardee that would be responsible for the continued “development of the CONNECT solution to adhere to standards and to meet the business needs of the Federal partners for health information exchanges.” Follow-On RFQ SOW at 3.

B. Award to Stanley and Harris’s Request for Debriefing

DOI received two quotations, one from Harris and one from Stanley. Award Notice at 1, attached as Ex. 5 to PL’s Mem. Although Harris’s quote was nearly [* * *] less than Stanley’s, “Harris’s technical quote *589was not rated as highly as Stanley Associates’ technical quote.” Basis for Award Decision at 2, attached as Ex. 10 to Pl.’s Mem. Thus, DOI determined that Stanley’s proposal offered the best value to the Government “due to its higher technical [rating] and slightly higher price” and awarded the task order to Stanley on September 24, 2010. Id. Harris requested a debriefing. In response, the DOI sent Harris a two-page letter on October 4, explaining that Harris was not selected despite its lower price because of Stanley’s superior technical rating.5 Basis for Award Decision at 1-2.

C. Transition Work

Meanwhile, on the day of the award to Stanley, which was also the day Harris’s bridge contract was set to expire, DOI advised Harris that it wished to “extend [Harris’s bridge contract] for 60 days for transition” to Stanley. Administrative Record (“AR”) Tab 1 at 1 (docket entry 29, Oct. 27, 2010) (E-mail from Shelita Saint-Louis of AQD to Harris (Sept. 24, 2010, 7:26 PM)); Id. at 2-8 (Bridge Transition SOW); Gallus-eio Deck ¶ 15. DOI provided Harris with a statement of work that charged Harris with, “developing an effective transition plan” to Stanley and continuing operation of the CONNECT system during the transition period. AR Tab 1 at 2-3.

DOI required Harris to submit a transition plan proposal within two working days, or “no later than Monday, September 27 at 3:00 PM EST.” AR Tab 1 at 1. On September 27, Harris wrote to the agency requesting a three-day extension, until “close of business Friday October 01, 2010.” AR Tab 2 at 9 (Letter from Vance Rowland of Harris to Shelita Saint-Louis of AQD (Sept. 27, 2010)). The contracting officer granted Harris an extension until September 28, but explained that no further extension would be granted because DOI wanted to use Fiscal Year 2010 money to fund the transition contract.6 AR Tab 2 at 10 (E-mail from Shelita Saint — Louis of AQD to Harris (Sept. 27, 2010, 4:19 PM)).

On September 28, Harris sent another letter to the contracting officer stating: “We only ask consideration for our business processes to allow us to submit our response with appropriate levels of review and approval as indicated in our letter yesterday.” AR Tab 3 at 12 (Letter from Vance Rowland of Harris to Shelita Saint-Louis of AQD at 1 (Sept. 28, 2010)). Harris received no “further communication from DOI regarding the transition work.” Galluseio Decl. ¶ 20. Defendant asserts that DOI was unable to extend Harris’s deadline because DOI did not receive a proposal from Harris in time to fund the contract with FY 2010 money. Def.’s Mot. at 3.

D. DOI’s Request That Harris Return Government Furnished Equipment

Because DOI did not receive a transition quote, it declined to offer Harris a contract for transition work. Def.’s Mot. at 3. DOI then orally and thereafter in writing requested that Harris return to DOI all government furnished equipment (“GFE”) and government furnished information (“GFI”) in its possession pursuant to the 2008 contract and the bridge contract. Email from Shelita Saint-Louis of AQD to Harris (Oct. 15, 2010, 5:29 PM), attached as Ex. 12 to Pl.’s Mem. On October 18, 2010, plaintiff sought “clarification and guidance” regarding the means and timing for the return of GFE and GFI. Letter from Vance Rowland of Harris to Shelita Saint-Louis of AQD at 1-2 (Oct. 18, 2010), attached as Ex. 13 to Ph’s Mem.

Plaintiff expressed particular concern about returning certain GFE and GFI that plaintiff believed [* * *]. Galluseio Deck ¶¶ 32-36. Plaintiffs task order quote [* * *] based on Harris’s already possessing this GFE and GFI. Harris claims it [* * *] if it is required to transfer the GFE and GFI back to the Government. Id. ¶37. Hands asserts that returning the GFE and GFI to *590the Government would alter the status quo and disadvantage Harris competitively in any reevaluation of the quotations. See Nov. 12 Tr. at 68-69 (“[* * *]”).

As of the heai’ing on November 12, 2010, DOI continued to request that Harris return certain GFE and GFI to the Government. See id; E-mail from Shelita Saint-Louis of AQD to Harris ¶¶ 1, 3 (Oct. 28, 2010 1:21 PM), attached as Ex. 16 to Pl.’s Resp. (requesting that Harris return “[* * *] ■ • • to” the Government’s designated representative, “Mr. [* * *] of the MITRE Corporation.”). However, according to Harris, DOI had not, as of the date of the hearing, required it to return the “[* * *],” and this GFE/GFI “remains in Harrises] possession.” Pl.’s Resp. at 23-24.

E. Harris’s GAO Protest

On October 4, 2010, the day Harris received DOI’s response to its request for a debriefing, Harris filed a protest of the award to Stanley at the GAO. See Harris Patriot Healthcare Solutions, LLC, B-404136.1 (Oct. 4, 2010); Galluscio Deel. ¶21. Plaintiff contends that on October 8, 2010, counsel for DOI asserted that by failing to submit a timely proposal for the transition work, “Harris had walked off the job and was not willing to perform.” Pl.’s Mem. at 8. Plaintiff also contends that because of this perceived failure on Harris’s part, upon the filing of its protest at GAO, DOI stated that it “intended to move forward with the override” of the automatic stay provided for by 31 U.S.C. § 3553(d). Id. In response, Harris submitted a letter to DOI that same day stating that “[tjhere should be no confusion. Harris is willing and able to continue to perform the CONNECT contract services as it has for the past 2 $ years.” AR Tab 9 at 34.

F. DOI’s Initial Plan to Override the CICA Stay

DOI received notice of Harris’s GAO protest of the award of the follow-on CONNECT contract to Stanley on the same day it was filed. AR Tab 5 at 18. Following discussions with HHS personnel at the Office of the National Coordinator (“ONC”) for Health Information Technology, DOI initially determined that it would seek to override the CICA stay pursuant to § 3553(d)(3)(C), on the ground that an override was “in the best interests of the United States.” AR Tab 10 at 40-46 (Initial Draft of Determination and Finding (“D & F”)).7 In its draft D & F, DOI described in detail how a stay of performance would disrupt and delay the goals of the CONNECT program.8

During the time DOI continued to draft its D & F, Stanley continued to perform under the follow-on CONNECT contract as the awardee. AR Tabs 12-14; Nov. 12 Tr. at 5. By October 15, 2010, the lawyers at DOI appeared ready to “sign off’ on the proposed D & F so that the head of the procuring activity could execute the final D & F. AR Tab 12 at 78. However, DOI postponed promulgation of the final D & F until the following Monday, October 18, 2010, in order to permit final revisions. AR Tab 12 at 81.

*591 G. Harris’s Lawsuit in this Court

1. Initial Status Conference and DOI’s Assurance of Compliance with the CICA Stay

On October 18, 2010, plaintiff filed the pending action.9 Compl. ¶ 1. Plaintiff alleged that what it believed to be DOFs decision to override the automatic stay was arbitrary and capricious. Id. ¶41. Plaintiff argued that the DOI had the viable alternative of extending Harris’s bridge contract and failed to consider that alternative to overriding the stay. Id. ¶ 43. Further, plaintiff claimed that DOI could not “show that any significant adverse consequences would arise if it respected the CICA stay,” that DOI “failed to meaningfully evaluate the risks and costs to the agency if GAO were to sustain Harrises] protest,” and the adverse impact of an override “on competition and the integrity of the procurement system.” Id. ¶¶ 42, 44, 45. Finally, plaintiff asserted that it was “ready, willing, and able” to perform if the agency determined that a bridge contract with Harris was a suitable alternative to overriding the CICA stay during the pendency of Harris’s GAO protest. Transcript of October 19, 2010 Status Conference at 13 (docket entry 26, filed Oct. 21, 2010) (“Oct. 19 Tr.”).

On October 19, 2010, the Court conducted an initial status conference with the parties. At the start of the status conference, counsel for defendant announced that DOI had that day issued a stop-work order to Stanley in recognition of the CICA stay.10 Oct. 19 Tr. at 6, 20-22; see also AR Tab 14 at 126 (signed and acknowledged stop-work order). However, DOI had not yet determined what course of action it would take with respect to the possibility of a potential future “partial override” of the CICA stay to permit work on what counsel described as certain very specific tasks critical to maintaining the CONNECT network. Oct. 19 Tr. at 18; see also id. at 23-24 (“[A] partial override specifically would allow Stanley as the awardee to perform only those specific tasks under the task order that were immediately necessary ... for the continuity of service.”) (statement of counsel for defendant).

By the time defendant responded to plaintiffs motion for interlocutory relief on October 27, DOI had decided that it did not “intend to override the stay at all.” Def.’s Mot. at 10 (emphasis in original); Declaration of Shelita Saint-Louis ¶ 7 (Oct. 27, 2010) (“Saint-Louis Deck”), attached as Ex. A. to Def.’s Mot. (“After consulting with ONC regarding its immediate needs, ONC now advises that it does not need to override the automatic stay and will not need to do so during the pendency of Harris’[s] GAO protest. In light of HHS’[s] re-evaluation of its needs, DOI does not intend to override the automatic CICA stay prior to the completion of the GAO protest.”) (emphasis added).

2. Corrective Action in Response to Harris’s GAO Protest

Subsequently, on October 28, 2010, DOI submitted a letter to GAO indicating that it intended to take corrective action in response to the allegations made by Harris in its protest. Letter from DOI to Lynn H. Gibson, General Counsel, GAO at 2 (Oct. 28, 2010), attached as Ex. B to Def.’s Renewed Mot. DOI outlined the steps it intended to take as corrective action and stated that “during the pendency of the corrective action, the stay of performance of the [CONNECT] Solution 2010 contract shall remain in place.” Letter from DOI to Lynn H. Gibson, General Counsel, GAO at 2 (Oct. 29, 2010) (“Revised Corrective Action Letter”), attached as Ex. C to Def.’s Renewed Mot. In light of DOI’s representation that it intended to take corrective action, GAO dismissed Harris’s protest as academic on November 2, 2010. Harris Patriot Healthcare Solutions, LLC, B-404136.1, Decision (Nov. *5922, 2010), attached as Ex. D to Def.’s Renewed Mot.

DOI has affirmed that it has no present intent to have Stanley or any other company perform work covered by the follow-on CONNECT contract during the pendency of DOFs corrective action. Nov. 12 Tr. at 8-9. However, in response to plaintiffs inquiry, DOI stated that it could not give a binding assurance that it would not permit Stanley or some other entity to perform work covered by the follow-on CONNECT contract using some alternative contractual vehicle in order to “meet its immediate and short term needs.” Nov. Tr. at 8 (“[DOI does] not intend to utilize Stanley via a separate contractual vehicle during the pendency of th[e] corrective action period, but ... the Agency could not, and was not willing to relinquish its rights to utilize any available means to meet immediate needs that might arise during the pendency of th[e] corrective action.”); see also Oct. 29 Tr. at 16. In the absence of such an assurance, plaintiff contended, the ease was not moot. Pl.’s Resp. at 15.

II. The Court No Longer Possesses Jurisdiction Over Plaintiffs Action Because Plaintiffs Claims Are Either Moot or Unripe

This court possesses jurisdiction to review an agency’s override of the CICA stay pursuant to 28 U.S.C. § 1491(b)(2) because the decision whether to override the CICA stay is agency action “in connection with a procurement.” RAMCOR Servs. Grp., Inc. v. United States, 185 F.3d 1286, 1289 (Fed.Cir.1999) (“Where an agency’s actions under a statute so clearly affect the award and performance of a contract, this court has little difficulty concluding that that statute has a ‘connection with a procurement.’”). However, the Court’s review of the override decision is limited and does not involve review of the underlying protest before the GAO. Reilly’s Wholesale Produce v. United States, 73 Fed.Cl. 705, 710 (2006).

Defendant and defendant-intervenor move to dismiss plaintiffs action for lack of jurisdiction pursuant to Rule 12(b)(1) of the Rules of the Court of Federal Claims (“RCFC”) because of three events that they claim have rendered this action moot: (1) DOI’s issuance of a stop-work order to Stanley on October 19, 2010; (2) GAO’s dismissal of Harris’s protest as academic because of DOI’s decision to undertake corrective action; and (3) DOI’s representation that the stay of performance of the follow-on CONNECT contract will remain in effect “during the pendency of the corrective action.” Def.’s Renewed Mot. at 8; Stanley’s Mot. at 3; Defendant’s Reply in Support of Its Renewed Motion to Dismiss at 6 (docket entry 51, Nov. 19, 2010) (“Def.’s Reply”); see also Revised Corrective Action Letter at 2. The burden rests with defendant to demonstrate that an action is moot. Friends of the Earth, Inc. v. Laidlaw Envtl. Servs., (TOC) Inc., 528 U.S. 167, 190-92, 120 S.Ct. 693, 145 L.Ed.2d 610 (2000) (contrasting mootness with standing and holding that defendant bears the burden to demonstrate mootness because of the potential for “sunk costs” to the judicial system in eases where the court possessed jurisdiction initially only to have the case subsequently dismissed as moot); see also Alexander v. United States, 52 Fed.Cl. 710, 713 (2002); Nat’l Med. Enters., Inc. v. United States, 11 Cl.Ct. 329, 332 (1986).

A. Plaintiff Is Not Entitled to an Order Requiring DOI to Maintain the “Status Quo" After Dismissal of Plaintiffs GAO Protest

1. Plaintiff’s Original Request for Relief is Now Moot

The mootness doctrine is one of several justiciability doctrines originating from the “case or controversy” requirement of Article III of the Constitution.11 “A case *593is moot when the issues presented are no longer ‘live’ or the parties lack a legally cognizable interest in the outcome.” NEC Corp. v. United States, 151 F.3d 1361, 1369 (Fed.Cir.1998) (quoting Powell v. McCormack, 395 U.S. 486, 496, 89 S.Ct. 1944, 23 L.Ed.2d 491 (1969)). Additionally, while “subsequent acts may moot a request for particular relief or a count, the constitutional requirement of a case or controversy may be supplied by the availability of other relief.” Intrepid v. Pollock, 907 F.2d 1125, 1131 (Fed.Cir.1990).

Although defendant’s burden is a “heavy” one, Cnty. of L.A. v. Davis, 440 U.S. 625, 631, 99 S.Ct. 1379, 59 L.Ed.2d 642 (1979), the Government has met its burden in this case. There is no doubt that the equitable relief originally requested by plaintiff is moot. Plaintiffs complaint sought to enjoin DOI from permitting Stanley to continue performance of the awarded task order and a declaration that “DOFs override decision is invalid and has no effect.” Compl. at 13. On October 19, 2010, DOI issued a stop-work order to Stanley, and DOI never made an “override decision.” Thus, there is no override the court could declare invalid or enjoin. See Eskridge Research Corp. v. United States, 92 Fed.Cl. 88, 93-94 (2010).

2. Plaintiff is Not Entitled to an Order Requiring DOI to “Maintain the Status Quo”

After DOI represented that it intended to take corrective action and after GAO dismissed Hams’s protest, plaintiff argued that the Court should require DOI to “maintain the status quo” while the agency undertook corrective action. PL’s Resp. at 17. Relying on dicta from the district court’s decision in Dairy Maid Dairy, Inc. v. United States, 837 F.Supp. 1370 (E.D.Va.1993), plaintiff argued that the Court should order the DOI to “maintain the status quo ... during the time required for compliance with the GAO’s decision.” Pl.’s Resp. at 19 (quoting Dairy Maid, 837 F.Supp. at 1385) (emphasis supplied by plaintiff). However, this argument is based on an overly-broad reading of CICA.

CICA precludes an agency from permitting performance by the awardee “while the protest is pending.” 31 U.S.C. § 3553(d)(3)(B). The CICA stay was intended to prevent an agency from allowing performance of a protested contract during GAO’s consideration of a protest because such performance could well place the protester at a disadvantage. Pl.’s Resp. at 18; see also H. REP. NO. 98-1157 at 24 (1984); Dairy Maid, 837 F.Supp. at 1377 (observing that “Congress enacted CICA, and incorporated the stay provisions here at issue, in an attempt to provide effective and meaningful review of procurement challenges before the protested procurement ]” becomes a fait ac-compli ) (citing Ameron Inc. v. U.S. Army Corps of Eng’rs, 787 F.2d 875, 878 (3d Cir.1986)). When DOI announced it intended to take corrective action and GAO dismissed Harris’s protest as academic, Revised Corrective Action Letter at 2; Harris Patriot Healthcare Solutions, LLC, B-404136.1, Decision (Nov. 2, 2010), that dismissal removed a prerequisite to CICA’s automatic stay — the pendency of a GAO protest.

Given the fact that dismissal of the GAO protest ended the automatic stay of performance of the follow-on CONNECT contract, it is unclear what relief plaintiff would be entitled to in order to “maintain the status quo.” The relief that plaintiff sought in its protest at GAO was a re-evaluation of DOI’s award decision taking into account plaintiffs allegations.12 But DOI is now taking corrective *594action in response to plaintiffs GAO protest, agreeing to investigate the grounds on which plaintiff based its protest. Moreover, DOI has committed to maintain the stay of performance of the follow-on CONNECT contract during the pendency of the corrective action. Revised Corrective Action Letter at 2. Therefore, DOI has provided Harris with the relief it would have been entitled to if the CICA stay had remained in effect.13

3. The Court Declines to Order the Agency to Permit Harris to Retain the GFE/GFI

Next, plaintiff argues that its action is not moot because Harris seeks an order precluding DOI from requiring the return of the GFE and GFI. Pl.’s Resp. at 29-30. Plaintiff contends that requiring the return of GFE/GFI would [* * *]. Id. at 24-25. Further, “requiring the return of the GFE/GFI while the corrective action is on-going is illogical and an unnecessary drain on the public fisc at a time of great economic strain.” Id. at 25; see also Nov. 12 Tr. at 86 (stating that prohibiting the Government from requiring “the return of the GFE” would “provide frankly all the relief’ plaintiff requires) (statement of counsel for Harris).

Defendant, however, states that Harris’s obligation to return the GFE and GFI is an obligation imposed by the now-expired bridge contract, which incorporated FAR § 52.245-1. Sole-Source Bridge RFQ Ex. B. at 8; Nov. 12 Tr. at 15; see also Def.’s Reply at 9 (“[T]he Government is well within its rights to request the return of its own property for purposes of closing out Harrises] now-expired contract.”) (emphasis in original). That provision, entitled “Government Property,” permits the Government at any time, upon written notice, to “[withdraw authority to use [the] property.” FAR § 52.245 — l(d)(3)(i)(C). Defendant thus argues that it has a contractual right to require the return of the GFE/GFI. Def.’s Reply at 9. The Court agrees.

To the extent that Hams were to conclude in the future that returning the GFE/GFI had unfairly affected DOI’s evaluation of Harris’s proposal, Harris could protest the award decision.14 Finally, although plaintiffs argument regarding the public fisc may turn out to have merit, this Court’s bid protest jurisdiction does not allow the Court to second guess the agency’s discretionary decisions regarding contract management.15 *595See Gov’t Technical Servs. LLC v. United States, 90 Fed.Cl. 522, 527 (2009) (holding that Contract Disputes Act is the “exclusive mechanism” for resolution of disputes regarding contract management.16

4. The Voluntary Cessation Doctrine Is Inapplicable

The agency’s issuance of a stop-work order would not necessarily be enough to moot plaintiffs action because “[i]t is well settled that ‘a defendant’s voluntary cessation of a challenged practice does not deprive a federal court of its power to determine the legality of the practice.’” Friends of the Earth, 528 U.S. at 189, 120 S.Ct. 693 (quoting City of Mesquite v. Aladdin’s Castle, Inc., 455 U.S. 283, 289, 102 S.Ct. 1070, 71 L.Ed.2d 152 (1982)); see also Parents Involved in Cmty. Schools v. Seattle Sch. Dist. No. 1, 551 U.S. 701, 719, 127 S.Ct. 2738, 168 L.Ed.2d 508 (2007); Unisys Corp. v. United States, 90 Fed.Cl. 510, 517 (2009). If a defendant’s voluntary cessation of challenged conduct could always render a case moot, defendant would be “free to return to [its] old ways” and resume the conduct in question once the case was dismissed. Friends of the Earth, 528 U.S. at 189, 120 S.Ct. 693 (quoting City of Mesquite, 455 U.S. at 289 n. 10, 102 S.Ct. 1070). Nonetheless, defendant’s “voluntary cessation” of the challenged practice can render an action moot if defendant “can demonstrate that ‘there is no reasonable expectation that the wrong will be repeated.’ ”16 United States v. W.T. Grant Co., 345 U.S. 629, 633, 73 S.Ct. 894, 97 L.Ed. 1303 (1953) (quoting United States v. Aluminum Co. of Am., 148 F.2d 416, 448 (2d Cir.1945) (L.Hand, J.)).

Again, while “[t]he burden is a heavy one,” id., defendant has adequately shown that there is no reasonable expectation that DOI’s violation of the CICA stay will be repeated because there is no longer any CICA stay in effect. See Nov. 12 Tr. at 30 (“Here there can be no reasonable expectation that the alleged violation, the allegedly wrongful behavior, could be expected to [recur] ... [because] there is no CICA stay to either ignore or to override. The stay no longer exists.”) (statement of counsel for Stanley). Plaintiff overstates the agency’s obligations under CICA when it argues that the ease is not moot because “the risk that the Government will again disrupt the status quo is clear and substantial.” Pl.’s Resp. at 16.

CICA does not preclude every alteration to the status quo; DOI’s obligation under CICA is narrower. In this case, DOI has agreed to re-evaluate the quotations of Stanley and Hams in light of the allegations made in Harris’s GAO protest. And DOI has stated that it intends to investigate each of Harris’s allegations. It has also represented that the stay of performance of the follow-on CONNECT contract will remain in place during the pendency of DOI’s corrective action. Any action the agency may take during or as a result of its corrective action would likely constitute a separate procurement decision that Harris could seek to challenge in an appropriate forum. However, the Government’s voluntary cessation of performance during the pendency of DOI’s corrective action and statements of Government counsel regarding DOI’s lack of any present intention to request that Stanley or any other contractor perform tasks covered by the follow-on CONNECT contract are sufficient to show, with the requisite clarity, that there is no reasonable expectation that DOI’s past violations of CICA will be repeated.

B. Any Challenge to DOFs Conduct in Taking Corrective Action Is Not Ripe For Review

Plaintiff next argues that there remains a live controversy because DOI may be setting *596itself up to be able to allow Stanley to perform tasks covered by the follow-on CONNECT contract through some contracting vehicle other than the follow-on CONNECT contract. See Revised Corrective Action Letter at 2 (confirming “that, during the pendency of the corrective action, the stay of performance of the [CONNECT] Solution 2010 contract shall remain in place.”) (emphasis added). Plaintiff argues that the Court should “enjoin[ ] the Government during the pendency of the corrective action process ... from allowing Stanley to perform tasks covered by the CONNECT Solution 2010 Solicitation ... either under the awarded contract or any other contract.” Pl.’s Resp. at 29-30. Putting aside the presumption of good faith that the Government is afforded when it undertakes corrective action, Chapman Law Firm Co. v. Greenleaf Constr. Co., 490 F.3d 934, 940 (Fed.Cir.2007), plaintiffs theory runs afoul of another justici-ability doctrine: ripeness.

“[T]he ripeness doctrine ... prevents] ... courts, through avoidance of premature adjudication, from entangling themselves in abstract disagreements over administrative policies, and also ... protects] the agencies from judicial interference until an administrative decision has been formalized and its effects felt in a concrete way by the challenging parties.”17 Abbott Labs. v. Gardner, 387 U.S. 136, 148-49, 87 S.Ct. 1507, 18 L.Ed.2d 681 (1967), overruled on other grounds by Califano v. Sanders, 430 U.S. 99, 97 S.Ct. 980, 51 L.Ed.2d 192 (1977). Agency action is ripe for review when it (1) “marks ‘the consummation of the agency’s decisionmaking process,’ i.e., it [is] not ... merely tentative or interlocutory” and (2) it is one that determines “rights or obligations” or is one “from which legal consequences will flow.” NSK Ltd. v. United States, 510 F.3d 1375, 1385 (Fed.Cir.2007) (quoting Bennett v. Spear, 520 U.S. 154, 177, 117 S.Ct. 1154, 137 L.Ed.2d 281 (1997)). This court has recognized in similar contexts that “[a] claim is not ripe where it rests upon contingent future events that may not occur as anticipated, or indeed may not occur at all.” Eskridge, 92 Fed.Cl. at 94 (quoting Tex. Bio- & Agro-Def. Consortium v. United States, 87 Fed.Cl. 798, 804 (2009)); see also Commonwealth Edison Co. v. United States, 56 Fed.Cl. 652, 658 (2003).

Plaintiffs suspicions about DOI’s future actions are simply too speculative to create a ripe controversy. In Madison Services, Inc. v. United States, 90 Fed.Cl. 673, 676 (2009), the plaintiff filed a protest in this court challenging the Federal Emergency Management Agency’s “expressed intention” to follow the recommendation of the GAO in a previous bid protest. The Government moved to dismiss on the ground that the agency had not yet definitively determined whether and how to implement GAO’s recommendation. Id. at 677. After the motion to dismiss had been fully briefed, the Government filed a renewed motion to dismiss informing the court that the underlying procurement had been cancelled. Id.

Like the plaintiff in Madison Services, Harris “cannot avoid dismissal by speculating as to what [DOI] might do.” Id. (emphasis added); see also Forestry Surveys & Data v. United States, 44 Fed.Cl. 485, 492 (1999) (declining to grant relief regarding agency’s potential use of past performance ratings in awarding future contracts because “no action can be maintained regarding future, and at this point speculative, contracts”). As Madison Services further demonstrates, speculation as to what the agency might do cannot give rise to a ripe controversy because the agency can decide to pursue a different course of action, as it did in Madison Services by cancelling the solicitation altogether.

Indeed, plaintiff is arguably in a worse position than the plaintiff in Madison Services because its concern is not only speculative, but also contradicted by Government counsel’s representation that DOI has no present intention of permitting Stanley or any other contractor to perform tasks covered by the follow-on CONNECT contract *597under that contract or any other contractual vehicle. Nov. 12 Tr. at 6-8. If future circumstances lead the DOI to change its mind in order to “meet its immediate and short term needs,” id. at 8, plaintiff may at that point seek to challenge DOI’s action in an appropriate forum. See id. at 25 (“[DOI] would have a right to explain the basis for wanting to utilize Stanley or someone else, and this Court would then have an opportunity to ... review ... that action, and determine its propriety, as well as weigh any harm that Harris would suffer as a result of that usage, and any harm that the government might suffer by being enjoined from using it, and where the public interest lies.”) (statement of counsel for defendant). But until the agency acts in a way that is not “merely tentative or interlocutory,” NSK, Ltd., 510 F.3d at 1385, this court may not adjudicate plaintiffs unripe claims.

C. The Court Declines to Stay Proceedings and Lacks Authority to Retain Jurisdiction Pending Future Developments

Plaintiff alternatively requests that the Court stay proceedings and retain jurisdiction over this action “to ensure that Harris has an opportunity for a bid protest remedy.” Pl.’s Resp. at 31. Plaintiff fears that DOI may elect to contract using a vehicle “arguably insulated from traditional bid protest review, separate and apart from the override issues before this Court.”18 Id.

Although plaintiff may be correct that future action by the DOI could leave it without a forum to hear its bid protest, such an outcome would be the result of the interplay of statutes regulating federal government procurement enacted by Congress at different times. The jurisdictional limitations that might prevent challenges to agency action in this court would remain applicable whether or not proceedings in this case were stayed. Plaintiffs concerns about the limitations Congress has imposed on this Court’s jurisdiction over bid protests do not provide a basis for this Court’s retaining jurisdiction and do not present a “pressing need for [a] stay” of proceedings in this ease. Cherokee Nation of Okla. v. United States, 124 F.3d 1413, 1416 (Fed.Cir.1997).

Moreover, the requirement that the parties be involved in a live dispute — i.e., one that is neither moot nor unripe — is a fundamental prerequisite to the court’s jurisdiction, namely, the requirement of a justiciable controversy. See Massachusetts v. Envtl. Protection Agency, 549 U.S. 497, 516, 127 S.Ct. 1438, 167 L.Ed.2d 248 (2007); see also Prasco, LLC v. Medicis Pharm. Corp., 537 F.3d 1329, 1336 (Fed.Cir.2008) (discussing the Supreme Court’s development of “various more specific but overlapping doctrines rooted in the same Article III inquiry, which must be met for a controversy to be justicia-ble, including standing, ripeness, and a lack of mootness”). Staying the ease while retaining jurisdiction is simply not an option because, having found that plaintiffs claims are either moot or unripe, the Court has no jurisdiction to hear them, and “must dismiss the action.” RCFC 12(h)(3) (emphasis added); see also Chapman Law Firm, 490 F.3d at 939-40 (after a finding that the action was moot, “the Court of Federal Claims should have dismissed the case”).

CONCLUSION

For the foregoing reasons, defendant and defendant-intervenor’s motions to dismiss *598pursuant to RCFC 12(b)(1) are GRANTED. Plaintiffs action is DISMISSED without prejudice on grounds of mootness and because Harris’s claims regarding conduct that may occur during the implementation of corrective action or at some other future time are not ripe for resolution by the Court at this time. The Clerk is directed to enter judgment for defendant consistent with the foregoing.

Some information contained herein may be considered protected information subject to the protective order entered in this action on October 20, 2010 (docket entry 19). This Opinion and Order shall therefore be filed under seal. The parties shall review the opinion to determine whether, in their view, any information should be redacted in accordance with the terms of the protective order prior to publication. The Court FURTHER ORDERS that the parties shall file, by Monday, December 13, 2010, a joint report identifying the information, if any, they contend should be redacted, together with an explanation of the basis for each of their proposed redactions.

IT IS SO ORDERED.

. Along with its complaint, plaintiff filed an application for a temporary restraining order ("TRO”) and motion for preliminary injunction. Application for TRO (docket entry 6, Oct. 18, 2010); Motion for Preliminary Injunction (docket entry 5, Oct. 18, 2010); see also Plaintiff’s Memorandum of Points and Authorities in Support of Plaintiff's Application for TRO and Motion for Preliminary Injunction (docket entry 9, Oct. 18, 2010) ("PL’s Mem.”). At the hearing on defendant and defendant-intervenor's motions to dismiss on November 12, 2010, the Court DENIED plaintiff’s application from the bench because plaintiff had failed to demonstrate a likelihood of success on the merits, and also failed to satisfy the three other criteria for interlocutory relief. See Nov. 12 Tr. at 99; November 12, 2010 Order at 1 (docket entry 47); see also FMC Corp. v. United States, 3 F.3d 424, 427 (Fed.Cir.1993).

. AQD is authorized to conduct procurements for the DOI, as well as various other civilian and military agencies. See Acquisition Services Directorate, About Us, http://www.aqd.nbc.gov/ About/AboutUs.aspx (rev.Nov.2010). The procurement at issue in this case was undertaken on behalf of the Department of Health and Human Services ("HHS”) Office of the National Coordinator ("ONC”) for Health Information Technology, Federal Health Architecture ("FHA") Program Office. Def.’s Mot. at 2 n.l. Following the parties, the Court will refer to the relevant procuring agency as the DOI.

. DOI exercised an option in June 2010, extending the bridge contract to September 19, 2010, Sole-Source Bridge Contract RFQ, Ex. D at 2. DOI extended it again from September 19 through September 24. Id. Ex. Eat 3.

. The Court refers to the task order awarded to Stanley and protested by Harris at the GAO as the "follow-on RFQ” or "follow-on CONNECT contract.” Harris’s bridge contract that existed between March 2010 and September 24, 2010 is referred to as Harris’s "sole-source bridge contract” or more generally as "the bridge contract.” The further bridge contract DOI unsuccessfully attempted to enter into after it awarded the follow-on RFQ to Stanley, discussed further infra, is referred to as the "transition bridge contract.”

. Plaintiff was not actually entitled to a formal "debriefing” because the procurement was conducted under FAR Part 8, which only requires "a brief explanation of the basis for the award decision.” FAR§ 8.405-2(d).

. For the federal government, the fiscal year "begins on October 1 of each year and ends on September 30 of the following year.” 31 U.S.C. § 1102.

. Section 3553(d)(3)(C) provides:

(C) The head of the procuring activity may authorize the performance of the contract (notwithstanding a protest of which the Federal agency has notice under this section)—
(i) upon a written finding that—
(I) performance of the contract is in the best interests of the United States; or
(II) urgent and compelling circumstances that significantly affect interests of the United States will not permit waiting for the decision of the Comptroller General concerning the protest; and
(ii) after the Comptroller General is notified of that finding.

The statute contemplates that after receiving notice of the GAO protest, the agency will "immediately direct the contractor to cease perform-anee under the contract.” 31 U.S.C. § 3553(d)(3)(A)(ii) (emphasis added). Performance may continue only if the responsible head of the procuring activity makes a "written finding” that performance is in the best interest of the United States or of urgent and compelling circumstances "and after the Comptroller General is notified of that finding." id. § 3553(d)(3)(C)(i) & (ii) (emphasis added). DOI, however, knew of the GAO protest on October 4, permitted Stanley to perform under the follow-on CONNECT contract while DOI was drafting its D & F, and did not issue the statutorily required stop-work order until October 19, one day after Harris filed this action.

. [* * *].

. Stanley filed an unopposed motion to intervene on the side of defendant in the case on October 19, 2010 (docket entry 15), which the Court granted. Order at 1 (docket entry 18, Oct. 20, 2010).

. The administrative record filed by defendant provides no explanation for the agency's change of position between October 18, 2010, when it was ready to obtain the requisite signature on the final D & F, and October 19, 2010, when it decided to issue the stop-work order and reevaluate its position.

. The Court of Federal Claims is established under Article I of the Constitution, 28 U.S.C. § 171(a), and is not bound by the "case or controversy” requirement of Article III. Zevalkink v. Brown, 102 F.3d 1236, 1243 (Fed.Cir.1996). This court has, however, applied the Article III justiciability doctrines for prudential reasons. See Anderson v. United States, 344 F.3d 1343, 1350 n. 1 (Fed.Cir.2003) ("The Court of Federal Claims, though an Article I court, applies the same standing requirements enforced by other federal courts created under Article III.”) (internal citations omitted).

. At the GAO, plaintiff alleged that the agency failed to take into account a potential Organizational Conflict of Interest ("OCI”) because a former employee of ONC had since been employed by one of Stanley’s subsidiaries. PL's Mem. at 8. Plaintiff also alleged that that the agency conducted a “flawed evaluation of non-price factors and [made an] unreasonable source selection decision.” Id. In its Corrective Action, DOI has agreed to:

«... undertake a review of the facts and circumstances on which Harris bases its allegations of unfair competitive advantage and unmitigated OCIs to determine whether awardee Stanley could have been afforded an unfair competitive advantage. The contracting officer will then determine what actions, if any, should be taken to address the appearance of impropriety, if any.
*594«... review all evaluations and, as appropriate, ... revise the evaluations of the proposals submitted.
• [make a] new best value determination_
• If Stanley remains the successful offeror, performance of the contract previously awarded will proceed. If a different contractor is selected, Stanley’s contract will be terminated for convenience and a new contract will be awarded.

Revised Corrective Action Letter at 2.

. To the extent that Davy Maid suggests that the court may require DOI to enter into the transition bridge contract with Harris, that decision is contrary to binding precedent of the Federal Circuit and therefore not helpful to plaintiff. See Parcel 49C Ltd. P'ship v. United States, 31 F.3d 1147, 1152-53 (Fed.Cir.1994); C.A.C.I., Inc.-Fed. v. United States, 719 F.2d 1567, 1574-75 (Fed.Cir.1983); see also Durable Metals Prods., Inc. v. United States, 27 Fed.Cl. 472, 476-77 (1993) (”[T]he equitable jurisdiction of this court does not include the authority to award a contract as plaintiff requests.”), aff'd, 11 F.3d 1071 (Fed.Cir.1993) (unpublished table opinion).

. Harris asserted at oral argument that certain statements in the administrative record indicate that DOI has prejudged the claims made by Harris in its GAO protest. Nov. 12 Tr. at 69 (referring to ”statement[s] in the government’s record, where they basically have done an assessment of [plaintiff’s] protest, and concluded that there is no merit.”); see also AR Tab 6 at 23 (E-mail from Anand Basu of ONC to Marc Weisman and Doug Fridsma of ONC (Oct. 5, 2010, 11:50 AM)) ("In no way did [the individual named in Harris’s GAO protest regarding an alleged OCI] have any involvement with the source selection plans for the CONNECT requirement."); id. ("[* * *]"). Any alleged prejudgment could also be protested if DOI’s corrective action ends unfavorably for Harris and if Harris decides to protest DOI’s action.

.Defendant argues, and the administrative record seems to confirm, that the return of the GFE would not drain the public fisc because in the follow-on CONNECT contract, DOI has identified a third-party, not the eventual awardee, to "perform the hosting requirements for which the GFE and GFI is necessary.” Def.’s Reply at 9. Thus, it appears that the GFE and GFI will be transferred to a third party regardless of the result of DOI’s corrective action. Id. at 9 & n.7; see also E-mail from Shelita Saint-Louis of AQD to Harris ¶¶ 1, 3 (Oct. 28, 2010 1:21 PM), attached as Ex. 16 to Pl.’s Resp. (identifying MI-*595TRE Corp. as the "Government’s designated representative” to receive the GFE/GFI).

. Counsel for Harris stated at oral argument that ”[t]he government bears the burden ... of showing that it is absolutely clear that there is no reasonable chance that some disruption to the status quo is not likely to return.” Nov. 12 Tr. at 49 (emphasis added). Harris’s proposed standard of absolute clarity appears to impose an even heavier burden than the standard prescribed by the Supreme Court. Even applying Harris's suggested standard, however, DOI has made a sufficient showing to establish with absolute clarity that there is no reasonable chance that DOI’s past violations of CICA will recur. The voluntary cessation doctrine is therefore inapplicable.

. Unlike mootness, it is plaintiff’s burden to establish ripeness. Morris v. United States, 58 Fed.Cl. 95, 97 (2003) (citing McNutt v. Gen. Motors Acceptance Corp. of Ind., 298 U.S. 178, 189, 56 S.Ct. 780, 80 L.Ed. 1135 (1936)).

. For example, if DOI issued a task order to Stanley valued at $10 million or less, neither GAO nor (arguably) this court would have jurisdiction because of the passage of the Federal Acquisition Streamlining Act of 1994, Pub.L. No. 103-355, 108 Stat. 3243 (1994) (codified as amended at 10 U.S.C. § 2304c(e) and 41 U.S.C. § 253j). See A & D Fire Protection, Inc. v. United States, 72 Fed.Cl. 126 (2006); see also Delex Sys., Inc., B-400321, 2008 CPD ¶ 154, 2008 WL 3112559, at *2 (Comp.Gen. Aug. 5, 2008) (dismissing GAO protest of task order valued under $10 million). But cf. Idea Int'l, Inc. v. United States, 74 Fed.Cl. 129, 137 (2006) ("FASA's prohibition on bid protests does not cover GSA Federal Supply Schedule orders.”); Matthew Chow, Tara L. Ward, Amy Bryan & Theodore Richard, Bench Memorandum: Court of Federal Claims Task Order Bid Protest lurisdiction and Expectation Damages, 38 Pub Cont LJ. 975, 998-99, 1010-11 (2009) (arguing that the Court of Federal Claims could potentially exercise jurisdiction over a protest of a task order "valued in excess of $10 million” based on an alleged breach of the implied contract to consider proposals fairly and honestly).